PROGRAMME MANAGEMENT AND BUSINESS PLANNING
|
|
|
- Barbra Carpenter
- 10 years ago
- Views:
Transcription
1 PROGRAMME MANAGEMENT AND BUSINESS PLANNING This paper describes what lessons were learned from the programme management and business planning which was done to support the operation of the Help Scheme through its various phases. 1
2 Introduction The Scheme Agreement 1 published in May 2007 set out the basis under which the BBC would provide assistance to eligible people in accordance with the Government s policy to operate a Help Scheme. The Scheme was part of the wider switchover programme coordinated by Digital UK. This paper will describe how the Help Scheme was planned and run from a programme management and business planning perspective. 1 Scheme Agreement. As subsequently revised: 2
3 What did we learn? 1 Strategic vision clear Management of the programme was aided by a clear and unambiguous strategic vision no one left behind which helped shape a culture based on risk aversion and quality of delivery. These principles filtered down from initial strategic intent into all areas of delivery, and aided the programme management function in ensuring that the programme outcomes were delivered on time and to the highest quality. 2 The critical importance of sponsorship The Help Scheme enjoyed strong sponsorship from the outset both from Government, and the BBC Trust and Executive. This was sustained throughout by very active management of these relationships, and close consultation and engagement. 3 Clear governance Re-enforcing this was the early groundwork done in clarifying governance and reporting, which was by no means straightforward in a complex, multi-faceted programme involving many partners and contractors. 4 Strong detailed design of management reporting, and robust communication channels The effort involved at the outset in designing and developing robust reporting systems was time well spent; these were refined periodically but stood the test of time. Based on these reporting systems, and the well-defined governance processes, communication channels were clear, which made for effective decision making. 5 Open and transparent culture Last but not least the Help Scheme programme benefited from a management culture that encouraged openness of emerging issues, a consultative approach to decision making, but at the same time short lines of command. This, together with an early warning approach to problems through formal and informal networks, all acted to encourage an atmosphere of mutual support and trust. 3
4 Programme and business management laying down the foundation From the outset in 2007 a small team of 2-3 people working to the Chief Executive was set up to create the programme structure. Its main activities are summarised in Chart 1 overleaf. It worked principally with three other groups of stakeholder: BBC executive management and the Trust, mainly through the Project Board in reporting on progress and issues on a monthly basis Digital switchover partners, DCMS and Digital UK, in the overall switchover programme The DSHS operations team and the main contractor, CES, in coordinating initiatives and receiving regular progress updates on key projects. 4
5 Governance reporting Chart 1 5
6 The operational phases of the Help Scheme How then did programme management evolve over the duration of the Help Scheme? The best way to see this is in the context of the five phases of the Help Scheme (see Chart 2 below). These phases were: Start up; Scale up; Review; Complete; and Close. Each phase reflected the overriding operational priorities at that time and involved quite different people, processes, reporting and risk management. We will therefore consider the approach taken to programme management in each phase. Chart 2 6
7 Context and business priorities Start up The essential aspects of setting up the Help Scheme programme were tackled in the first few weeks from May 2007 onwards, and established a framework which proved to be durable and adaptable. Rather than being wedded to strict programme management methodologies per se, it was deliberately more fluid and pragmatic in design, but aligned to the principles and best practice set out by the OGC 2. At the outset, some of the essential building blocks for a successful programme were in place but there was a lot still to be done in a fairly short period of time (with the Copeland pilot just months away): The purpose, scope and vision: The purpose and scope were quite well defined in the Scheme Agreement; the vision was also clear: that no one should be left behind Sponsorship: There was active support for this at the highest levels; the Scheme Agreement was agreed by the Secretary of State for Culture, Media and Sport and the BBC. Operationally, BBC Executive Board members were the Senior Responsible Officers (SROs) for respectively DSO overall and the Help Scheme specifically Business case and budget: The business case was based on the overall cost benefit analysis of switchover carried out by Government. The overall Help Scheme budget was agreed, as was the contract for Digital UK to supply services. The process for approving spend would be aligned with BBC Finance Committee requirements Benefits management: This was included in the Government cost benefit analysis of switchover The leadership: The top management was in place; the leadership team was starting to be recruited Other resources: These were still to be defined and would need to be supplemented by specialist consultants as required, especially in the short term Design and delivery: Only a prototype design existed at the start. This would emerge through the competitive dialogue process to select a contractor to run the Scheme 2 For example, Managing Successful Programmes, Office of Government Commerce,
8 The detailed governance: This was being set up and agreed. The reporting content and structure to stakeholders was being developed The timetable: This was known and, crucially, unchangeable (determined by the wider switchover programme) The outcomes: The overall vision was broadly clear but the success measures were still to be agreed Risk management: The key risks and issues were yet to be captured. 8
9 Focus of the programme Therefore, given the above, a small team working to the Chief Executive acted essentially as a programme office to meet the programme management and reporting needs. The reporting cycle was monthly to the Project Board, chaired by the BBC but with observers from the principal stakeholders of DCMS, DWP, Digital UK, OGC (when the procurement was running), and the BBC Trust. A sample of the reporting which illustrates the scope of the programme activities is included below in Table 1. This is the Chief Executive s monthly Board report finalised a few months after the Scheme Agreement had been signed. The emphasis from the outset was to: Have a comprehensive plan in place which defined all key milestones, deliverables and inter-dependencies (see Item 4 in Table 1). This was monitored on a daily basis and formally updated monthly for the Board reporting cycle Capture overall delivery performance over time against plan. (Item 2). There were three clear priorities in this stage which were the focus of management effort: o Running a small scale pilot operation (Copeland) o Procuring a contractor for the Main Scheme o Designing and recruiting the Intelligent Client team Define the programme risks, assess their impact and develop and monitor appropriate mitigating actions (Item 3). It was very important to be completely realistic about risks. In the early stages of a programme with a large of number of uncertainties and limited prior experience a preponderance of amber and some red risks may look disconcerting but are completely to be expected Document the key decisions made by the Design Authority (whose role it was to put more flesh on the bones of the Scheme Agreement, when operating the Help Scheme on a day-to-day basis) (Item 5); and most importantly Summarise the key messages for all major stakeholders (Item 1). This acted as an early warning system for issues emerging and a means of alerting top management where support may be required such as in helping resolve issues, freeing up resources. 9
10 Table 1 Chief Executive s monthly Project Board Report (extracts) 3 Item 1 Stakeholder messages Item 2 Overall delivery performance 3 September
11 Item 3 Key programme risks Item 4 Milestone performance Item 5 Design Authority Key Decisions 11
12 Scale up The period from 2008 to 2009 was characterised by a steady increase in activity as the Scheme became fully operational and began to service customers across a number of different regions simultaneously as switchover rolled out across the UK, in the build up to the very large single switchover in Granada (North West England) in Autumn In this period there was a steady refinement of the monthly reporting processes and information, and management of ad hoc projects and papers as required. Specifically, programme and business management was responsible for coordinating on behalf of the CEO initiatives such as: Rollout plans for each new region. Operationally, a plan had to be prepared and agreed with CES for each new region. The programme team reported on progress on this in the normal way (See Table 1 Item 2) Lessons learned as regions closed. Lessons learned were captured and presented as a Project Board paper, and key learnings consolidated into a Scheme-wide learning log Readiness for a multi-regional and high volume operation. This was an example of a specific project to assess the level of preparedness for the volumes of activity anticipated in late 2009, which was coordinated and reported on through programme management The first iteration of a Help Scheme business plan. The business plan was a major initiative and was tackled once CES had settled in as contractor and the ambition of the Scheme was taking shape. The senior management team took stock of the current state and future vision through a structured business planning process. In the light of the operating environment, and the purpose and scope of activities determined by the Scheme Agreement, the full ambition of the Scheme, the nature of the offer (where this could be influenced), KPIs, and critical success factors were all determined. The team then turned to look at how it should be delivering against this ambition, the role of partners and third parties, and people and financial resource implications. (See Table 2 below for Business Plan contents). 12
13 Table 2 Switchover Help Scheme business plan: constituent elements April 2009 Business Context what is the operating environment? Business rationale for the Help Scheme Political, economic, social and technological analysis Key business constraints Principal assumptions Business Drivers - what are our ambitions? Ambition of the Scheme Business products and services, and our key strategic initiatives Key performance indicators targets & measures Critical success factors Business implications how do we deliver against our ambition? Engage with people especially the hard to reach Building our reputation among all stakeholders Service eligible people with a simplicity agenda Key timescales Resources and capabilities Key partners and third parties Other initiatives Financial resources Risk management Governance 13
14 Review The comparatively lower levels of activity in 2010 (see Chart 2) afforded the opportunity to review all aspects of operations ahead of the very high levels anticipated in Specifically: Work was completed on a further iteration of the business plan A transformation project was launched to improve the customer journey The Making it Happen initiative got under way, designed to ensure that all aspects of the Scheme were fit for purpose to deal with the scope of activities in 2011 The Scheme s risk, issue, dependency and crisis management processes were all reviewed. The Making it Happen in 2011 programme provided project management support to prepare the Help Scheme for expected increased activity from Autumn 2010 and across It was a very important initiative run within the overall programme management framework, and designed to ensure that, as the Help Scheme entered 2011, it was operationally fit for purpose and ready to manage the increased activity whilst continuing to deliver its quality commitments to our customers. Making it Happen in 2011 was constructed from a number of integrated plans, developed across seven core workstreams, each with a designated Help Scheme lead: Direct Marketing, Contact Centre, Field Operations, Aftercare, Care Homes, Outreach, and Complaints. Progress on each of these workstreams and overall was reported monthly through the usual Project Board channel. This programme was instrumental both in ensuring that the Help Scheme was best placed for the challenges of 2011, but also by providing the timely information flows to reassure top management that this was so. 14
15 Complete With the Scheme operation in fully mature mode, the task of programme management was to assist management in maintaining focus and momentum. There were operational initiatives introduced in the period designed to do this which required programme coordination. One such was priority customer management. The aim of this was to improve the way the Scheme manages those people with whom it had difficulty communicating, by enabling front-line staff to flag someone as a priority customer through their customer journey. This highlights to everyone who deals with that person that they may need to give more time, attention, and offer other services that are available to assist them. A further customer management initiative, the multiple failure flag, was also introduced, designed to identify those, thankfully rare, instances where the Help Scheme failed repeatedly to provide a good experience for a customer. The visibility of the flag meant that extra attention was paid to resolving that person s issue. In addition to these new initiatives, the programme management function continued to oversee the completion of milestones and deliverables in each region, ensuring the continued timely implementation of what were by this point business as usual activities. 15
16 Close Whilst the final regional switchovers took place in 2012, for the Help Scheme in 2013 there remained service obligations such as aftercare to be carried out by the Scheme s principal contractor, Carillion, which would still need to be overseen by the BBC, meet the BBC Trust s success measures, and comply with the Code of Service Standards for customers. A much smaller team would clearly be required to manage Scheme duties in By the end of 2012 virtually all the DSHS management and staff would have left, together with many of the Carillion management team previously operating the Help Scheme service. Responsibilities were being transferred to elsewhere in the BBC, to ensure that the final aspects of service delivery were properly carried out. The closure plan was run as a separate programme comprising nine projects: I. DSHS people - retain and motivate people until their planned departure dates II. III. IV. Finance and legal - ensure there are sufficient funds, effective financial management Operational continuity - customer service quality of business as usual Communications - consumer PR, stakeholder communications, issue management V. Governance - appropriate decision-making processes in place in all phases VI. VII. VIII. IX. The tin box handover - key elements of Scheme for handover after switchover completed Information security - decommission all data and systems Carillion contract - handle end of contract smoothly Scheme legacy capture and communicate Scheme learning. The leader of each project - a member of DSHS management was charged with developing detailed terms of reference for their project, a set of deliverables, and project risks. This was reviewed and signed off by DSHS management and forms the backbone of closure planning. All the project plans were consolidated into a detailed programme plan, with responsibilities and milestones identified. The closure plan was independently reviewed by external consultants and judged to be comprehensive and fit for purpose. 16
17 Figure 3 below, the closure timeline, shows the 2012 regions to switch, the four phases as described, and the proposed stages in the TV Licensing handover. Whilst TV Licensing would not take over formal responsibility until the final switchover in Northern Ireland in October 2012, a gradual process of familiarisation and assimilation was planned. The current DSHS Chief Executive, who planned to relinquish formal Scheme responsibility in October 2012, would remain on the DSHS Board until he left the Scheme in December Figure 3 Help Scheme closure timeline DSHS Closedown Timeline 17
18 Conclusion Running the Switchover Help Scheme was new territory for the BBC. Operationally complex, with a multiplicity of stakeholders and a customer base difficult to access, the approach to programme management from the outset was to take what may appear to be an unlikely mix of rigour and pragmatism. Rigour certainly in: governance decision making and reporting; risk management; and demonstrating value for money. It was more pragmatic in its use of tools and techniques, not through scepticism or distrust - indeed in the course of such a long programme it is likely that every single tool and technique was considered if not used - but as a result of not wishing to be constrained by methodologies which may not be universally applicable. 18
Gateway review guidebook. for project owners and review teams
Gateway review guidebook for project owners and review teams The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and
HARLOW COUNCIL PERFORMANCE MANAGEMENT FRAMEWORK
HARLOW COUNCIL PERFORMANCE MANAGEMENT FRAMEWORK July 2013 1 P age Contents Page 1.0 Definition 3 2.0 Context 3 3.0 Purpose and aim of the policy 4 4.0 Policy Statement 4 5.0 Framework for Performance Management
Network Rail Infrastructure Projects Joint Relationship Management Plan
Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf
Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee
Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Page 1 2 Contents 1. Introduction... 3 1.1 Definition of a... 3 1.2 Why have
PROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
The Transport Business Cases
Do not remove this if sending to pagerunnerr Page Title The Transport Business Cases January 2013 1 Contents Introduction... 3 1. The Transport Business Case... 4 Phase One preparing the Strategic Business
Programme Governance and Management Plan Version 2
PROCESS FOR CHANGE - Detailed Design Programme Governance and Management Plan Version 2 1 INTRODUCTION In October 2008, the Council approved the selection of seven opportunity themes to take forward from
Shona Morrison, OPCC Policy Development Manager. This is a Controlled Document
Title: POLICE AND CRIME COMMISSIONER FOR THAMES VALLEY CONTRACT MANAGEMENT STRATEGY Version: 3.0 Authors: Master Copy: Section: Document Status: Authorized By: Shona Morrison, OPCC Policy Development Manager
WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)?
WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)? Due to the often complex and risky nature of projects, many organizations experience pressure for consistency in strategy, communication,
World Class Education and Training, for World Class Healthcare
World Class Education and Training, for World Class Healthcare Introducing Health Education England 2 Contents Foreword... Page 4 Overview... Page 5 Vision and Purpose... Page 6 Shared Principles... Page
Office of the Auditor General AUDIT OF IT GOVERNANCE. Tabled at Audit Committee March 12, 2015
Office of the Auditor General AUDIT OF IT GOVERNANCE Tabled at Audit Committee March 12, 2015 This page has intentionally been left blank Table of Contents Executive Summary... 1 Introduction... 1 Background...
Part B1: Business case developing the business case
Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project
Government Communication Professional Competency Framework
Government Communication Professional Competency Framework April 2013 Introduction Every day, government communicators deliver great work which supports communities and helps citizens understand their
PEOPLE AND ORGANISATION DEVELOPMENT STRATEGIC FRAMEWORK FOR LOCAL GOVERNMENT IN NORTHERN IRELAND
PEOPLE AND ORGANISATION DEVELOPMENT STRATEGIC FRAMEWORK FOR LOCAL GOVERNMENT IN NORTHERN IRELAND DRAFT JULY 2011 PEOPLE AND ORGANISATION DEVELOPMENT STRATEGIC FRAMEWORK FOR LOCAL GOVERNMENT IN NORTHERN
Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.
APM Introductory Certificate in Project Management Exam paper Candidate Reference Number Date of Exam Location of the Exam General Notes Time allowed 1 hour Answer all 60 multiple choice questions Use
AGENDA ITEM 5 AYRSHIRE SHARED SERVICE JOINT COMMITTEE 1 MAY 2015 AYRSHIRE ROADS ALLIANCE CUSTOMER SERVICE STRATEGY
AYRSHIRE SHARED SERVICE JOINT COMMITTEE 1 MAY 2015 AYRSHIRE ROADS ALLIANCE CUSTOMER SERVICE STRATEGY Report by the Head of Roads Ayrshire Roads Alliance PURPOSE OF REPORT 1. The purpose of this report
Benefits realisation. Gate
Benefits realisation Gate 5 The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and Planning, January 2010. The Queensland
OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT)
OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT) 3 DAY COURSE INTRODUCTION The principles of project management are generic and therefore can be applied to all projects regardless of business sector.
(1) To approve the proposals set out in paragraphs 3.1-2 to ensure greater transparency of partnership board activity; and
Agenda Item No. 7 Governance Committee 23 November 2015 Partnership Governance for Contract Management Report by Director of Law Assurance and Strategy Executive Summary This report sets out some areas
Request for feedback on the revised Code of Governance for NHS Foundation Trusts
Request for feedback on the revised Code of Governance for NHS Foundation Trusts Introduction 8 November 2013 One of Monitor s key objectives is to make sure that public providers are well led. To this
Managing ICT contracts in central government. An update
Managing ICT contracts in central government An update Prepared by Audit Scotland June 2015 Auditor General for Scotland The Auditor General s role is to: appoint auditors to Scotland s central government
Middlesbrough Manager Competency Framework. Behaviours Business Skills Middlesbrough Manager
Middlesbrough Manager Competency Framework + = Behaviours Business Skills Middlesbrough Manager Middlesbrough Manager Competency Framework Background Middlesbrough Council is going through significant
building and sustaining productive working relationships p u b l i c r e l a t i o n s a n d p r o c u r e m e n t
building and sustaining productive working relationships p u b l i c r e l a t i o n s a n d p r o c u r e m e n t INTRODUCTION 1 1 THE GROWING INFLUENCE OF PROCUREMENT PROFESSIONALS 2 2 GUIDELINES FOR
How PRINCE2 Can Complement PMBOK and Your PMP Jay M. Siegelaub Impact Strategies LLC. Abstract. About PRINCE2
How PRINCE2 Can Complement PMBOK and Your PMP Jay M. Siegelaub Impact Strategies LLC Abstract PMBOK is the recognized (de facto) standard of project management knowledge. In the UK and Europe, PRINCE2
Change and project management
Change and project management www.first.com What gets measured, gets d! -Change leader Change and Project Management Change and project management Prince 2, PMI and PCI When projects fail in an organisation,
Before starting it is worth considering what we mean by the term project - basically it can be defined as:
Delivering Successful Projects, Tom Moriarty, MDR Consulting This paper outlines the critical requirements of success in managing projects of all types from the definition of a business need to the delivery
PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3)
PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) 1st February 2006 Version 1.0 1 P3M3 Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value
Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000
Project Management Project Management Public Private Partnership Guidance Note 7 14 April 2000 Guidance Note 7 14 April 2000 Project Management Contents Section Page I INTRODUCTION...1 SCOPE AND PURPOSE
Service Management and ICT Monitoring and Reporting Advisory and Implementation Services
Service Management and ICT Monitoring and Reporting Advisory and Implementation Services G-Cloud Service 1 1. An overview of the G-Cloud Service Arcus can assist you with a review and advice on the effectiveness
Keys to a Successful Outsourcing Transition
Keys to a Successful Outsourcing Transition finance.arvato.com Getting it Right the First Time: Keys to a Successful Outsourcing Transition A large part of success in outsourcing depends on a seamless
Achieving efficiencies in public transport delivery: The role of Local Integrated Transport Services (LITS)
Research and Information Service Paper 80/12 27 Apr 2012 NIAR 250-12 Des McKibbin Achieving efficiencies in public transport delivery: The role of Local Integrated Transport Services (LITS) 1 Overview
Retained Fire Fighters Union. Introduction to PRINCE2 Project Management
Retained Fire Fighters Union Introduction to PRINCE2 Project Management PRINCE2 PRINCE stands for: PRojects IN Controlled Environments and is a structured method which can be applied to any size or type
Verification of need. Assessment of options. Develop Procurement Strategy. Implement Procurement Strategy. Project Delivery. Post Project Review
Who should read this fact sheet? Many construction clients are not regular purchasers of construction work. This fact sheet is an introduction to construction procurement for occasional clients with a
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Project Management Self-Assessment Contents Introduction 3 User Guidance 4 P3M3 Self-Assessment Questionnaire
The STFC Project Management Framework
The STFC Project Management Framework Version 4 April 2016 For further information contact: Tony Medland, Programmes Directorate ([email protected]) Matt Fletcher, National Laboratories Directorate
Confident in our Future, Risk Management Policy Statement and Strategy
Confident in our Future, Risk Management Policy Statement and Strategy Risk Management Policy Statement Introduction Risk management aims to maximise opportunities and minimise exposure to ensure the residents
Chapter 6 Implementation Planning
Chapter 6 Planning Planning- Division into Work Packages The following are the recommended Work Packages Overall Change Programme Work Package 1 E-Cabinet Model Work Package 2 Security Policy Design Work
Part E: Contract management
Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project
LONDON GROWTH DEAL. Building London s skills base and supporting businesses; Helping Londoners into sustainable employment; and
LONDON GROWTH DEAL The London Growth Deal will support jobs and growth in the capital, including in key new sectors such as the digital economy. It will ensure the capital s businesses and individuals,
Senior Project Manager A14 Cambridge to Huntingdon, Complex Infrastructure Programme Grade 6. Candidate Pack
Senior Project Manager A14 Cambridge to Huntingdon, Complex Infrastructure Programme Grade 6 Candidate Pack 2 Introduction The Highways Agency is an Executive Agency of the Department for Transport, and
DEVELOPING AN EFFECTIVE PERFORMANCE MANAGEMENT SYSTEM. Ross Fraser HouseMark
DEVELOPING AN EFFECTIVE PERFORMANCE MANAGEMENT SYSTEM Ross Fraser HouseMark Raising the Bar on Performance and Sector Revitalization July 5 and 6, 2007 Contents Page 1. Introduction 2 2. What should a
Project Management Guidebook
METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple
Project, Programme and Portfolio Management Delivery Plan 6
Report title Agenda item Project, Programme and Portfolio Management Delivery Plan 6 Meeting Performance Management and Community Safety Panel 27 April 2009 Date Report by Document number Head of Strategy
Best practice. Corporate Governance. Financial Reporting Council. July 2013. Audit Tenders. Notes on best practice
Best practice Corporate Governance Financial Reporting Council July 2013 Audit Tenders Notes on best practice The FRC is responsible for promoting high quality corporate governance and reporting to foster
CONTRACT MANAGEMENT POLICY
CONTRACT MANAGEMENT POLICY Section Finance Approval Date 25/08/2014 Approved by Directorate Next Review Aug 2016 Responsibility Chief Operating Officer Key Evaluation Question 6 PURPOSE The purpose of
Customer Management Strategy (2014-2017)
Customer Management Strategy (2014-2017) Version 1.1 Page 1 Foreword As technology improves, the demand for Council services to be available online and accessible 24/7 will increase as our customers choose
How To Design A Project
Introduction to Procurement Why is procurement important? Client needs are unique and consequently each project meeting those needs has unique characteristics. This means that achieving the right project
Get in on the Act. The Care Act 2014. Corporate
Get in on the Act The Care Act 2014 Corporate Get in on the Act The Care Act 2014 Background The Care Act was first published as a Bill in the House of Lords on 9 May 2013, following prelegislative scrutiny.
The NHS Foundation Trust Code of Governance
The NHS Foundation Trust Code of Governance www.monitor-nhsft.gov.uk The NHS Foundation Trust Code of Governance 1 Contents 1 Introduction 4 1.1 Why is there a code of governance for NHS foundation trusts?
Specification Document (11/1023)
Responsive funding in the NIHR SDO programme: open call (with special interest in studies with an economic/costing component) Closing date 1.00pm on 15 September 2011 1. Introduction This is the fifth
Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3
/01 PROJECT ADVISORY Stakeholder management and communication Leadership Series 3 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital programmes,
TERMS OF REFERENCE - MAJOR EVENTS PANEL
TERMS OF REFERENCE - MAJOR EVENTS PANEL OVERVIEW The Major Events Panel is a specialist advisory body to the UK Sport Board and its Major Events Team. Its main purpose is to represent the interests of
How To Manage Change Projects In A Business Unit
Project Delivery in Business-as-Usual Organizations tim carroll Chapter 1 Introduction This book tackles the challenges of delivering business projects in support of a company s strategic agenda. It is
External Audit BV Performance Report: Delivering Change Management and Financial Sustainability
CLACKMANNANSHIRE COUNCIL THIS PAPER RELATES TO ITEM 05 ON THE AGENDA Report to: Resources and Audit Committee Date of Meeting: 24 September 2015 Subject: External Audit BV Performance Report: Delivering
P3M3 Portfolio Management Self-Assessment
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Portfolio Management Self-Assessment P3M3 is a registered trade mark of AXELOS Limited Contents Introduction
IPL Service Definition - Project Management, Programme Management and Governance
IPL Proposal IPL Service Definition - Project Management, Programme Management and Governance Project: Date: 16th Dec 2014 Issue Number: Issue 1 Customer: Crown Commercial Service Page 1 of 8 IPL Information
Shropshire Highways Draft Asset Management and Communications Strategy and Implications of Department for Transport Incentivised funding
Committee and Date Cabinet 14 th October 2015 Shropshire Highways Draft Asset Management and Communications Strategy and Implications of Department for Transport Incentivised funding Responsible Officer
IIA POSITION PAPER: THE ROLE OF INTERNAL AUDITING IN ENTERPRISE-WIDE RISK MANAGEMENT
IIA POSITION PAPER: THE ROLE OF INTERNAL AUDITING IN ENTERPRISE-WIDE RISK MANAGEMENT Revised: Page 1 of 8 Introduction The importance to strong corporate governance of managing risk has been increasingly
Financial Conduct Authority. The FCA Data Strategy - How we will manage and use the data we collect
Financial Conduct Authority The FCA Data Strategy - How we will manage and use the data we collect September 2013 Contents 1. Overview 2 2. Our vision for the future of FCA data 4 3. Our strategy to deliver
Change Management Practitioner Competencies
1 change-management-institute.com Change Management Institute 2008 Reviewed 2010, 2012 Change Management Practitioner Competencies The Change Management Practitioner competency model sets an independent
Accelerating your financial close arrangements
Accelerating your financial close arrangements EY Think Piece Contents at a glance Local government accounting, auditing and governance preserving quality financial reporting in light of the new reporting
THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini)
PAGE 1 THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini) Ing. Guido Mattu More than 25 years experience in Engineering and Project Management activities
IT1T Integrated Recruitment Systems 2015
UCD IT Services IT1T Integrated Recruitment Systems 2015 Project Initiation Document Version 1.0 2 December 2014 Version History Version Date Summary of Changes Changed by 1.0 02/12/2014 Initial Draft
Specialist Cloud Services Lot 4 Cloud EDRM Consultancy Services
Specialist Cloud Services Lot 4 Cloud EDRM Consultancy Services Page 1 1 Contents 1 Contents... 2 2 Transcend360 Introduction... 3 3 Service overview... 4 3.1 Service introduction... 4 3.2 Service description...
Communication Capability Review: Department for Business, Innovation & Skills
Communication Capability Review: Department for Business, Innovation & Skills 1 1 Management summary 1.1 The Communication Capability Review of the Department for Business, Innovation and Skills (BIS)
A responsible, sign. team up. front. Committing to where we re going and putting our hearts into what we do. We get engaged every day.
4 NZ Transport Agency Statement of intent 214 18 A responsible, collaborative and agile organisation In order to deliver our desired targets and results effectively and efficiently, we continue to invest
How To Be Accountable To The Health Department
CQC Corporate Governance Framework Introduction This document describes the components of CQC s Corporate Governance Framework: what it is intended to achieve, what the components of the Framework are
Date of Trust Board 29 th January 2014. Title of Report Performance Management Strategy - 2013-2016
ENCLOSURE: P Date of Trust Board 29 th January 2014 Title of Report Performance Management Strategy - 2013-2016 Purpose of Report Abstract To set out the Performance Management Strategy of the Trust in
Prepared for: Prepared by:
Executive Project Review Prepared for: Prepared by: Table of contents Introduction... 3 WHY an Executive Project Review?... 3 WHO is Involved?... 4 WHAT is an Executive Project Review?... 5 WHEN? - Schedule
Master Level Competency Model
Change Manager Master Level Competency Model The Change Manager Master competency model sets an independent industry benchmark for SENIOR level change management practitioners. The model was launched in
EXECUTIVE SUMMARY...5
Table of Contents EXECUTIVE SUMMARY...5 CONTEXT...5 AUDIT OBJECTIVE...5 AUDIT SCOPE...5 AUDIT CONCLUSION...6 KEY OBSERVATIONS AND RECOMMENDATIONS...6 1. INTRODUCTION...9 1.1 BACKGROUND...9 1.2 OBJECTIVES...9
Business Intelligence is a system that collects, integrates, analyses and presents business information to support better business decision making.
UNIVERSITY OF EXETER BUSINESS INTELLIGENCE Key Messages & Communications Plan 1 Key Messages Background: Staff from across the University extract information from a variety of data storage areas to support
Performance Management and Service Improvement Framework
Performance Management and Service Improvement Framework Author Marcus Evans, Operational Director - Performance and Customer Insight Date: September 2014 Contents Page 1. Introduction 3 2. Strategic ning
How are companies currently changing their facilities management delivery model...?
Interserve and Sheffield Hallam University market research 2012 Page 2 www.commercial.interserve.com How are companies currently changing their facilities management delivery model...? we have a strategy
UNECE PPP Healthcare Standard
INTERNATIONAL SPECIALIST CENTRE OF EXCELLENCE ON PPPs IN HEALTH MANILA, PHILIPPINES UNECE PPP Healthcare Standard Questions on lessons learned in the development of Public-Private Partnership ( PPP ) programmes
How To Write A Workforce Strategy
Inspiring leaders to improve children s lives Building and implementing an effective local workforce strategy Module 4: project managing the workforce strategy development process August 2010 Resource
SCHEDULE 3. Milestones and Deliverables. Redacted Version
SCHEDULE 3 Milestones and Deliverables Redacted Version This Schedule 3 sets out the Service Provider s obligations in respect of the milestones and deliverables relating to the implementation and operation
Connect Renfrewshire
How the council will use its information and technology assets to achieve successful change Contents Strategy Context 2 Digital Delivery and Citizen Engagement 4 Operational Excellence and Transformation
White Paper. PPP Governance
PPP Governance The Governance of Projects, Programs and Portfolios (PPP) (sometimes called project governance for convenience) is the sub-set of corporate and organisational governance 1 focused on assisting
PERFORMANCE MANAGEMENT STRATEGY
PERFORMANCE MANAGEMENT STRATEGY Date published: May 2013 South Essex Homes Keeping you informed www.southessexhomes.co.uk 0800 833 160 1 of 12 SOUTH ESSEX HOMES: PERFORMANCE MANAGEMENT STRATEGY This strategy
Specialist Cloud Services Lot 4 Cloud Printing and Imaging Consultancy Services
Specialist Cloud Services Lot 4 Cloud Printing and Imaging Consultancy Services Page 1 1 Contents 1 Contents... 2 2 Transcend360 Introduction... 3 3 Service overview... 4 3.1 Service introduction... 4
Item 10 Appendix 1d Final Internal Audit Report Performance Management Greater London Authority April 2010
Item 10 Appendix 1d Final Internal Audit Report Performance Management Greater London Authority April 2010 This report has been prepared on the basis of the limitations set out on page 16. Contents Page