DuPont Tyvek ThermaWrap R5.0 Installation Guidelines for New Construction Using Vinyl, Brick and Stone Claddings
|
|
|
- Thomas Tate
- 9 years ago
- Views:
Transcription
1 Tyvek ThermaWrap R5.0 Installation Guidelines for New Construction Using Vinyl, Brick and Stone Claddings VERSION 1/16 FOR SINGLE FAMILY HOMES AND LOW RISE MULTI-FAMILY BUILDINGS LESS THAN 4 STORIES
2 Tyvek ThermaWrap R5.0 Installation Guidelines Table of Contents Applicable Products... 2 Recommended Installation Accessories... 2 Recommended Tools*... 3 Warranty... 3 Code Requirements... 3 Precautions and Special Considerations... 3 General Instructions... 4 Wall Preparation... 6 Installation of Tyvek ThermaWrap R Conventional Framed Tilt Wall Window Flashing (Flanged Window Installed After WRB) Door Flashing (Brick Mold Door Installed After WRB) Window Flashing (Flanged Window Installed Before WRB) Door Flashing (Brick Mold Door Installed Before WRB) Flashing Pipe Penetrations Flashing Electrical Box Flashing Dryer Vent Handling Tears and Holes Cladding Installation Brick and Stone Installation Cladding Transition Cladding Considerations Applicable Products Insulating Air and Water-Resistive Barrier PRODUCT DIMENSIONS AREA Tyvek ThermaWrap R5.0 4 ft x 40 ft 160 sq ft Flashing Products PRODUCT DIMENSIONS AREA FlexWrap NF 6 in x 75 ft sq ft 9 in x 75 ft sq ft StraightFlash 4 in x 75 ft 25 sq ft 9 in x 75 ft sq ft StraightFlash VF 6 in x 75 ft 37.5 sq ft Flashing Tape 4 in x 75 ft sq ft 6 in x 75 ft sq ft 9 in x 75 ft sq ft Recommended Installation Accessories PRODUCT TYPE/DIMENSIONS QUANTITY Tyvek HomeWrap 3 ft x 100 ft 300 sq ft Tyvek Tape 2 in Bulk Pack 36 rolls/case 3 in Bulk Pack 24 rolls/case Tyvek Wrap Caps for 16 gauge; available in 7/8, 2000 per box Stinger Cap Stapler 1-1/4, and 1-1/2 lengths Wrap Cap Nails 1 electro-galvanized ring shank nail 2000 per box Other manufacturers cap staples and cap nails Adhesive/Primer Window and Door Foam Residential Sealant 3/4 minimum length Insulated Batten 3 in x 4 ft 24/box Insulated Batten CT 5.8 in x 4 ft 11/box min. 3 10d common nails for installing Insulated Battens Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 2
3 Tyvek ThermaWrap R5.0 Installation Guidelines Recommended Tools* Stinger CS150 Cap Stapler Stinger CN100 Cap Nailer Vinylign Nail Depth Regulator WISS Scissor W10TM Olfa 60mm rotary cutter Standard carpet knife *Use or apply per manufacturers guidelines. For non-dupont products, DuPont assumes no liability in use of recommended products; installers need to evaluate suitability of recommended products in their end-use applications. Precautions and Special Considerations Although normal handling of Tyvek ThermaWrap R5.0 requires no special Personal Protective Equipment (PPE), DuPont recommends appropriate job site PPE in accordance with OSHA and site standards during installation of the product. Tyvek ThermaWrap R5.0 is combustible and should not come into contact with open flame or other high heat sources. Clearances around fireplaces, hot pipes, etc. should follow the National Fire Protection Agency (NFPA) and local code requirements. For more information about the combustibility of Tyvek products, refer to the last page of this document. Warranty Please see warranty requirements for Tyvek ThermaWrap R5.0 at Code Requirements Tyvek ThermaWrap R5.0 meets ICC-ES AC-38 Water-Resistive and Air- Barrier Requirements. ICC-ES Evaluation Report ESR Tyvek ThermaWrap R5.0 provides continuous exterior insulation when installed as directed. To achieve a continuous insulation value of R5.0, the Insulated Batten and the Insulated Batten CT must be used where directed. See Tyvek ThermaWrap R5.0 Physical Properties Data Sheet and Insulation Fact Sheet for additional information. Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 3
4 Tyvek ThermaWrap R5.0 Installation Guidelines General Instructions Tyvek ThermaWrap R5.0 Installation A Certified Installer training program is available for the installation of Tyvek ThermaWrap R5.0. Certification is not required to install Tyvek ThermaWrap R5.0; however, installers should read and adhere to all steps of these installation guidelines. Tyvek ThermaWrap R5.0 is not intended for open stud construction. All windows and doors must be installed on the same plane as the Tyvek ThermaWrap R5.0 outer layer. The best time to install Tyvek ThermaWrap R5.0 is: After the roof sheathing is installed After the step flashing and kick out flashing have been installed BEFORE the windows are installed When installing Tyvek ThermaWrap R5.0 A larger brick/stone ledge may be required to accommodate the 1-1/2 thickness of the Tyvek ThermaWrap R5.0. Extension jambs may be required around the interior of the windows. This product may also affect the appearance of the window sill corners. All insulation edges must butt tightly against one another to help maintain continuous insulation. A feature of the Tyvek ThermaWrap R5.0 is that the insulating fibers can be torn vertically. This eliminates the need for cutting the fibers in such areas as flap creation and window opening preparation. During installation of Tyvek ThermaWrap R5.0, an uninsulated Tyvek flap may be required to ensure shingling for proper water management. To create a flap, separate the insulation from the Tyvek membrane a minimum of 6. Fold back the Tyvek layer. Cut or tear to remove the insulation. Do not damage the Tyvek layer. It may not be necessary to install Tyvek ThermaWrap R5.0 on gable ends to meet energy codes. If Tyvek ThermaWrap R5.0 is not installed on the gables, use Tyvek HomeWrap. Additional furring may be required in order for all cladding to be on the same plane. Check local building codes for additional information. It is essential to maintain the continuity of the water-resistive barrier from top to bottom including proper shingling with sufficient lapping. Continue wrapping all the way up the structure, overlapping the previous layer of Tyvek ThermaWrap R5.0 top sheet by a minimum of 6. Lap Tyvek ThermaWrap R5.0 top sheet over all flashing (e.g. step flashing, wall to roof intersections and through wall flashings). Insulated Batten For optimal thermal performance and to achieve a continuous insulation value of R5.0, the Insulated Batten and the Insulated Batten CT are to be installed into framing members. The Insulated Batten CT is designed to be used as a nail base at all inside and outside corners, around windows and doors, penetrations, wall to roof intersections and at areas on the structure where cladding accessories such as shutters and decorative trim are installed. NOTE: It is acceptable to use nominal 2 thick lumber in place of the Insulated Batten CT. It is NOT acceptable to use substitutes for the Insulated Batten in the field of the wall. The foam portion of the battens is to be installed against the wood sheathing. The Insulated Batten CT can be ripped if the full width is not required. 1-1/2 in. Insulated Battens 1-1/2 in. Plywood Foam 3 in. Side View Insulated Batten CT 5-3/16 in. Plywood Foam 5-3/4 in. For use with lap siding, see Tyvek ThermWarp R5.0 Installation Guidelines for New Single Family Houses Using Lap Siding. K Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 4
5 Tyvek ThermaWrap R5.0 Installation Guidelines DuPont Installation products should be installed on clean, dry surfaces that are free of frost. Wipe surfaces to remove moisture, dirt, grease and other debris that could interfere with adhesion. Adverse weather conditions or cold temperatures may require the use of a primer to promote adhesion of DuPont Products to most building materials. Concrete and masonry require the use of Adhesive/Primer. Apply pressure along entire surface of flashing for a good bond using a J-roller or firm hand pressure. Sealants If a sealant other than Residential Sealant is used, apply per manufacturers guidelines. DuPont assumes no liability in use of non DuPont products; installers need to evaluate suitability of these products in their end-use applications. Review the sealant manufacturers literature or label to confirm that the product used has the chemical and adhesive properties necessary for use with Tyvek air and water barriers and DuPont flashing materials. Refer to Chemical Compatibility of Representative Building Sealants (K-27282) for more information about chemical compatibility Remove all wrinkles and bubbles that may allow for water intrusion by smoothing surfaces and repositioning as necessary. When flashing the sill area for windows and doors, DuPont recommends the use of 6 wide Flexwrap NF for 2 x 4 framing and 9 wide Flexwrap NF for 2 x 6 framing. As an option, if a rigid back dam is desired, cut to the length of the sill and nail into place on the interior edge of the sill prior to installation of Flexwrap NF. Then install Flexwrap NF over sill and corner guard back dam. If using 6 FlexWrap NF with optional rigid back dam, seal ends of corner guard with Residential Sealant, or other recommended sealant. Door and window rough sill framing must be level or slightly sloped to the exterior to ensure proper drainage to the exterior. This best practice ensures continuous support with positive slope to the exterior. Residential Sealant should be tooled flat to allow the natural curing process to create a concave joint. Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 5
6 Tyvek ThermaWrap R5.0 Installation Guidelines Wall Preparation STEP 1 BUMP OUT FRAME INSTALLATION Install a bump-out frame around all windows and door openings before installing Tyvek ThermaWrap R5.0. For optimal thermal performance, the Insulated Batten CT is recommended. Standard nominal 2 thick lumber is acceptable. Wider Bump-out frames may be required to accommodate window and door trim. Cut the frame pieces so they create vertical seams at the sill and horizontal seams at the head (the sill piece should be the width of the rough opening. The jamb pieces should extend to the top of the rough opening and the head piece should extend to the outside of the jamb pieces.) Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 6
7 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 2 BOTTOM OF WALL DETAIL Brick and Stone Installations Sheathing Framing Flashing Systems product Vinyl Siding Installations Along the sill plate, install a min. 4 wide piece of Flashing System product around the perimeter of the home. 1 should extend on to the foundation. DuPont recommends the installation of termination accessories such as a bump-out or termination ledge along the sill plate and at roof to wall intersections. A nominal 2 thick bump-out will provide added support for a cladding starter strip. For optimal thermal performance, the Insulated Batten CT is recommended. The square edge should be directed to the bottom of the wall. Standard 2 x 3 s and 2 x 4 s are acceptable. Fasteners must penetrate framing member a min. 1. If an accessory is not used, proceed to step 4. Through wall flashing Sheathing (OSB or plywood) Framing Foundation 4 Flashing Systems Product Insulated Batten CT Sill Plate Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 7
8 Tyvek ThermaWrap R5.0 Installation Guidelines Alternative Bottom of Wall Details Termination Ledge Must be wide enough to protect bottom edge of Tyvek ThermaWrap R5.0. Termination Ledge will not provide support for cladding starter strip. If there is a concern about water infiltration behind Tyvek ThermaWrap 5.0, one option is to replace the 4 piece of DuPont self-adhered flashing product behind the bump out with a piece of 9 Flashing Tape. In addition to protecting the exposed surface of the bump out, this piece of flashing will the protect bottom 2-1/2 of sheathing. Termination Ledge Sheathing (OSB or plywood) Framing 2 Min. Bump Out Ledge Sheathing (OSB or plywood) Framing STEP 3 TOP OF WALL, ROOF-TO-WALL, LEDGER BOARD DETAILS Using the Insulated Batten and the Insulated Batten CT, install a bump-out at the top of the wall, roof to wall intersections and all ledger board locations. Each batten is to be secured into the stud using a min. 3 long framing nail. Secure each batten 2 from each end and every in the field. See details on pages Standard nominal 2 thick lumber such as a 2x4 is acceptable. STEP 3A TOP OF WALL DETAILS Common Truss Before the installation of the Tyvek ThermaWrap R5.0, install a bump out at the top of the wall. For optimal thermal performance, a Insulated Batten or Insulated Batten CT is recommended. A standard nominal 2 thick lumber such as a 2x4 is acceptable. Tyvek ThermaWrap R5.0 should overlap batten 1-2 at the top. At the overlap, separate Tyvek from insulation to create a flap. Tuck excess insulation along the bottom edge of the batten. Secure flap with cap fastener and Tyvek Tape or a Flashing System product. Flashing Systems product 1-1/2 Flashing Systems product Roof Termination Ledge Sill Plate Bump Out Sill Plate May need to remove corner of batten Insulated Batten Tyvek Tape Excess insulation Uninsulated flap Tyvek ThermaWrap 5.0 Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 8
9 Tyvek ThermaWrap R5.0 Installation Guidelines Raised Heel Truss Before the installation of the Tyvek ThermaWrap R5.0, install a bump out at the top of the wall. For optimal thermal performance, a Insulated Batten or Insulated Batten CT is recommended. A standard nominal 2 thick lumber such as a 2x 4 is acceptable. The batten should be installed to accommodate soffit installation. Tyvek ThermaWrap R5.0 should overlap the batten at the top 1-2. At the overlap, separate Tyvek from insulation to create a flap. Tuck excess insulation along the bottom edge of the batten. Secure flap with cap fastener and Tyvek Tape or a product. Gable Before the installation of the Tyvek ThermaWrap R5.0, install a Insulated Batten CT. The square edge should align with the edge of the roof. This is to accommodate rake board. Tyvek ThermaWrap R5.0 should overlap the Insulated Batten CT at the top 1-2. At the overlap, separate Tyvek from insulation to create a flap. Tuck excess insulation along the bottom edge of the Insulated Batten CT. Secure flap with cap fastener and Tyvek Tape. NOTE: A nominal 2 thick bump-out can be used if the attic is unconditioned. For example, use 2 x 4 as a bump-out for a 2x 6 or 2 x 8 rake board. Roof Insulated Batten CT Tyvek Tape Bump-out Insulated Batten CT Nailer for soffit Soffit Rake board Insulated Batten CT Excess insulation Uninsulated flap Tyvek ThermaWrap 5.0 Tyvek Tape Rake board Uninsulated flap Excess insulation Tyvek ThermaWrap 5.0 Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 9
10 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 3B WALL TO ROOF INTERSECTIONS Bump-out should be installed after step flashing. Bump-out must be installed a minimum of 2 above the roof surface. For optimal thermal performance, the Insulated Batten CT is recommended. The square edge should be directed to the bottom of the wall. Standard 2 x 3 s and 2 x 4 s are acceptable. See page 15 for proper termination of Tyvek ThermaWrap R5.0 at base of wall. STEP 3C LEDGER BOARD DETAIL Make necessary cuts in the ThermaWrap R5.0 and install appropriate step or through wall flashing ensuring a minimum 6 overlap. Tape Tyvek ThermaWrap R5.0 to flashing using Tyvek Tape. DuPont is a manufacturer of weatherization products and therefore is not responsible or liable for building design or structural performance. Tyvek ThermaWrap R5.0 Flashing Systems product Bump-out Metal Ledger Flashing (inserted between insulating fibers and Tyvek layer) Tyvek Tape Sealant Ledger (installed to structural member as designed and in accordance with applicable codes.) Insulated Batten CT or nominal 2 lumber Tyvek water-resistive barrier Tyvek Tape Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 10
11 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 4 BUMP-OUT FLASHING A. Install a 4 x 4 piece of FlexWrap NF at both upper corners of the bump-out frame. Install 2-3 inches on the wood sheathing and ensure the FlexWrap NF extends to the edge or overlaps on to the face of the bump-out frame. B. Install product at the intersection of the wood sheathing and Insulated Batten CT (bump-out frame) at all windows. Cut a piece the width of the Insulated Batten CT (bump-out frame). NOTE: Product must protect the foam and wood edge of the Insulated Batten CT (bump-out frame). For round top windows, use FlexWrap NF. Install 2-3 inches on the wood sheathing and continue along the top edge of bump-out frame. STEP 5 CREATING A GUIDE Using a chalk line, create a guide for installing the first course of Tyvek ThermaWrap R5.0. If using a Insulated Batten CT or nominal 2 wood bump-out, create a line around the building 4 ft. above the top of the bump-out. If using the termination ledge, create a line around the building 4 ft. above the bottom edge of the strip. If a bottom detail is not used, the line should be 47 above the bottom of the sill plate. OPTION: Use a wider product to integrate with window flashing. A 4 feet B A Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 11
12 Tyvek ThermaWrap R5.0 Installation Guidelines Installation of Tyvek ThermaWrap R5.0 These guidelines cover the installation of Tyvek ThermaWrap R5.0 installed on Conventional Framed structures and Tilt Wall Framed structures. To maintain proper shingling, Tyvek ThermaWrap R5.0 can only be installed horizontally. See page 16 for installation over Tilt Wall Framed structures. Unroll directly over windows and doors. For larger window and door openings, an option is to cut the material at the right jamb and move the roll and start again at the left jamb. This will eliminate the waste that is normally cut from the window opening. When using this method, the Tyvek ThermaWrap R5.0 must be cut so that there is enough material to wrap into the interior of the window or door opening and secured to the inside of the wall as shown on page 21. On walls that have multiple window and door openings, another option is to pre-cut pieces of Tyvek ThermaWrap R5.0 to fit between the openings. Again, the Tyvek ThermaWrap R5.0 must be cut long enough to extend into the window opening and be secured. Don t leave window openings covered overnight. Prepare the window openings as shown on step 1 on page 19. This allows air to pass through the opening and prevents the potential for blow-off or damage to the Tyvek ThermaWrap R5.0 Conventional Framed Start at the bottom of the structure to ensure proper shingling throughout the installation. Proper shingling is required to shed water and to prevent water from entering the wall system. STEP 1 UNROLLING TYVEK THERMAWRAP R5.0 Starting at a corner of the building, align the vertical edge of insulation with the edge of the building and begin unrolling Tyvek ThermaWrap R5.0 from right to left. Ensure insulation material is against the wall sheathing. Do not secure the 6 Tyvek flap at the beginning of the roll. Use the chalk line on the wall as a guide for the top edge. Unroll directly over window and door openings. DO NOT INSTALL INSULATION UPSIDE DOWN. DO NOT STRETCH OR PULL MATERIAL TIGHT AGAINST WALL SHEATHING INCLUDING INSIDE AND OUTSIDE CORNERS. Tension on the Tyvek ThermaWrap R5.0 will reduce the thickness and R-value. Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 12
13 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 2 FASTENING TYVEK THERMAWRAP R5.0 Along the top edge of the roll, there is an area for fastening. On the dashed line, attach the Tyvek ThermaWrap R5.0 every 16 using: Tyvek Wrap Cap Staples for Stinger Tyvek Wrap Cap nails for Stinger or DuPont recommended cap fastener NOTE: Do not fasten within 9 of bump-outs STEP 3 Install first roll of Tyvek ThermaWrap R5.0. Continue around the structure installing the next roll making sure the vertical edge of the insulation butts against the vertical edge of the previous roll. STEP 4 Continue to unroll the product around the structure until the first course is complete. Cut the Tyvek ThermaWrap R /2 beyond corner of the structure. STEP 5 Install the next and subsequent courses the same as the first. Ensure the bottom edge of the insulation butts against the top edge of the prior course. Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 13
14 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 6 TERMINATING TYVEK THERMAWRAP R5.0 Fold horizontal and vertical flaps and tape all seams with 2 Tyvek Tape. Seal the bottom edge using the details on pages NOTE: The bottom edge should NOT be sealed until all Tyvek ThermaWrap R5.0 has been installed and all other seams have been taped, including the top of the wall detail. This will ensure that precipitation does not collect behind the product during the installation process. Once Tyvek ThermaWrap R5.0 has been fully and properly installed and the bottom edge sealed, bulk water will not collect behind the product. Brick and Stone Installation Terminate the uninsulated Tyvek flap to the through wall flashing with 2 Tyvek Tape Tyvek ThermaWrap R5.0 Tyvek ThermaWrap R5.0 uninsulated flap Tyvek Tape Foundation This flap is folded down and covers fasteners. Tape flap. Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 14
15 Tyvek ThermaWrap R5.0 Installation Guidelines Vinyl Siding Installations If using a Insulated Batten CT or nominal 2 bump-out at the base of the wall, terminate the bottom uninsulated Tyvek flap. Trim the flap flush with the bottom edge of the Insulated Batten CT. Secure the flap with 3 Tyvek Tape or a product. The product or the 3 Tyvek Tape must terminate on the Flashing Systems product secured to the wall and foundation. If using the termination ledge, remove the uninsulated Tyvek flap at the bottom and secure to the termination strip with a product or Tyvek Tape. Termination Ledge Framing Tyvek ThermaWrap R5.0 Framing Sheathing (OSB or plywood) 1-1/2 2 Min. Sheathing (OSB or plywood) Flashing Systems Product Termination Ledge Tyvek ThermaWrap R5.0 Sill Plate Flashing Systems Product or Tyvek Tape Sill Plate Insulated Batten CT Uninsulated Flap Flashing Systems Product or 3 Tyvek Tape If a termination accessory is not used, seal the flap at the bottom of the wall with a product, Tyvek Tape, or Residential sealant. The uninsulated Tyvek flap should cover the bottom edge of insulation before turning down onto the foundation. Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 15
16 UP UP UP UP Tyvek ThermaWrap R5.0 Installation Guidelines Tilt Wall First Floor STEP 1 Provide enough insulation to overhang the bottom edge of the wall so that the bottom of the wall termination can be completed when the wall is tilted upright. Be sure to include material for rim board. Determine the amount of material overhanging and subtract this distance from the width of a roll of Tyvek ThermaWrap R5.0 (4 ft.). Strike a chalk line this distance above the bottom edge of the wall. There are UP arrows printed on the Tyvek top sheet. Starting at the edge of the wall unroll the Tyvek ThermaWrap R5.0 so the UP arrows will point upwards to the top of the wall after the wall is tilted. Leave a minimum of 6 flap at the beginning. This may require the creation of a flap. STEP 2 At window and door openings, cut the Tyvek ThermaWrap R5.0 on the first side long enough to extend to the back of the window opening. Separate insulation from Tyvek back to the outside edge of the bump out frame. Cut or tear insulation along outside edge of bump out frame. Fold Tyvek flap into window opening. Do the same for the other side of the opening. UP Remove insulation Up Arrows Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 16
17 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 3 At the end of the panel, cut the Tyvek ThermaWrap R5.0 flush with the edge of the wall. At all corners, leave additional ThermaWrap R5.0 to accommodate thickness of framing and Tyvek ThermaWrap R5.0 on adjacent wall. Secure on the dashed line along the top edge into every stud. Cut the left side longer to compensate for both framing and TWR5.0 thickness of the adjacent wall Depending on Wall Construction Leave additional insulation on the right side to compensate for both framing and TWR5.0 thickness of the adjacent wall STEP 4 Install the 2nd course the same as the first course. STEP 5 For single story structures, unroll 3rd course, fasten along top edge and cut off excess. For multiple story structures, it s not necessary to install a 3rd course at this time. STEP 6 Fold back any material hanging over the bottom edge of the wall. This will prevent the material from getting pinched when the wall is raised. UP UP UP STEP 7 As each wall section is raised, ensure the bottom of the insulation butts against the termination accessory or overlaps the sill plate. Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 17
18 Tyvek ThermaWrap R5.0 Installation Guidelines Second Floor and above STEP 8 For multiple story structures, or sides with gables, the exposed sheathing can be covered when the Tyvek ThermaWrap R5.0 is installed on the second and successive stories or gables. When installing the Tyvek ThermaWrap R5.0 on the story above the exposed sheathing, measure the amount of exposed sheathing below. Be sure to include the rim board. Subtract this amount from 4 ft. and strike a chalk line this distance from the bottom of the second story wall or gable. Install the top edge of Tyvek ThermaWrap R5.0 along this line. STEP 9 Fold back the material hanging over the wall. This will prevent the material from getting pinched when the wall is tilted. If a termination accessory is not used, seal the flap at the bottom of the wall with a product, Tyvek Tape, or Residential sealant. The uninsulated flap should cover the bottom edge of insulation before turning down onto the foundation. Framing Sheathing (OSB or plywood) Tyvek ThermaWrap R5.0 STEP 10 Fold horizontal and vertical flaps and tape all seams with 2 Tyvek Tape. Seal the bottom edge using the below steps. NOTE: The bottom edge should NOT be sealed until all Tyvek ThermaWrap R5.0 has been installed and all other seams have been taped, including the top of the wall detail. This will ensure that precipitation does not collect behind the product during the installation process. Once Tyvek ThermaWrap R5.0 has been fully and properly installed and the bottom edge sealed, bulk water will not collect behind the product If using a Insulated Batten CT or nominal 2 bump-out at the base of the wall, terminate the bottom uninsulated Tyvek flap. Trim the flap flush with the bottom edge of the Insulated Batten CT. Secure the flap with 3 Tyvek Tape or a product. The product or the 3 Tyvek Tape must terminate on the Flashing Systems product secured to the wall and foundation. If using the termination ledge, remove the uninsulated Tyvek flap at the bottom and secure to the termination strip with a Tyvek product or a Tyvek Tape. Termination Ledge This flap is folded down and covers fasteners. Tape flap. Sill Plate Flashing Systems Product or Tyvek Tape Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 18 Framing 1-1/2 2 Min. Sill Plate Tyvek ThermaWrap R5.0 Sheathing (OSB or plywood) Flashing Systems Product Termination Ledge Insulated Batten CT Uninsulated Flap Flashing Systems Product or 3 Tyvek Tape
19 Tyvek ThermaWrap R5.0 Installation Guidelines Window Flashing (Flanged Window Installed After WRB) See page 6 for wood buck installation Wall Sheathing (OSB) DuPont Insulated Batten CT or Solid Nailing Surface (Wood Bump-out Frame) DuPont ThermaWrap R5.0 STEP 1 PREPARING THE WINDOW OPENING Make an I-Cut in the Tyvek ThermaWrap R5.0. Begin with a horizontal cut along the bottom and top of the window opening. Both cuts should extend the width of the rough opening. For round top windows, the cut should begin above the mull joint. From the center, cut straight down the sill. The horizontal cuts must penetrate the Tyvek top sheet and insulation. It s not necessary to cut through the insulation when making the vertical cut. Window Head Flashing DuPont StraightFlash (1) Head Tape DuPont Tyvek Tape Sill Flashing Head Flap Flashing DuPont StraightFlash (1) (1) DuPont Flashing Tape can be substituted for DuPont StraightFlash Jamb Flashing DuPont StraightFlash (1) Exterior for Roundtop Windows Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 19
20 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 2 Cut two 45 degree slits at a minimum of 8 extending from the corner of the window head up and away from the window opening. This will create a flap above the rough opening and expose the bump out frame. Remove the insulation from this flap by separating it from the Tyvek layer and cutting along the horizontal. Do not cut or damage the Tyvek. Fold back Tyvek flap and temporarily secure with Tyvek Seam Tape. 8 Minimum STEP 3 Cut two 45 slits not to exceed 3 extending from the bottom corner up and away from the window opening. Starting at the vertical cut in the middle of the window, separate the Tyvek layer from the insulation to the outside of the bump-out frame. Starting at the top corners of the bump-out frame, tear or cut straight the insulating fibers along both jambs. This will expose the window opening and the bump-out fame. At the sill, make 2 vertical cuts starting 1-2 to the outside of the window opening. Both cuts should extend to the bottom of the bump-out frame. Remove the insulation from this flap by separating it from the Tyvek and cutting along the bottom edge of the bump-out frame. Do not cut or damage the Tyvek. At the bottom corners, carefully push the insulation to the outside of the bump-out frame. For bump-out frames narrower than 4 It s not necessary to make the 2 vertical cuts below the sill. Instead, separate the insulation from the Tyvek layer that sits on top of the bump-out frame along the sill. Tuck the excess insulation along the bottom edge of the bump-out frame. Ensure there is no insulation on top of the bump-out frame. This can cause the cladding and trim to appear uneven around windows and doors. Exterior Exterior Vertical cuts for Remove bump-out frame insulation Exterior greater than 4 Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 Exterior 20
21 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 4 INSTALLATION OF FLEXWRAP NF Cut FlexWrap NF at least 12 longer than the width of the rough opening sill. The FlexWrap NF must extend as far into the opening as the window and still maintain 2-3 on the face of the wall. Remove the first piece of the release paper, cover horizontal sill and adhere into rough opening along sill and up jambs (min. 6 on each side). Remove second release paper. Fan out FlexWrap NF at bottom corners onto face of wall. Coverage of FlexWrap NF should be 2-3 onto the face of the wall. STEP 5 A. Tape along jambs and at the inside of the top and bottom corners of the window opening. Fold Tyvek flaps to the inside and secure. A No gap in corner Window jamb DuPont FlexWrap NF A WRONG Sill CORRECT FRONT VIEW CORNER DETAIL 1 Overhang 6 minimum Interior Exterior Sill length +12 DO NOT STRETCH Exterior Exterior Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 21
22 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 6 Apply Residential Sealant, or other sealant, on three sides (jambs and head) as shown. If sealant is applied to the sill, ensure that there are at least (2) 2 gaps in the sealant bead for every 4 of window to allow for drainage. For Rectangular Windows STEP 7 WINDOW INSTALLATION AND FLASHING Install window according to manufacturer s instructions. Cut two pieces of StraightFlash or FlexWrap NF or jamb flashing extending 1 above window head flange and below bottom edge of sill flashing. Remove release paper and press tightly along sides of window frame. Cut a piece of StraightFlash or FlexWrap for head flashing, which extends beyond outer edges of jamb flashings. Remove release paper and install completely covering mounting flange and adhering to exposed sheathing or framing members. 1 minimum NOTE: product at jambs must overlap the FlexWrap NF at the sill and adhere to the Tyvek ThermaWrap R5.0 below the sill. INCORRECT FlexWrap NF reverse flashed CORRECT StraightFlash overlaps FlexWrap NF Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 22
23 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 8 Flip down Tyvek ThermaWrap R5.0 flap so it lies flat across head flashing. Tape seams as shown. DO NOT TAPE at bottom of window. At the head, continuous tape seams as shown with Tyvek Tape. Apply products to diagonal seams of Tyvek ThermaWrap R5.0. STEP 9 Final Step Install Residential Sealant, or other sealant, (and backer rod as necessary ) around the window opening at the interior. It is also acceptable to use Window and Door Foam or other recommended foam. The seal created by the sealant (and backer road as necessary) or foam will also serve as a back dam. Residential Sealant should be tooled flat to allow the natural curing process to create a concave shape. Be sure the sealant penetrates the grooves of the FlexWrap NF around the sill. Flashing Systems product Interior Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 23
24 Tyvek ThermaWrap R5.0 Installation Guidelines For Roundtop Windows STEP 7 NOTE: Follow rectangular window instructions (Steps 1 through 5) for proper installation of sill and jamb flashing prior to head flashing installation. A. Cut FlexWrap NF head flashing at least 12 LONGER than the arc length (H) of roundtop window. B. Remove both release papers and install to conform around top of window, covering entire mounting flange and adhering to exposed sheathing or framing members. Head flashing should overlap jamb flashings at least 6. STEP 8 A. Flip down Tyvek ThermaWrap R5.0 flap so it lies flat across head flashing. B. Tape seams as shown. DO NOT TAPE at bottom of window. At the head, continuous tape seams as shown with Tyvek Tape. StraightFlash or Flashing Tape A B A FlexWrap NF FlexWrap NF FlexWrap NF 6 minimum Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 24
25 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 9 Final Step Install Residential Sealant, or other sealant, (and backer rod as necessary) around the window opening at the interior. It is also acceptable to use Window and Door Foam or other recommended foam. The seal created by the sealant (and backer rod as necessary) or foam will also serve as a back dam. Residential Sealant should be tooled flat to allow the natural curing process to create a concave shape. Be sure that the sealant penetrates the grooves of the FlexWrap NF around the sill. Interior Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 25
26 Tyvek ThermaWrap R5.0 Installation Guidelines Door Flashing (Brick Mold Door Installed After WRB) See page 6 for wood buck installation Wall Sheathing (OSB) DuPont Insulated Batten CT or Solid Nailing Surface (Wood Bump-out Frame) STEP 1 PREPARING THE DOOR OPENING Make an I-Cut in the Tyvek ThermaWrap R5.0. Begin with a horizontal cut along the bottom and top of the door opening. Both cuts should extend the width of the rough opening. From the center, cut straight down the sill. The horizontal cuts must penetrate the Tyvek top sheet and insulation. It s not necessary to cut through the insulation when making the vertical cut. DuPont ThermaWrap R5.0 Door Head Flashing DuPont StraightFlash Head Tape DuPont Tyvek Tape Sill Flashing Jamb Flashing DuPont StraightFlash Head Flap Flashing DuPont StraightFlash Exterior Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 26
27 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 2 Cut two 45 degree slits at a minimum of 8 extending from the corner of the door head up and away from the door opening. This will create a flap above the rough opening and expose the bump out frame. Remove the insulation from this flap by separating it from the Tyvek layer and cutting along the horizontal. Do not cut or damage the Tyvek. Fold back Tyvek flap and temporarily secure with Tyvek Seam Tape. 8 Minimum STEP 3 Cut two 45 slits not to exceed 3 extending from the bottom corner up and away from the door opening. Starting at the vertical cut in the middle of the door, separate the Tyvek layer from the insulation to the outside of the bump-out frame. Starting at the top corners of the bump-out frame, tear or cut straight the insulating fibers along both jambs. This will expose the door opening and the bump-out fame. At the sill, make 2 vertical cuts starting 1-2 to the outside of the door opening. Both cuts should extend to the bottom of the bump-out frame. Remove the insulation from this flap by separating it from the Tyvek and cutting along the bottom edge of the bump-out frame. Do not cut or damage the Tyvek. At the bottom corners, carefully push the insulation to the outside of the bump-out frame. For bump-out frames narrower than 4 It s not necessary to make the 2 vertical cuts below the sill. Instead, separate the insulation from the Tyvek layer that sits on top of the bump-out frame along the sill. Tuck the excess insulation along the bottom edge of the bump-out frame. Ensure there is no insulation on top of the bump-out frame. This can cause the cladding and trim to appear uneven around windows and doors. Vertical cuts for bump-out frame greater than 4 Exterior Exterior Exterior Exterior Remove insulation Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 27
28 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 4 INSTALLATION OF FLEXWRAP NF 9 FlexWrap NF is recommended. Cut FlexWrap NF at least 12 longer than the width of the rough opening sill. The FlexWrap NF must extend as far into the opening as the window and still maintain 2-3 on the face of the wall. Remove the first piece of the release paper, cover horizontal sill and adhere into rough opening along sill and up jambs (min. 6 on each side). Remove second release paper. Fan out FlexWrap NF at bottom corners onto face of wall. Coverage of FlexWrap NF should be 2-3 onto the face of the wall. Fold Tyvek flaps to the inside and secure. STEP 5 A. Tape along jambs and at the inside of the top and bottom corners of the window opening. A No gap in corner Window jamb DuPont FlexWrap NF WRONG Sill CORRECT FRONT VIEW CORNER DETAIL A 1 Overhang Interior Exterior 6 minimum Sill length +12 DO NOT STRETCH Exterior Exterior Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 28
29 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 5 (OPTIONAL BACK DAM FOR DOORS) Install the sill flashing as indicated leaving the 1 of FlexWrap NF with release paper extending it past the door threshold on the inside. When the 1 of release paper is removed, there should be 3/4 of flashing to form the back dam. OPTION 2: Some flooring cannot accomodate a back dam. In that case fold the 1 back dam on top of FlexWrap NF in the sill. Door will be installed on top of the 1 fold to create a back dam. EXTERIOR INTERIOR Door Door Threshold Transition Threshold Flooring Optional DuPont StraightFlash Insulated Batten CT High Pressure Skirt (See Step 6 Optional) SIDE VIEW DETAIL DuPont FlexWrap NF Sheathing DuPont Tyvek ThermaWrap R5.0 Sub Floor Corner Guard (Optional) Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 29
30 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 6 (OPTIONAL) - HIGH PRESSURE SKIRT (Completing installation of flashing for brick mold door) For extreme weather conditions, performance requirements exceeding ASTM E1677, or window/door design ratings of DP45 or greater, see General Instructions. A. Create the high pressure skirt by cutting a piece of Tyvek WRB 1 wider than the width of door opening and approximately 10 in height. B. Cut a piece of StraightFlash VF to the same width of skirt. Remove release paper from one side of StraightFlash VF and adhere to Tyvek WRB. The skirt may be made with either StraightFlash VF or StraightFlash. C. Remove the release paper from the other side of StraightFlash VF and adhere the butyl adhesive at the sill skirt to the underside of the door threshold behind the jamb flashing. D. Secure edges of the optional skirt with two 4 pieces of StraightFlash. E. Tape the bottom of the optional skirt to allow for drainage and to minimize wind damage during construction. F. If sealant is applied to the threshold, ensure that there are at least two (2) 2 gaps in the sealant bead to allow for drainage for every 4 of door using Residential Sealant, or other sealant. DuPont StraightFlash VF B Butyl Adhesive 10 A C Peel Off Release Paper and attach to underside of door threshold Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 30
31 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 7 STRAIGHTFLASH VF INSTALLATION A. Prepare head flashing by cutting a piece of StraightFlash VF at least twelve (12) inches LONGER than the head length. B. Break the scored release paper on one edge of the head flashing by folding it back and forth upon itself. C. Center the StraightFlash VF along the length of the door head and position so that it contacts the door frame and interior side of the brick mold or flange. Remove the outer release paper and adhere the flashing to the door frame. Use the inner release paper to form a tight seal in the corner. D. Remove the inner release paper strip and adhere the flashing to the back of the brick mold or flange. E. Beginning at the junction of the jamb and head, and away from the corner, cut the StraightFlash VF at a 45 angle. F. Fold the newly created flashing flap down flat against the brick mold or flange. G. Fold remaining head flashing flaps down onto the jamb frame. A A C D E A F G Brick Mold Door Interior Door Interior Door Interior Door Interior Scored Release Paper Butyl VIEW A-A Door Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 31
32 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 8 A. Prepare jamb flashing by cutting a piece of StraightFlash VF at least six (6) inches LONGER than the jamb. B. Break the scored release paper on one side of the jamb flashing by folding it back and forth upon itself. C Position so that the StraightFlash VF contacts the door frame and interior side of the brick mold. Ensure that the jamb flashing is positioned 1-1/2 inch below the top edge of the head flashing. Jamb flashing adhesive must come in contact with head flashing adhesive by one inch. D. Remove the outer release paper and adhere the flashing to the door frame. Use the inner release paper to form a tight seal in the corner. E. Remove the inner release paper and adhere the flashing to the back of the brick mold. F. Repeat on for opposite jamb. STEP 9 A. Beginning at the junction of the jamb and head and beginning at the junction of the jamb and sill, and away from the corner, cut the StraightFlash VF along both corners at a 45 angle. B. Fold newly created flaps down flat against the head flashing. C. Fold newly created flaps down onto the head and sill of door frame. A B C C 1-1/2 Make sure the adhesive on these pieces will overlap. C 1-1/2 E C A Door Interior Door Interior Door Interior Door Interior Door Interior Door Interior D Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 32
33 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 10 DOOR INSTALLATION A. Install door according to manufacturer s installation instructions. B. Remove the remaining release paper from the StraightFlash VF jamb flashing and press firmly to adhere it to the Tyvek WRB. C. Remove the release paper at the head and adhere it to the wall surface. D. OPTIONAL: Cover exposed butyl with StraightFlash or Flashing Tape. STEP 11 (RECOMMENDED BEST PRACTICE) A. OPTIONAL: Cut a piece of metal or vinyl drip cap 1/8 LONGER than the width of the door and bend down edges. Place a bead of Residential Sealant, Commercial Sealant or recommended sealant on the rear side. Install the drip cap tight against the door head and cover the top edge with StraightFlash or Flashing Tape. B. Flip down upper flap of the Tyvek WRB so it lays flat across head flashing. C. Tape seams as shown. DO NOT TAPE at bottom of door. At the head, continuous tape seams as shown with Tyvek Tape; if an air barrier is not required or if additional drainage is desired. Skip-taping at the head is acceptable. D. Tape down diagonal seams of Tyvek WRB. C D EXTERIOR INTERIOR Door Door Threshold Transition Threshold Flooring A C B Sheathing (OSB or plywood) Tyvek ThermaWrap R5.0 Optional B DuPont StraightFlash High Pressure Skirt (See Step 5 Optional) SIDE VIEW DETAIL DuPont FlexWrap NF DuPont Tyvek WRB Sheathing Sub Floor Corner Guard (Optional) Flashing System Product Bump-out Frame Flashing Drip Cap Brick Mold StraightFlash VF Bump-out Frame Door Opening Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 33
34 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 12 Final Step A. When the interior flooring is ready to install, remove release paper and use Folding Option One or Two to form back dam. B. Install Residential Sealant, Commercial Sealant or recommended sealant (and backer rod as necessary) around the door opening at the interior. It is also acceptable to use Window & Door Foam or recommended foam. The seal created by the sealant (and backer rod as necessary) or foam will also serve as a back dam. Residential Sealant or Commercial Sealant should be tooled flat to allow the natural curing process to create a concave shape. Be sure that the sealant penetrates the grooves of the FlexWrap NF around the sill. NOTE: Installations that specify a window/door design rating of DP45 or greater require extra precautions. See General Instructions for performance requirements exceeding this design rating. A Folding Option One Folding Option Two OR Fold Out and Up Fold In and Up Fastening Option One Fastening Option Two OR Staples Tape Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 34
35 Tyvek ThermaWrap R5.0 Installation Guidelines Window Flashing (Flanged Window Installed Before WRB) See page 6 for wood buck installation Wall Sheathing (OSB) Bump-out Frame Flashing DuPont Insulated Batten CT or Solid Nailing Surface (Wood Bump-out Frame) Head Flashing DuPont StraightFlash (1) STEP 1 APRON INSTALLATION Complete Wall Preparation as shown on pages Create apron from Tyvek ThermaWrap R5.0 by removing the insulation from the back. Any Tyvek water-resistive barrier (WRB) can also be used. Apron should extend to the outside of the bump-out frame and far enough below the rough opening to overlap the sill plate or WRB below. Apron must overlap the WRB below a min. 6. Window DuPont ThermaWrap R5.0 Apron Sill Flashing Jamb Flashing DuPont StraightFlash (1) (1) DuPont Flashing Tape can be substituted for DuPont StraightFlash DuPont Tyvek Tape Sill width Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 35
36 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 2 Use Tyvek Tape to secure the apron to the bump-out frame at the sill. The bottom of apron should be left free to overlap later with Tyvek ThermaWrap R5.0 installation. The top edge of the apron should be flush with the sill. STEP 3 INSTALLING FLEXWRAP NF Cut FlexWrap NF at least 12 longer than the width of the rough opening sill. The FlexWrap NF must extend as far into the opening as the window and still maintain 2-3 on the face of the wall. Remove the first piece of the release paper, cover horizontal sill and adhere into rough opening along sill and up jambs (min. 6 on each side). Remove second release paper. Fan out FlexWrap NF at bottom corners onto face of wall. Coverage of FlexWrap NF should be 2-3 onto the face of the wall. WRONG No gap in corner Window jamb DuPont FlexWrap NF Sill CORRECT FRONT VIEW CORNER DETAIL Sill length Overhang 6 DO NOT STRETCH minimum Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 36
37 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 4 Apply Residential Sealant, or other sealant, on three sides (jambs and head) as shown. If sealant is applied to the sill, ensure that there are at least (2) 2 gaps in the sealant bead for every 4 of window to allow for drainage. STEP 5 WINDOW INSTALLATION AND FLASHING Install window according to manufacturer s instructions Cut two pieces of a product for jamb flashing extending 1 above window head flange and extending below bottom edge of sill flashing. Remove release paper and press tightly along the sides of the window frame. Cut a piece of product for head flashing to extend beyond outer edges of jamb flashings. Remove release paper and install completely covering mounting flange and adhering to exposed sheathing or framing members. 1 minimum INCORRECT FlexWrap NF reverse flashed CORRECT StraightFlash overlaps FlexWrap NF Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 37
38 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 6 Install Bump-out Frame Flashing A. Install a 4 x 4 piece of FlexWrap NF at both upper corners of the bump-out frame. Install 2-3 inches on the wood sheathing and ensure the FlexWrap NF extends to the edge or overlaps on to the face of the bump-out frame. B. Install product at the intersection of the wood sheathing and Insulated Batten CT at all windows. Cut a piece the width of the Insulated Batten CT. For round top windows, use FlexWrap NF. Install 2-3 inches on the wood sheathing and continue along the top edge of bumpout frame. OPTION: Use a wider product to integrate with window flashing For Roundtop Windows STEP 7 NOTE: Follow rectangular window instructions (Steps 1 through 5) for proper installation of sill and jamb flashing prior to head flashing installation. Cut head flashing at least 12 longer than the arc length of round top window. Remove both release papers and install to conform around top of window, covering entire mounting flange and adhering to exposed sheathing or framing members. Head flashing should overlap jamb flashings at least 6. FlexWrap NF A B FlexWrap NF H FlexWrap NF A 6 minimum Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 38
39 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 8 Install Residential Sealant, or other sealant, (and backer rod as necessary ) around the window opening at the interior. It is also acceptable to use Window and Door Foam or or other recommended foam. The seal created by the sealant (and backer road as necessary) or foam will also serve as a back dam. Residential Sealant should be tooled flat to allow the natural curing process to create a concave shape. Be sure the sealant penetrates the grooves of the FlexWrap NF around the sill. STEP 9 EXPOSING THE WINDOW Refer to page 12 for Tyvek ThermaWrap R5.0 installation. After installing Tyvek ThermaWrap R5.0, use shears to cut as shown to expose window. At the jambs and head, cut around the perimeter of the window frame 1 from the edge. Do Not cut around the bump-out frame. Make a cut the width of the apron along the bottom edge of the bump-out frame. Make two 45 degree cuts extending from the corner of the window head up and away from the window opening. This will create a flap above the rough opening and expose the bump-out frame. Pull apron to the outside of the Tyvek ThermaWrap R5.0. Cut 1 from edge of window DO NOT CUT through DuPont Flashing Systems products or apron. Apron Interior Interior Apron Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 39
40 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 11 Remove insulation that overlaps bump-out frame at the head and jambs. STEP 12 TERMINATING THE TYVEK THERMAWRAP R5.0 AROUND THE WINDOW Tape as shown using Tyvek Tape. Use products at the 45 cuts at the head. Remove insulation DuPont Flashing Systems products Window FlexWrap NF Apron made of Tyvek Apron must be properly integrated with lower course of Tyvek ThermaWrap R5.0 6 Minimum Overlap Tyvek Tape Tyvek ThermaWrap R5.0 SIDE VIEW DETAIL Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 40
41 Tyvek ThermaWrap R5.0 Installation Guidelines Door Flashing (Brick Mold Door Installed Before WRB) See page 6 for wood buck installation Wall Sheathing (OSB) Bump-out Frame Flashing DuPont Insulated Batten CT or Solid Nailing Surface (Wood Bump-out Frame) Head Flashing DuPont StraightFlash (1) STEP 1 APRON INSTALLATION Complete Wall Preparation as shown on pages Create apron from Tyvek ThermaWrap R5.0 by removing the insulation from the back. Any Tyvek water-resistive barrier (WRB) can also be used. Apron should extend to the outside of the bump-out frame and far enough below the rough opening to overlap the sill plate or WRB below. Apron must overlap the WRB below a min. 6. Door DuPont ThermaWrap R5.0 Apron Sill Flashing Jamb Flashing DuPont StraightFlash (1) (1) DuPont Flashing Tape can be substituted for DuPont StraightFlash DuPont Tyvek Tape Sill width Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 41
42 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 2 FLEXWRAP NF INSTALLATION Preparation of sill flashing: A. Cut piece of FlexWrap NF at least 12 LONGER than the width of the sill (S). B. FlexWrap NF has perforated release paper to help with the formation of the back dam. To ensure that the perforation tears cleanly, fold the perforation 180 and crease the flashing. C. Remove the two widest pieces of release paper leaving the narrowest release paper on the flashing. When the finished floor is applied, the release paper can be removed and the back dam can be completed. 6-inch for 2x4-inch studs 9-inch for 2x6-inch studs B Overlap Perf A Break Perf C Peel Off 2-pieces of Backing Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 42
43 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 3 (OPTIONAL BACK DAM) Install the sill flashing as indicated leaving the 1 of FlexWrap NF with release paper extending it past the door threshold on the inside. When the 1 of release paper is removed, there should be 3/4 of flashing to form the back dam. OPTION 2: Some flooring cannot accomodate a back dam. In that case fold the 1 back dam on top of FlexWrap NF in the sill. Door will be installed on top of the 1 fold to create a back dam. EXTERIOR INTERIOR Door Door Threshold Transition Threshold Flooring Optional No Gap in Corner DO NOT STRETCH WRONG Door Jamb FlexWrap NF Sill CORRECT FRONT VIEW CORNER DETAIL DuPont StraightFlash Insulated Batten CT High Pressure Skirt (See Step 6 Optional) SIDE VIEW DETAIL DuPont FlexWrap NF Sheathing DuPont Tyvek ThermaWrap R5.0 Sub Floor Corner Guard (Optional) Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 43
44 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 4 A. Fan out FlexWrap NF at bottom corners onto the face of the wall. Coverage of FlexWrap NF should be 2 to 3 onto the face of the wall. A Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 44
45 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 5 STRAIGHTFLASH VF INSTALLATION A. Prepare head flashing by cutting a piece of StraightFlash VF at least twelve (12) inches LONGER than the head length. B. Break the scored release paper on one edge of the head flashing by folding it back and forth upon itself. C. Center the StraightFlash VF along the length of the door head and position so that it contacts the door frame and interior side of the brick mold or flange. Remove the outer release paper and adhere the flashing to the door frame. Use the inner release paper to form a tight seal in the corner. D. Remove the inner release paper strip and adhere the flashing to the back of the brick mold or flange. E. Beginning at the junction of the jamb and head, and away from the corner, cut the StraightFlash VF at a 45 angle. F. Fold the newly created flashing flap down flat against the brick mold or flange. G. Fold remaining head flashing flaps down onto the jamb frame. A A C D E A F G Brick Mold Door Interior Door Interior Door Interior Door Interior Scored Release Paper Butyl VIEW A-A Door Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 45
46 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 6 A. Prepare jamb flashing by cutting a piece of StraightFlash VF at least six (6) inches LONGER than the jamb. B. Break the scored release paper on one side of the jamb flashing by folding it back and forth upon itself. C Position so that the StraightFlash VF contacts the door frame and interior side of the brick mold. Ensure that the jamb flashing is positioned 1-1/2 inch below the top edge of the head flashing. Jamb flashing adhesive must come in contact with head flashing adhesive by one inch. D. Remove the outer release paper and adhere the flashing to the door frame. Use the inner release paper to form a tight seal in the corner. E. Remove the inner release paper and adhere the flashing to the back of the brick mold. F. Repeat on for opposite jamb. STEP 7 A. Beginning at the junction of the jamb and head and beginning at the junction of the jamb and sill, and away from the corner, cut the StraightFlash VF along both corners at a 45 angle. B. Fold newly created flaps down flat against the head flashing. C. Fold newly created flaps down onto the head and sill of door frame. A B C C 1-1/2 Make sure the adhesive on these pieces will overlap. C 1-1/2 E C A Door Interior Door Interior Door Interior Door Interior Door Interior Door Interior D Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 46
47 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 8 (OPTIONAL - HIGH PRESSURE SKIRT) For extreme weather conditions, performance requirements exceeding ASTM E1677, or window/door design ratings of DP45 or greater, see General Instructions. A. Create the high pressure skirt by cutting a piece of Tyvek WRB 1 wider than the width of the door opening and approximately 10 in height. B. Cut a piece of StraightFlash VF to the same width of skirt. Remove release paper from one side of StraightFlash VF and adhere to Tyvek WRB. The skirt may be made with StraightFlash VF, StraightFlash or Flashing Tape. C. Remove the release paper from the other side of StraightFlash VF and adhere the butyl adhesive at the sill skirt to the underside of the door threshold behind the jamb flashing. D. Secure edges of the optional skirt with two 4 pieces of StraightFlash or Flashing Tape. E. Tape the bottom of the optional skirt to allow for drainage and to minimize wind damage during construction. F. If sealant is applied to the sill, insure (2) 2 gaps to allow for drainage for every 4 of door using Residential Sealant, or other sealant. DuPont StraightFlash VF B Butyl Adhesive 10 A C Peel Off Release Paper and attach to underside of door F D Optional High Pressure Skirt D E Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 47
48 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 9 DOOR INSTALLATION A. Install door according to manufacturer s installation instructions. B. Remove the remaining release paper from the StraightFlash VF jamb flashing and press firmly to adhere it to the exterior sheathing or framing members. C. Remove the release paper at the head and adhere it to the exterior sheathing or framing members. OPTIONAL: Cover exposed butyl with StraightFlash, Flashing Tape or Tyvek Tape. STEP 10 (OPTIONAL) A. Cut a piece of metal or vinyl drip cap slightly longer than the width of the door and place a bead of Residential Sealant, Commercial Sealant, or recommended sealant on the rear side. Install the drip cap tight against the door head and cover the top edge with StraightFlash or Flashing Tape. A C B Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 48
49 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 11 EXPOSING THE DOOR After installing the Tyvek WRB, cut as shown to expose door and apron. (Refer to the page 12 to install the Tyvek ThermaWrap R5.0 properly). DO NOT CUT THROUGH THE DUPONT FLASHING SYSTEMS PRODUCTS OR APRON. STEP 12 TERMINATING THE TYVEK THERMAWRAP R5.0 AROUND THE WINDOW A. Tape seams as shown. DO NOT TAPE at bottom of window. At the head, continuous tape seams as shown with Tyvek Tape. B. Lap bottom of apron and the Tyvek WRB over building materials below for proper shingling. DO NOT CUT through DuPont Flashing Systems Products or apron. Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 49
50 Tyvek ThermaWrap R5.0 Installation Guidelines ALTERNATE TAPE DETAIL Place a continuous bead of Residential Sealant, Commercial Sealant, or recommended sealant around the jamb and head flashing under the Tyvek WRB. Press the Tyvek WRB securely into the sealant. STEP 13 Final Step A. When the interior flooring is ready to install, remove release paper and use Folding Option One or Two to form back dam. B. Install Residential Sealant, Commercial Sealant, or recommended sealant (and backer rod as necessary) around the window opening at the interior. It is also acceptable to use Window & Door Foam or recommended foam. The seal created by the sealant (and backer rod as necessary) or foam will also serve as a back dam. Residential Sealant or other sealant should be tooled flat to allow the natural curing process to create a concave shape. Be sure that the sealant penetrates the grooves of the FlexWrap NF around the sill. NOTE: Installations that specify a window/door design rating of DP45 or greater require extra precautions. See General Instructions for performance requirements exceeding this design rating. Folding Option One Folding Option Two OR Fold Out and Up Fold In and Up Fastening Option One Fastening Option Two OR Staples Tape Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 50
51 Tyvek ThermaWrap R5.0 Installation Guidelines Flashing Pipe Penetrations Drilling through Tyvek ThermaWrap R5.0 will damage the insulation. Use appropriate size boxes to compensate for the thickness of the Tyvek ThermaWrap R5.0 STEP 1 Make a small cut in the Tyvek ThermaWrap R5.0. Expose wall sheathing and drill hole for pipe. STEP 2 Install pipe and trim Tyvek ThermaWrap R5.0 around the perimeter. STEP 3 Install Tyvek FlexWrap NF starting with a piece at the bottom STEP 4 Install a second piece of Tyvek FlexWrap NF at the top ensuring it overlaps the bottom piece a minimum of 2. STEP 5 Tape a piece of Tyvek over the FlexWrap FlexWrap NF Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 51
52 Tyvek ThermaWrap R5.0 Installation Guidelines Flashing Electrical Box NOTE: Different size electrical box or extensions may be required to compensate for thickness of Tyvek ThermaWrap R5.0 STEP 1 Make a small cut in the Tyvek ThermaWrap R5.0. Expose sheathing and drill hole for wire. STEP 2 Pull wire through insulation and box. Secure box to the exterior of the structure. STEP 3 Install Tyvek FlexWrap NF starting with a piece at the bottom. STEP 4 Install a piece of Tyvek FlexWrap NF at the top ensuring it overlaps the bottom piece a minimum of 2. STEP 5 Tape a piece of Tyvek WRB over the FlexWrap FlexWrap NF FlexWrap NF Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 52
53 Tyvek ThermaWrap R5.0 Installation Guidelines Flashing Dryer Vent STEP 1 Make a small cut in the Tyvek ThermaWrap R5.0. Expose sheathing and drill hole for penetration. STEP 2 DuPont recommends all penetrations greater than 1 inch in diameter have a bump-out installed to accommodate a nailer for the cladding. Create a bump-out using 2 pieces of Insulated Batten CT and cut the profile of the penetration. Insert the pieces behind the Tyvek ThermaWrap R5.0 and secure. STEP 3 Flash the lower half of the opening using FlexWrap NF. The FlexWrap should extend to the back of the opening and a minimum of 2 must extend on to the front of the wall. FlexWrap NF STEP 4 Insert the dryer vent and secure. Flash both sides of the vent followed by the top with product. STEP 5 Tape a piece of Tyvek WRB over the top piece of flashing. FlexWrap NF FlexWrap NF Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 53 FlexWrap NF
54 Tyvek ThermaWrap R5.0 Installation Guidelines Handling Tears and Holes During the course of installing Tyvek ThermaWrap R5.0, minor tears may occur. Be sure to tape all tears. Tears can easily be covered with Tyvek Tape (2 or 3 ) or Products. Larger holes (greater than 1 ) may require cutting a piece of Tyvek water resistive barrier (WRB) to cover the hole, maintaining proper shingling. Replace any missing insulation with a piece of Tyvek ThermaWrap R5.0 insulation, by removing it from the Tyvek top sheet. Cut a slit 2 above the hole and extending a minimum of 2 on each side of the hole. Measure and cut a piece of Tyvek WRB to fit into the slit and cover the hole. Tuck the cut piece of Tyvek WRB into the slit. Tape along the perimeter by starting at the bottom of the patch, shingling upper tape over bottom tape. Tears 1 1 Holes minimum Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 54
55 Tyvek ThermaWrap R5.0 Installation Guidelines Cladding Installation Install cladding per manufactures guidelines and code requirements. Fasteners must be 1-1/2 longer to compensate for the thickness of the Tyvek ThermaWrap R5.0 and to meet the required penetration into the structural member. Stud Sheathing Vinyl Cladding Installation When installing cladding fasteners, do not compress the Tyvek ThermaWrap R5.0. Compressing the product will reduce the thermal resistance. Use the Vinylign Nail Depth Regulator to help control the depth of the fastener during vinyl siding installation. STEP 1 Install trim around windows,doors, penetrations, interior and exterior corners, gables, etc. Tyvek ThermaWrap R5.0 Siding Fastener Fasteners must be of sufficient length to penetrate through to stud. Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 55
56 Tyvek ThermaWrap R5.0 Installation Guidelines STEP 2 Install starter strip at base of wall. If alternate bottom of wall detail termination ledge is used, be sure to not compress the Tyvek ThermaWrap R5.0. STEP 3 Install cladding. Do not compress Tyvek ThermaWrap R5.0. Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 56
57 Tyvek ThermaWrap R5.0 Installation Guidelines Brick and Stone Installation 1. Install mortar dropping collection device if needed 2. Use standard brick ties and fasteners. The installation of brick ties will compress the Tyvek ThermaWrap R5.0 but will not significantly affect the overall R-value of the wall. 3. Install brick Tyvek ThermaWrap R5.0 Brick tie Tyvek Tape Mortar dropping collection device Tyvek ThermaWrap R5.0 uninsulated flap Through wall flashing Foundation Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 57
58 Tyvek ThermaWrap R5.0 Installation Guidelines Cladding Transition INSTALLATION A. Install bump-out at transition B. Install metal flashing over bump-out C. Install flashing on metal flashing/wood sheathing D. Refer to page 12 for Tyvek ThermaWrap R5.0 installation E. Refer to page 55 for cladding installation A B E C D Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 58
59 Tyvek ThermaWrap R5.0 Installation Guidelines Cladding Considerations Water-resistive barrier performance is dependent upon the ability of the facade to drain. The following must be considered for specific facades. Brick The 2012 International Residential Code (Section R ) requires a nominal 1 inch airspace separating the brick from the water-resistive barrier (WRB). The Brick Industry Association recommends a 1 inch air-space in front of wood stud construction and a 2 inch air-space in front of steel stud construction. Consistent with these requirements and recommendations, Tyvek WRBs shall be separated from the brick veneer by a nominal 1 inch air-space. Window and door flashing, and through-wall flashing shall be integrated with the Tyvek WRB layer ensuring proper shingling. For maximum moisture management and drying of the wall system the airspace in front of the Tyvek WRB shall be vented to the exterior at the top and bottom of the wall. Some types of brick ties will act as additional fasteners for Tyvek WRBs, and, if installed as soon as practically possible after the Tyvek WRB, may reduce the required number of fasteners used for the initial attachment of the Tyvek WRB. Vinyl Siding Vinyl Siding is installed directly over Tyvek WRBs. Vinyl siding shall be installed in accordance with manufacturer s instructions, industry standards and applicable codes, including ASTM D Standard Practice for Installation of Rigid Poly(Vinyl Chloride) (PVC) Siding and Soffit. In high wind areas at gable end walls, FEMA recommends vinyl siding be installed over wood sheathing rather than over plastic foam sheathing. Copyright 2016 E. I. du Pont de Nemours and Company. All Rights Reserved. K27290 Version 1/16 59
60 Technical Specifications Tyvek WRBs used in construction products are made from 100% flash spunbonded high density polyethylene fibers which have been bonded together by heat and pressure, without binders or fillers, into a tough, durable sheet structure. Additives have been incorporated into the polyethylene to provide ultraviolet light resistance. DuPont requires that Tyvek ThermaWrap Rv5.0 be covered within four months (120 days) of installation. self-adhered flashing products are made from a synthetic rubber adhesive and a laminate of polyethylene film, polypropelene film, elastic fiber, synthetic rubber adhesive, polyurethane adhesive, and a top sheet of flash spunbonded high density polyethylene fibers or polypropelene film. Additives have been incorporated into these materials to provide ultraviolet light resistance. DuPont requires that products be covered within four months (120 days) of installation. Warning Tyvek air and water barriers are slippery and should not be used in any application where it will be walked on. In addition, because they are slippery, DuPont recommends using kickjacks or scaffolding for exterior work above the first floor. If ladders must be used, extra caution must be taken to use them safely by following the requirements set forth in ANSI Standards 14.1, 14.2 and 14.5 for ladders made of wood, aluminum, and fiberglass, respectively. Tyvek products are combustible and should be protected from a flame and other high heat sources. Tyvek products will melt at 275 F (135 C); if the temperature of Tyvek products reaches 750 F (400 C), it will burn and the fire may spread and fall away from the point of ignition. For more information, call Tyvek. self-adhered flashing products and their release paper are slippery and should not be walked on. Remove release paper from work area immediately. products will melt at temperatures greater than 250 F (121 C). products are combustible and should be protected from flames and other high heat sources. products will not support combustion if the heat source is removed. However, if burning occurs, ignited droplets may fall away from the point of ignition. For more information, call Tyvek. Residential Sealant is irritating to skin, eyes, and respiratory tract. For proper usage, follow directions stated on the product label. For health information, refer to the Material Safety Data Sheet or call Chemtrec at Note When installed in conjunction with other building materials, self-adhered flashing products must be properly shingled with these materials such that water is diverted to the exterior of the wall system. Tyvek ThermaWrap R5.0 is not the primary water barrier. The outer facade is the primary barrier. You must follow facade manufacturer s installation and maintenance requirements for all facade systems in order to maintain water holdout properties and ensure performance of Tyvek products. Use of additives, coatings or cleansers on or in the facade system may impact the performance of Tyvek ThermaWrap R5.0. Tyvek Weatherization Systems products are to be used as outlined in this installation guideline. products should only be used to seal penetrations and flash openings in houses or buildings. products are not to be used in roofing applications. For superior protection against bulk water penetration, DuPont suggests a system combining a quality exterior facade, a good secondary WRB and exterior sheathing, high quality windows and doors, and appropriate flashing materials paying attention to proper installation of each component. DuPont believes this information to be reliable and accurate. This information may be subject to revision as additional experience and knowledge is gained. It is the user s responsibility to determine the proper construction materials needed on each project. For complete warranty information, please visit or call Tyvek. This information is not intended to be used by others for advertising, promotion or other publication for commercial purposes. R-value The higher the R-value, the greater the insulating power. Ask your seller for the fact sheet on R-values. Tyvek ThermaWrap R5.0 uses a blanket insulation made of polyester and polyolefin fibers and will produce an R5.0 insulating value at a thickness of 1.5 inches. For more information about DuPont Weatherization Systems, please call Tyvek or visit us at Copyright 2016 E. I. du Pont de Nemours and Company. All rights reserved. The DuPont Oval Logo,, The miracles of science, Tyvek, HomeWrap, ThermaWrap, FlexWrap, StraightFlash, and Vinylign are registered trademarks or trademarks of DuPont or its affiliates. K /16
DuPont Tyvek ThermaWrap R5.0 Installation Guidelines for New Construction Using Stone Veneer or Lap Siding, e.g. Fiber Cement and Wood/Cedar
Tyvek ThermaWrap R5.0 Installation Guidelines for New Construction Using Stone Veneer or Lap Siding, e.g. Fiber Cement and Wood/Cedar VERSION 1/16 FOR SINGLE FAMILY HOMES AND LOW-RISE MULTI-FAMILY BUILDINGS
DuPont Tyvek ThermaWrap R5.0 Installation Guidelines for New Residential Single Family Houses Using Vinyl, Brick and Stone Claddings VERSION 10/13
DuPont Tyvek ThermaWrap R5.0 Installation Guidelines for New Residential Single Family Houses Using Vinyl, Brick and Stone Claddings VERSION 10/13 Table of Contents Applicable Products... 2 Recommended
DuPont Flashing Systems Installation Guidelines
Installation Instructions for Integral Flanged Door FTER Water-Resistive Barrier (WRB) is Installed DuPont Flashing Systems Installation Guidelines INSTLLTION INSTRUCTIONS FOR INTEGRL FLNGED DOOR FTER
DuPont Tyvek Water-Resistive and Air Barriers Installation Guidelines
DuPont Tyvek Water-Resistive and Air Barriers Installation Guidelines DuPont Tyvek Water-Resistive and Air Barriers Installation Guidelines HELPING YOU GET THE JOB DONE RIGHT FOR BUILDINGS LESS THAN 5
Sun Windows General Information Sun New Construction Window Installation Instructions
Sun Windows General Information Section 1 G F H H H A. Apply Weather Resistive Barrier B. Apply Sill Flashing Tape C. Place Waterproof Sill Shims D. Caulk Back of Nail Fin Sides & Top, Set Window, Fasten
GreenGuard Housewrap Installation Guide
000768PACBPHW_Flashing Bro 5/23/03 2:52 PM Page 1 For the most current product information, go to www.green-guard.com. Pactiv Building Products believes the information and recommendations herein to be
Tundra Series Windows January 2016
Tundra Series Windows January 2016 New Construction Installation Instructions Nail Fin, J-Fin and Brickmold Aplications product. ATTENTION! Read and understand all installation instructions before installing
Window Installation Instructions
Caution The correct installation methods of windows in full frame or insert applications is critical towards achieving the tested performance of the window and longterm enjoyment and energy savings for
WINDOW INSTALLATION GUIDE FOR NEW CONSTRUCTION - WOOD FRAMING
WINDOW INSTALLATION GUIDE FOR NEW CONSTRUCTION - WOOD FRAMING IMPORTANT NOTICES AND INFORMATION Read these instructions in their entirety prior to installing windows. Any local building code requirements
Clad Direct Glaze Window Installation Instructions
Clad Direct Glaze Window Installation Instructions Sill flashing and sealing: 2. An overview of the proper flashing sequence is shown in figure 1. Please read entire installation instructions carefully
WELCOME. Recommended Window Installation. 1.5 credits Minnesota Department of Labor and Industry
WELCOME Recommended Window 1.5 credits Minnesota Department of Labor and Industry In accordance with the Department of Labor and Industry s statute 326.0981, Subd. 11, This educational offering is recognized
INSTALLATION INSTRUCTIONS for Vinyl Windows with Integral Nailing Fin (JII001)
Thank you for selecting JELD-WEN products. Attached are JELD-WEN s recommended installation instructions for Vinyl windows with an integral nailing fin. While the use of these installation instructions
How To Repair A Boat Landing Deck With A Boat Bed
RESIDENTIAL INSULATED SHEATHING INSTALLATION GUIDE Residential Insulated Sheathing Installation Guide ROXUL COMFORTBOARD IS Table of Contents Slab-on-grade-to Above Grade Wall...1 Foundation Wall at Footing
Residential Roofing Guide
Residential Roofing Guide TABLE OF CONTENTS Building Detail and Accessories...... 1 Panel Introduction and Handling...... 2 Cutting and Trimming.... 3 Roof Preparation..... 3 Roof Slope..... 3 Re-roofing...
Installation Instructions Double-Hung, Single-Hung, Casement, Awning, Sliding, Picture & Shapes Non-Impact & Impact Resistant Nailing Fin Windows
Installation Instructions Double-Hung, Single-Hung, Casement, Awning, Sliding, Picture & Shapes Non-Impact & Impact Resistant Nailing Fin Windows americancraftsmanwindows.com Project Requirements: Read
PANELIZED HOME INSTALLATION GUIDELINE
PANELIZED HOME INSTALLATION GUIDELINE A typical home package will be constructed of Snap-N-Lock Insulated Panels clad with steel skins. 4" panels will be used for the walls, and 6" panels for the roof.
Asphalt Shingle Application Requirements
Alberta Allied Roofing Association Asphalt Shingle Application Requirements Section 1 Roof Decks 1.1 General Asphalt Shingles are not permitted to be installed directly over rigid insulation. When Asphalt
application instructions
application instructions ARCHITECTURAL COLLECTION PRIMED BOLD PROFILE 120 SERIES LAP SIDING (D5, T4, D8, T5, Q4) General At the time of manufacture, siding meets or exceeds the performance standards set
300mm. 2mm MIN GAP. PLACE 100mm X 100mm. SO THAT IT IS 38mm INTO
INSTALL PEEL & STICK (P&S) GUSSETS WITH PRIMER AS PER MANUFACTURERS INSTRUCTIONS 2mm MIN GAP IN SHEATHING STEP 1 PLACE 100mm X 100mm PIECE OF P&S IN CORNER SO THAT IT IS 38mm INTO THE OPENING EACH WAY
SUPER SHED. Indoor shelter for your outdoor tools.
SUPER SHED Indoor shelter for your outdoor tools. Not everyone needs a garden shed. But, if you've no more space on your garage wall for that new leaf rake, if you can't find your potting trowel because
Chapter 9: INSTALLING ROOFING
9.1 LEAK BARRIER (ICE AND WATER SHIELD) 9.2 SHINGLE UNDERLAYMENT 9.3 INSTALLING GUTTER APRON AND GABLE D-EDGE 9.4 INSTALLING SHINGLES 9.5 RIDGE VENT AND CAP Tools needed by each volunteer: Hammer (16 oz.
The better way to build TM. Installation Manual. FOUNDATION SIPs & FROST WALLS SIPs
The better way to build TM Installation Manual FOUNDATION SIPs & FROST WALLS SIPs February 2016 PWF FOUNDATION & FROST WALL SIPs Installation Manual Table of Contents Topics General Requirements...................................
Envelope INSULATION BATT (2) Avoid Using Batt Insulation With Metal Framing. Pressure or Friction Fit
R-H-DI1 INSULATION BATT NR-E-IB1 Avoid Using Batt Insulation With Metal Framing Batt insulation should not be used with metal framing systems. Although it is common to see fiberglass batt insulation installed
INSTALLATION OF A BAY WINDOW
INSTALLATION OF A BAY WINDOW Installation of a Bay Window These instructions relate to the replacement of an existing bay window or replacement of a straight window with a new bay window, in an opening
NEW ELECTRICAL SUBSTATION Building 300 SECTION 07 53 23 ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING WORK
ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING WORK PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within
The WANZ Guide to Window Installation
The WANZ Guide to Window Installation as described in E2/AS1 Amendment 5 Ver. 1.1 Page 2 of 74 Contents Overview Page 5 Objective Page 5 Scope Page 5 Opening Preparation Page 7 Step P1 Preliminary Check
Free 12 x 8 Shed Plan With Illustrations, Blueprints & Step By Step Details
Free 12 x 8 Shed Plan With Illustrations, Blueprints & Step By Step Details Brought To You By: MyShedPlans Click Here To Download 12,000 Shed Plans >> 12 x 8 Basic Shed This 8 12-ft. shed features a simple
Stormproof Your Roof. I ve done enough roof repairs to know that storm water that gets past the shingles
Stormproof Your Roof Self-adhering underlayment provides critical protection in vulnerable locations BY MIKE GUERTIN I ve done enough roof repairs to know that storm water that gets past the shingles and
Best Barns USA Assembly Book
Best Barns USA Assembly Book Revised November 27, 2013 the Easton - R 12'x 20' Manufactured by Reynolds Building Systems, Inc. 205 Arlington Drive Greenville, PA 16125 724-646-3775 This manual is copyrighted.
DRAINAGE MATS For Vertical: Flow 15-P For Horizontal: Flow 18-H
DRAINAGE MATS For Vertical: Flow 15-P For Horizontal: Flow 18-H Soil Drainage Mat with Built-In Protection Layer POLYGUARD DRAINAGE MATS are three-part prefabricated geocomposite drain consisting of a
Superform Products Ltd.
TYPICAL CORNER REINFORCING NOTE : SEE ENGINEERED REBAR SCHEDULES SUPPLIED BY THE MANUFACTURER STEEL REINFORCEMENT WALL CORNER 90 Copyright 2012 Sept. 2012 5.1.1 Rebar Spacing 6" 12" Max. Load LB./FT. 2000
HfHMD uses LP SmartSide siding and trim.
HfHMD uses LP SmartSide siding and trim. These products are: More durable than cement fiber board. Much more volunteer-friendly to install. When installed correctly, have a 5/50- year pro-rated warranty.
Installation Guide for Andersen Architectural Clad Outswing Commercial Doors
Installation Guide for Andersen Architectural Clad Outswing Commercial Doors Congratulations! You have just purchased one of the many fine Andersen products. Proper assembly, installation and maintenance
INSTALLATION INSTRUCTIONS for Vinyl Windows with Integral Nailing Fin (JII001) IMPORTANT INFORMATION AND GLOSSARY ROUGH OPENINGS
Thank you for selecting JELD-WEN products. Attached are JELD-WEN s recommended installation instructions for Vinyl windows with an integral nail fin. Not all window types may be installed into every wall
March 14, 2007. Installation of Bay, Bow and Garden Windows
March 14, 2007 Re: Installation of Bay, Bow and Garden Windows Attached are the Atrium Companies, Inc recommendation for the installation of bay, bow and garden windows. These instructions were developed
INSTALLATION INSTRUCTIONS for Vinyl Patio Doors with Integral Nailing Fin (JII006)
Thank you for selecting JELD-WEN products. Attached are JELD-WEN s recommended installation instructions for Vinyl Patio Doors with nailing fin. Any local building code requirements supersede the recommended
PREMIUM LAMINATED ASPHALT SHINGLES Dallas, TX Tuscaloosa, AL Phillipsburg, KS
Application Instructions for THESE ARE THE MANUFACTURER S APPLICATION INSTRUCTIONS FOR THE ROOFING CONDITIONS DESCRIBED. TAMKO BUILDING PRODUCTS, INC. ASSUMES NO RESPONSIBILITY FOR LEAKS OR OTHER ROOFING
DE Frame with C Series Sidelight
TOOLS REQUIRED Tape measure 6' magnetic level 3' magnetic level Screw gun with clutch adjusted #2 phillips tip #3 phillips tip Screwdriver (used to adjust frame on will using oval slots) Pry Bar Powder
INSTALLATION INSTRUCTIONS for Vinyl Windows without Nailing Fin (JII011) ImPOrTANT INFOrmATION & GlOssAry. rough OPeNINGs
Thank you for selecting JELD-WEN products. Attached are JELD-WEN s recommended installation instructions for vinyl windows without a nailing fin (including finless, flush fin and flange). Read these instructions
!!!!!! !!! Decra Plus DPSW010 DPSTW011 DPSW012 DPSW013 DPSW014 DPSW015 DPSW016 DPSW020 DPSW021 DPSW024 DPSW030 DPSW031 DPSW035 DPSW030 DPSW031 DPSW035
Decra Plus Drawing no DPSW010 DPSTW011 DPSW012 DPSW013 DPSW014 DPSW015 Description Shown In Decra Brochure Most Commonly Used Detail t~êã=oççñ=b~îéë=aéí~áä=b~îéë=lîéêü~åö=táíü=fåëìä~íéç=c~ëåá~=~åç=pçññáí
VA25014B0516 VA CINCINNATI PROJECT NO. 539-328 INPATIENT BED TOWER ADDITION (4 TH AND 5 TH FLOORS) SECTION 09 29 00 GYPSUM BOARD
SECTION 09 29 00 GYPSUM BOARD PART 1 - GENERAL 1.1 DESCRIPTION This section specifies installation and finishing of gypsum board, vapor retarder and air and moisture barrrier. 1.2 RELATED WORK A. Installation
INSTALLATION INSTRUCTIONS IMPERVIA (Vent and Fixed) AWNING, CASEMENT, and LARGE AWNING WINDOW WITH FINS
2009 Pella Corporation INSTALLATION INSTRUCTIONS IMPERVIA (Vent and Fixed) AWNING, CASEMENT, and LARGE AWNING WINDOW WITH FINS Part Number: 80WH0100 Installation Instructions for Typical Wood Frame Construction.
How to Install UnderDeck The Original.
How to Install UnderDeck The Original. TOOLS: Chalk Line Caulk Gun Garden hose or water bucket Gloves Hammer or Screw Gun Power Mitre Saw with OSB Blade Pencil Pliers Safety Glasses Straight Edge / Carpenter
Directions For Applying Malarkey Laminate Shingles
S Laminate Shingle Instructions 1 Directions For Applying Malarkey Laminate Shingles GENERAL INSTRUCTIONS Install Malarkey laminate shingles according to building code and local amendments. To qualify
Replacement Window Installation Guide Non-Impact & Impact Resistant Windows without Nailing Fin
Replacement Window Installation Guide Non-Impact & Impact Resistant Windows without Nailing Fin americancraftsmanwindows.com Project Requirements: Failure to follow these instructions may void product
Read and understand all installation instructions and precautions before installing. GENERAL APPLICATION INSTRUCTIONS
AC TOPSEAL SELF-ADHERED, GRANULAR SURFACED, SINGLE PLY, LOW SLOPE ROLLED ROOFING 3 X 33.3 = 100 SQ. FT. 10 YEAR MATERIAL LIMITED WARRANTY For Use on Porches / Sheds / Utility Buildings / Accessory Buildings
SLIDING PATIO DOOR INSTALLATION INSTRUCTIONS USING FRAME SCREWS
Vinyl Windows and Doors Manufactured by Pella Corporation Part Number: V984528 2012 Pella Corporation SLIDING PATIO DOOR INSTALLATION INSTRUCTIONS USING FRAME SCREWS Installation Instructions for Typical
G VYCOR DECK PROTECTOR
G VYCOR DECK PROTECTOR Self-Adhered Flashing Contractor s Guide DECKS AND DETAIL AREAS For longer lasting decks, install Grace Vycor Deck Protector. FROM THE MAKERS OF G Ice & Water Shield What Self-Adhered
Storage Store the siding in a dry and ventilated area. Do not place it directly on the ground. Always cover the siding after a day s work.
Installation Guide Before you begin, take the time to read this entire guide to clearly understand the requirements and steps to follow for proper installation. Warning Do not install defective material.
Shingle Installation Guide
Shingle Installation Guide Getting Started Dedicated to improving the environment, NewTech manufactures roofing tiles that are composed of up to 90% recycled post-industrial plastic. The manufacture of
CERTIFICATE NAME OF PRODUCT MANUFACTURER PRODUCT DESCRIPTION CERTIFICATION PROCEDURE. No VTT C-6044-10 Date of issue 11.10.2010, Updated July 1, 2011
CERTIFICATE NAME OF PRODUCT No VTT C-6044-10 Date of issue 11.10.2010, Updated July 1, 2011 H-CONTROL REFLEX+ reflective insulating vapour control layer for roof and wall applications MANUFACTURER ACTIS
RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000
RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 SECTION R905 REQUIREMENTS FOR ROOF COVERINGS R905.1 Roof covering application. Roof coverings
Composite Stone Veneer
Composite Stone Veneer Installation Guide Ver 1 Jun 2015 www.compstone.com Composite Stone Veneer Installation Guide Contents Introduction & Overview 3 Required Tools 4 Optional Tools 4 Attachment Guidelines:
The WANZ Guide to Window Installation
The WANZ Guide to Window Installation as described in E2/AS1 Amendment 5 2 of 60 Contents Overview 5 Objective 5 Scope 5 Opening Preparation 7 Step P1 Preliminary Check 8 Step P2 Cut the Underlay 9 Step
AAMA 2400-10. Standard Practice for Installation of Windows with a Mounting Flange in Open Stud Frame Construction for Low Wind/Water Exposure
A M E R I C A N A R C H I T E C T U R A L AAMA 2400-10 Standard Practice for Installation of Windows with a Mounting Flange in Open Stud Frame Construction for Low Wind/Water Exposure M A N U F A C T U
We urge you to read and follow the attached installation instructions. Failure to do so may void the warranty of this garden window unit.
Important Information for New Construction Installations Attention Installer! We urge you to read and follow the attached installation instructions. Failure to do so may void the warranty of this garden
Classic Products, Inc. ClickLock Standing Seam Installation Manual
Classic Products, Inc. ClickLock Standing Seam Installation Manual Classic Products, Inc. 8510 Industry Park Drive Piqua, OH 45356 800.543.8938 Table of Contents page Introduction 1. 1 Starter. 2. 1 Panels.
Final inspections are completed by site visit only. Access to fenced yards shall be planned.
ROOFING RESIDENTIAL BUILDING INSPECTIONS DEPARTMENT www.ci.blaine.mn.us This handout is intended only as a guide and is based in part on the 2015 Minnesota State Building Code, Blaine City ordinances,
DUPONT TYVEK BUILDING WRAPS VS. ZIP SYSTEM WALL SHEATHING
TECH TALK DUPONT TYVEK BUILDING WRAPS VS. ZIP SYSTEM WALL SHEATHING DuPont offers six different DuPont Tyvek building wraps intended for use on a wide range of buildings from single family homes to high
OLD BRICK ORIGINALS KILN-FIRED THIN BRICK VENEER Installation Guide. GeneralShale.com
OLD BRICK ORIGINALS KILN-FIRED THIN BRICK VENEER Installation Guide GeneralShale.com OLD BRICK ORIGINALS THIN BRICK VENEER Page 2 INTRODUCTION Check local building codes for proper installation guidelines
HERITAGE WOODGATE LAMINATED ASPHALT SHINGLES Dallas, TX
Application Instructions for THESE ARE THE MANUFACTURER S APPLICATION INSTRUCTIONS FOR THE ROOFING CONDITIONS DESCRIBED. TAMKO BUILDING PRODUCTS, INC. ASSUMES NO RESPONSIBILITY FOR LEAKS OR OTHER ROOFING
Installing Window and Door Mouldings
Installing Window and Door Mouldings About Window and Door Mouldings The trim around windows and doors greatly influences the look and style of your interior. They also bridge the gaps and cover spaces
HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES
HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES 101 Retrofits Required. Pursuant to Section 553.844 553.884, Florida Statutes, strengthening of existing site-built,
Installer Training and Certification Overview
Installer Training and Certification Overview Outline of This Presentation The Need for a Training Program The History of the Program Details of the Training Program The Certification Process The Need
INSTALLATION INSPECTION GUIDE FOR 3RD PARTY INSPECTORS FOR PAREX USA EXTERIOR INSULATION AND FINISH SYSTEMS
INSTALLATION INSPECTION GUIDE FOR 3RD PARTY INSPECTORS FOR PAREX USA EXTERIOR INSULATION AND FINISH SYSTEMS Introduction This inspection guide is organized to follow the EIF System's Installation Guide.
THIRD PARTY INSPECTION GUIDELINES FOR OWNERS AND GENERAL CONTRACTORS/CONSTRUCTION MANAGERS DS150
THIRD PARTY INSPECTION GUIDELINES FOR OWNERS AND GENERAL CONTRACTORS/CONSTRUCTION MANAGERS DS150 SECTION ONE A. Objective The objective of this guide is to provide Owners and General Contractors/Construction
Linea Weatherboard DIRECT FIX CONCRETE SLAB AND SOFFIT FIGURE 1
Top plate Stud Soffit lining 45mm min nog Fix scotia bead Building underlay/james Hardie rigid air barrier Soffit Detail Building underlay/james Hardie rigid air barrier Bottom plate 25mm wide cant strip.
CONTENTS. General conditions 2. Material requirements 3. Terms 4. Estimating shingle requirements 4. Roof preparation 6. Shingle application 9 - 1 -
CONTENTS General conditions Material requirements 3 Terms 4 Estimating shingle requirements 4 Roof preparation 6 Shingle application 9 Shingle Shingle application application guide guide - - b a 3a 3b
Avoiding Air Barrier Pitfalls
Avoiding Air Barrier Pitfalls Design & Durability November 2013 Air barriers, when correctly installed, help buildings achieve high levels of energy efficiency by decreasing heat loss. For example, great
DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 8 DOORS AND WINDOWS 08 50 00 WINDOWS
SECTION INCLUDES Metal Windows Vinyl/Aluminum Clad Wood Windows Solid Fiberglass and Vinyl Windows Wood Windows (Historic Preservation only) RELATED SECTIONS 02 83 00 Lead Paint Remediation 06 10 00 Rough
Brick Veneer Construction
Brick Veneer Construction Check list of suggested tools & support items Claw hammer Tape measure 3/4" [19 or 20] Wood chisel Wood or plastic shims Pry bar Utility knife Caulking and caulking gun Power
SHINGLE APPLICATION GUIDE
SHINGLE APPLICATION GUIDE CONTENTS 01. General conditions 01. Material requirements 02. Terms 07. Estimating shingle requirements 08. Roof preparation 10.Shingle application E version 2006 GENERAL CONDITIONS
Introduction...COMB-2 Design Considerations and Examples...COMB-3
SECTION DIRECTORY General Information Introduction...COMB-2 Design Considerations and Examples...COMB-3 Combination Assembly Recommendations and Limitations Composite Configurations...COMB-4 Typical Sealant
Housewrap Errors. By Steve Easley
Housewrap Errors By Steve Easley There Are Seven Common Mistakes Contractors Make When Installing Housewraps Green building and remodeling programs, the U.S. Environmental Protection Agency s IAQ Plus
INSTALLATION MANUAL For Grand Rib-3 / Multi Purpose / & Classic Rib Roofing Panels
INSTALLATION MANUAL For Grand Rib-3 / Multi Purpose / & Classic Rib Roofing Panels Grand Rib-3 / Multi-Purpose / Classic Rib Grand Rib-3 / Multi-Purpose / & Classic Rib Grand Rib 3 panels are a strong,
Installation Guide for Andersen Architectural Wood Inswing Entry Doors
Installation Guide for Andersen Architectural Wood Inswing Entry Doors Congratulations! You have just purchased one of the many fine Andersen products. Proper assembly, installation and maintenance are
INSTALLATION INSTRUCTIONS for Swinging French and Patio Doors (JII105)
Thank you for selecting JELD-WEN products. Attached are JELD-WEN s recommended installation instructions for Steel, Fiberglass, Vinyl, and Wood French and Patio Doors. Read these instructions thoroughly
INSTALLATION INSTRUCTION - INSTRUCCIONES DE INSTALACION FOR DOUBLE-HUNG VENT REPLACEMENT WINDOW
Vinyl Windows and Doors Manufactured by Pella Corporation INSTALLATION INSTRUCTION - INSTRUCCIONES DE INSTALACION FOR DOUBLE-HUNG VENT REPLACEMENT WINDOW Lea las instrucciones en español en el reverso.
STANDARD REQUIREMENTS FOR BONDING OR MECHANICAL ATTACHMENT OF INSULATION PANELS AND MECHANICAL ATTACHMENT OF ANCHOR AND/OR BASE SHEETS TO SUBSTRATES
ROOFING APPLICATION STANDARD (RAS) No. 117 STANDARD REQUIREMENTS FOR BONDING OR MECHANICAL ATTACHMENT OF INSULATION PANELS AND MECHANICAL ATTACHMENT OF ANCHOR AND/OR BASE SHEETS TO SUBSTRATES Scope 1.1.
H-Stud Area Separation Wall System
12 TH EDITION 09 21 16.33/NGC H-Stud Area Separation Wall System 09 21 16.33 139 H-STUD AREA SEPARATION WALL SYSTEM The fire-protection of gypsum-based Area Separation Walls is demonstrated in dramatic
ROOF CONSTRUCTION Roof Styles Gable Roof Hip Roof Gambrel Roof
ROOF CONSTRUCTION The overall appearance of a building is greatly affected by the roof lines and the roofing materials. The designer has many standard designs to choose from and should be able to find
CHAPTER 7: Building Systems ROOFING SYSTEMS
ROOFING SYSTEMS Purpose Examples 1. Shingle roof system 2. Metal roof with blanket insulation 3. Metal roof with rigid insulation 4. Built-up asphalt roof system 5. Single-ply roof system 6. Modified Bitumen
Barewood Octagon and Elongated Windows Installation Instructions
Step-by-step instructions to a beautiful window. Measuring and Installation of your new window from Century Specialty Windows couldn't be easier with our step-by-step instructions. Quality, function and
Comment Form on Proposed Gut Rehabilitation Alternatives
Comment Form on Gut Rehabilitation Alternatives Name: Organization: Email: Instructions Submission: Please submit this form to [email protected] by October 10 th, 2012 with the subject line
UNIT 4: SHEATHING AND SHINGLING THE ROOF
KEY CONCEPTS 1. Identify tools needed for roofing 2. Steps to finishing a roof 3. Maintenance of a roof 4. Safety while roofing INSTRUCTIONAL ACTIVITIES 1. Complete Follow Up Worksheet from Unit 3 2. Roof
Installation Instructions For Slider Casement Air Conditioners
Installation Instructions For Slider Casement Air Conditioners NOTE: These instructions describe installation in a typical wood framed window with a wood SLIDE-BY sash, or installation in a metal CASEMENT
Discount Direct Metal Roofing Plus Rib Roofing Panels Installation Instructions
Discount Direct Metal Roofing Plus Rib Roofing Panels Installation Instructions All questions and concerns please call 904-696-9700 Discount Direct Metal Roofing Plus Rib metal roofing panels are a strong,
INSTALLATION INSTRUCTIONS for Vinyl Patio Doors without Nailing Fin (JII015) IMPORTANT INFORMATION AND GLOSSARY
Thank you for selecting JELD-WEN products. Attached are JELD-WEN s recommended installation instructions for vinyl patio doors without nailing fin, including flush fin. Read these instructions thoroughly
WINDOW INSTALLATION GUIDE
WINDOW INSTALLATION GUIDE is not responsible for or liable for any use or misuse of the information contained in this window installation guide. Window Installation Guide This guide provides basic information
Basement Window Installation Guide Hopper and Sliding
Basement Window Installation Guide Hopper and Sliding americancraftsmanwindows.com Project Requirements: Installation must comply with all applicable building codes. Existing window frame, wall and weatherresistant
Section A Roof Truss
Section A Roof Truss Truss Types Wisconsin Truss, Inc. can build a variety of truss types, pictured below are some common examples. Common Bobtail Scissor Mono Studio Dual Slope Cathedral Tray Vault Parallel
Important Information for Installer & Homeowner
Important Information for Installer & Homeowner Homeowner: Please keep this information for your records, do not discard! Installation Instructions for Wood Frame Construction Replacement (See other side
METAL ROOFING INSTALLATION GUIDE
METAL ROOFING INSTALLATION GUIDE MIGHTY-RIB PBR (R-Panel) Regardless of whether your roofing project is a new installation or a re-roof, and whether your building is residential, commercial or agricultural,
2.9 WINDOW & DOOR BUCKS
2.9 WINDOW & DOOR BUCKS Bucks provide attachment surfaces for windows and doors while holding back concrete from these openings during concrete placement. Mark the center and edges of openings as you place
Fig. 2 WALL-TO-WALL PANEL CONNECTIONS CORNER WALL CONNECTION
SIPS SCREWS WITH MINIMUM 1" PENETRATION IN WOOD MEMBER IN SIP WALL PANEL CONNECTED TO @ 24" O.C. MAXIMUM OUTSIDE SKIN EACH SIDE OF FRAMING TYP. AS RECOMMENDED BY FOAM CORE AS EACH SIDE OF FRAMING TYP.
Built to Last. Built for Beauty. Good. Solid. Logix. TM
Built to Last. Built for Beauty. Good. Solid. Logix. TM Quality, Value and Service Introducing LOGIX Insulated Concrete Forms. Based on the simple concept of interlocking blocks, LOGIX ICF gives you a
Electrical Wiring Technical Bulletin
Electrical Wiring Technical Bulletin Overview In general, SIP construction is easier and more cost effective when things are planned and thought out before the panels are manufactured. This process will
We urge you to read and follow the attached installation instructions. Failure to do so may void the warranty of this garden window unit.
Important Information for New Construction Installations Attention Installer! We urge you to read and follow the attached installation instructions. Failure to do so may void the warranty of this garden