Company Header POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN. For [site name] [EPL number]
|
|
|
- Mervyn Riley
- 10 years ago
- Views:
Transcription
1 Company Header POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN For [site name] [EPL number]
2 Pollution Incident Response Management Plan for [insert site name] Contents [need to check correct page numbers] Contents [need to check correct page numbers] 2 1 OVERVIEW 3 2 EVALUATION 6 3 HAZARD, LIKELIHOOD AND PRE-EMPTIVE ACTIONS TO PREVENT POLLUTION INCIDENT RISKS Overview Summary of Pollution Types Use and Storage of Chemicals Safety Issues 3.3 Risk assessment and Control Measures (pre-emptive actions) Identification of Risk Areas 3.4 Risk Modules 4 MAPS 4.1 EPL site map for [insert site name] 5 EMERGENCY INCIDENT RESPONSE PROCEDURES Internal communications key names and contacts Action to be Taken Immediately after a Pollution Incident by License Holder and Occupier of the Premises Procedures to be followed by the Responsible Person notifying the Pollution Procedures to be followed for coordinating with the Authorities or Persons 5.2 Procedure to be followed for Combating the Pollution Caused by a Spill Incident 5.3 Procedure to be followed Following an Air Incident 5.4 External communications government agencies and other parties Co-coordinating, with the authorities Site Control Incident Response 5.5 Procedures for Notifying Pollution Incident to EPA, Local Councils or Relevant Authorities
3 6 EARLY WARNINGS AND COMMUNICATIONS TO NEIGHBOURS 6.1 Community Communication and Consultation 6.2 Website information 6.3 Availability and Location of This Plan 7 TRAINING SUMMARY AND REFERENCE TO PROJECT PROCEDURE 8 UPDATING OF PLAN 9 TESTING 10 IMPLEMENTATION OF THE PLAN APPENDIX 1 RISK MODULES APPENDIX 2 MAPS APPENDIX 3 Regulatory Requirements
4 1. OVERVIEW This Pollution Incident Response Management Plan (PIRMP or Plan) has been written to comply with the legislative requirements under the Protection of the Environment Operations Act 1997 (POEO Act) and the Protection of the Environment Operations (General) Regulation [Insert general info regarding site environmental management system and EPL] Under the legislation referred to above, the EPL also requires a PIRMP to clearly document pollution risks, communication procedures to authorities and community regarding pollution incidents, and testing and training for pollution response. If there is a pollution incident involving material harm or threatened material harm to human health or the environment, the PIRMP will be implemented. [confirm that material harm is the threshold for implementing plan could be lower than that] The PIRMP contains the following sections as required by the regulation: 1. Background describes main features of the regulation 2. Hazard, likelihood and pre-emptive actions to prevent pollution incident risks describes type of pollution incidents that may be possible and lists procedures that are already in place to minimise and manage pollution. Ranking of risks is included in appendices 3. Maps map of project to show location of potentially affected neighbours and environmentally sensitive areas 4. Emergency incident response procedures what to do in case of material harm 5. Early warnings and communication to neighbours when to contact neighbours in case of pollution incidents and info required for website 6. Training information to be passed on to staff and contractors 7. Updating of plan frequency of updates 8. Testing frequency of drills to test effectiveness of PIRMP 9. Implementing of plan reference to legislation requirement to carry out aspects of the plan during a pollution incident Introduction The [site name] is licensed to [insert specific details of EPL] This site is covered by an Environment Protection Licence (EPL) number [. ] for the scheduled activities [insert description of site activities from EPL] The site has an overarching environmental management system supported by [insert info regarding site or company procedures] Purpose The purpose of this PIRMP is to improve the way pollution incidents are reported, managed and communicated to the general community. The purpose of this plan is to: Ensure comprehensive and timely communication about a pollution incident to staff at the premises, the Environment Protection Authority (EPA), other relevant authorities specified in the Act (such as local councils, NSW Ministry of Health, WorkCover NSW, and Fire and Rescue NSW) and people outside the facility who may be affected by the impacts of the pollution incident
5 Minimise and control the risk of a pollution incident at the facility by requiring identification of risks and the development of planned actions to minimise and manage those risks Ensure that the plan is properly implemented by trained staff, identifying persons responsible for implementing it, and ensuring that the plan is regularly tested for accuracy, currency and suitability. Scope This PIRMP is for the use of all [site name] staff involved in the [insert activities that have potential for pollution incidents] and [company name] contractors undertaking works on the site. The PIRMP will be implemented only if material harm to human health or the environment occurs or threatens to occur [need to confirm if PIRMP will be implemented at a lower threshold or material harm threshold] The [site name] site is located at [site location] and holds EPL number [ ]. Environmental Management at the site is subject to improvements in processes and practices from time to time. To accommodate these ongoing changes and also to accommodate increases in site specific environmental assessment and management, the plan will be progressively reviewed. This Plan is to clearly define the requirements of [company name] staff to report and respond to pollution incidents in accordance with the 2011 and 2012 changes to the POEO Act 1997 and the POEO (General) Regulation 2010 Responsibilities All [company name] staff and contractors are responsible for understanding and implementing this PIRMP as appropriately identified. The PIRMP identifies the general roles and responsibilities of [company name] staff. [permanent contractors on site] shall manage pollution incidents in accordance with this PIRMP. [Supervisors and managers] are responsible for ensuring that their staff is aware of the PIRMP and their roles where appropriate. They are also responsible for the training of their staff [environment department or management section] is responsible for: assisting with advice, reporting and response process; ensuring the Plan is made available to staff responsible for implementing the plan and authorised officers under the POEO Act; giving advice on whether environmental incidents need to be reported to external agencies; assisting in the notification of pollution incidents to the relevant authorities provision of maps associated with the plan; assistance with the implementation of response actions to pollution incidents assistance in commutating with neighbours and the local community about the Plan and when incidents of a certain nature occur; ensuring that training responsible for activating about their roles in the Plan; testing; and Reviewing this plan.
6 Legal Branch [if legal branch exists] is responsible for providing legal advice, assisting with investigations of pollution incidents and preparation of reports for the Environment Protection Authority and other regulators for major incidents and ensuring legal compliance of the Plan. Documentation The environmental incident register [insert document or spreadsheet name] is used to record and monitor all environmental incidents within [company or site name]. The register will assist with record keeping, reporting and determining improvements to incident response and review of the Plan. The register is kept by the [insert title of person responsible for keeping register]. The Environment Manager [or insert other person] is responsible for monitoring and measuring the effectiveness of incident management and of this Plan. Additional Information Contact: Effective date: Review date: [insert title and phone number of person responsible for this plan] [date that plan is effective] See Updating of Plan
7 2. EVALUATION This Pollution incident Response management Plan (the Plan) complies with the requirements under the: POEO Act 1997 Part 5.7A Duty to Prepare and implement Pollution Incident Response management Plans POEO (General) Regulation 2009 Part 3A The requirements under the legislation are supported by the Environmental Guidelines: Preparation of pollution incident response management plans, which provides additional advice from the EPA on Plan preparation. Plan preparation is a requirement for holders of Environment Protection Licences (EPLs). The [site name] operates under EPL no. [..] and is therefore required to prepare a PIRMP and implement the PIRMP if and when an incident occurs. Key areas which this Plan covers are described in table 1 PIRMP Requirements. PIRMP Legislation covered under this Plan Reference POEO Act Part A 153C Duty of licence holder to prepare pollution incident response management plan Information to be included in plan including procedures on actions to take after an incident and coordinating with authorities 153D Keeping of plan: E Testing of plan: 9 153F Implementation of plan: 10 POEO (General) Regulation C(a) Hazard assessment: C(b) Likelihood assessment: C(c) Pre-Emptive Action: C(d) Pollutant Inventory Types: C(e) Pollutant Inventory Quantities: C(f) Safety Equipment: C(g) Staff Contacts: Whole document plus references 5 + references 98C(h) Authority Contact: references 98C(i) Early Warnings Neighbours: 3.4 & 6
8 98C(j) Staff Safety: C(k) Maps location of pollutants: 3.4 and 4 98C(l) Early Warnings General: 3.4 and 6 98C(m) Training of Staff: 7 98C(n) Timing of Testing: 9 98C(o) Updating of Plan: 8 98C(p) Plan Testing: 9 98D(1) Availability of plan: D(2) Publishing Plan Parts: D(3) Procedures under Act: 5 + references 98D(4) Privacy Protection: E(1) Testing of the Plan: 9 98E(2) Minimum Testing requirements: 9
9 3. HAZARD, LIKELIHOOD AND PRE-EMPTIVE ACTIONS TO PREVENT POLLUTION INCIDENT RISKS Overview This chapter deals with the POEO (General) Regulation 2009 s sections 98(a) to 98(f) and partially covers s98(j). These sections deal with the hazard, likelihood and pre-emptive actions which are similar processes to undertaking a risk assessment and providing appropriate control measures to proven or minimise these risks. The [site name] site undertakes [insert information regarding site activities] This Plan also considers both air and water based pollution incident impacts. Overall considerable design and written environmental management systems are in place to effectively minimise the likelihood and impact of a pollution incident. However, such incidents despite the best design and management methods can occur. Such accidental events are also covered in the Plan by the use of incident response methods. This Plan uses a modular approach to this risk assessment process. Each module represents an operation undertaken in [insert main activity of site] such as use and storage of hazardous chemicals and use and storage of non-hazardous chemicals [insert other activities whose impacts will be assessed in risk assessments]. These modules are common across [insert company name] operations, but include site specific issues for each Plan. They are based on [add name of site EMS] The risk assessment and control measures process includes impact on neighbours and crosses over with safety risk assessment processes and is covered under [add name of site OHS management system] Each module also includes an inventory of pollutants or expected maximum quantities of pollutants likely to be stored. The pollutant types include hazardous chemicals as defined under the Workplace Health and Safety legislation and non-hazardous chemicals such as aqueous based liquids. Summary of Pollution Types [insert main activity on site] by its nature has a limited list of typical pollution types which are required to be considered under the PIRMP. This list covers the main types found for the [site name].
10 Table 2: List of Typical Main Pollutants in [insert site activity] Description Comments Air Based Emissions Dust From [insert sources of dust if any]. Dust is covered under this Plan and also [add any relevant additional procedures]. Fire Fire is not considered an environmental incident, but the smoke from the fire can be and can affect neighbours. Fire Management is covered under the [insert procedure names that covers fire management eg Emergency Preparedness and Incident reporting] Noise Emitted by plant and equipment. Covered under [insert procedure that covers noise management]. Noise is not considered a pollution incident and not covered further under this Plan. Odour Odour is generally [not] associated with this site. [if odour is an issue add details] Odour incidents are not considered to be material environmental harm, but are included in the PIRMP for consistency with site EMS Spill type emissions [this list has examples will need to be revised to be made site specific] Class 3 flammable For plant and equipment operations. Covered under: liquids e.g. Fuels [insert document names] including petrol based fuels and Combustible Liquids (C1 & C2) Lubricants and hydraulic oils and other Other dangerous Goods classes e.g. Compressed gases Corrosive substances Oxidzing substances Toxics Other dangerous goods For plant and equipment operations. Covered under [insert document names] e.g. Ammonia Paints, inks and surface coatings Pesticides Other chemicals Aqueous wastes Wastes Surface coatings are applied on site. Covered under [insert document names] Control of weeds and pests: Covered under [insert document names] For plant and equipment operations. Covered under [insert document names] Management of water and stormwater. Covered under: [insert document names] Storage of wastes and wastes containing chemicals: Covered under: [insert document names]
Ingredion ANZ Pty Ltd
Ingredion ANZ Pty Ltd 170 Epping Road, Lane Cove, NSW 2066 EPL: 518 Page 1 of 8 1. Purpose and Background POLLUTION INCIDENT RESPONSE The purpose of this Pollution Incident Response Management Plan (PIRMP)
Pollution Incident Response Management Plan
Pollution Incident Response Management Plan POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN 1. Introduction This Pollution Incident Response Management Plan (PIRMP) has been prepared to describe the processes
Protection of the Environment Operations Act 1997
New South Wales Protection of the Environment Operations (General) Amendment (Pollution Incident Response Management Plans) Regulation 2012 under the Protection of the Environment Operations Act 1997 Her
POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN
FUCHS LUBRICANTS (AUSTRALASIA) PTY LTD 2 HOLLAND STREET WICKHAM NSW POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN ENVIRONMENTAL PROTECTION LICENCE No.10181 Pubic Version DOC REF:ENV228 ISSUE:1 DATE:21.11.13
Pollution Incident Response Management Plan (PIRMP)
Pollution Incident Response Management Plan (PIRMP) For NSW Ports For Construction of Berth 103 Stage 2 Extension WATERWAY CONSTRUCTIONS PTY LTD ABN 74 061 311 395 Po Box 290, Annandale NSW 2038 TELEPHONE:
POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN
POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Pentarch PTY LTD Answerth Drive Oaklands, NSW Table of Contents 1. Description and Intended Use... 4 1.1. Overview... 4 1.2. Objectives... 4 1.3. Criteria...
Pollution Incident Response Plan
Pollution Incident Response Plan Introduction Schmidt Quarries is committed to ensuring all aspects of our quarrying activities comply with the environmental legislative requirements in NSW. This Pollution
POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN
POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Southern Oil Refining Pty Ltd 42 Lewington St. Bomen. NSW. 2650 Table of Contents 1 INTRODUCTION 1.1 Facility details 1.2 Overview of Operations 1.3 Plan Objectives
Narellan Field Service Centre. Pollution Incident Response Management Plan. Prepared by Endeavour Energy Safety and Environmental Services.
Narellan Field Service Centre Pollution Incident Response Management Plan Prepared by Endeavour Energy Safety and Environmental Services Version 3 Version Date 1 30 August 2012 2 30 September 2013 3 9
Pollution Incident Response Management Plan (PIRMP) Newcastle Grain Terminal
Pollution Incident Response Management Plan (PIRMP) Newcastle Grain Terminal en-3-00844/v2/3 Jul 14 UNCONTROLLED WHEN PRINTED Page 1 Table of Contents 1.0 Purpose and Background... 3 2.0 Scope... 3 3.0
Jemalong Irrigation Limited. Pollution Incident Response Management Plan
Jemalong Irrigation Limited Pollution Incident Response Management Plan Pollution incidents must be reported immediately A pollution incident can be any of the following: An accident which involves any
Pollution Incident Response Management Plan
Pollution Incident Response Management Plan DOCUMENT CONTROL DOCUMENT DETAILS Title Pollution Incident Response Management Plan Reference Document Status ENV 002 12 Pollution Incident Response Management
Environmental Incident Response Procedure. Newcastle Gas Storage Facility Document Number: NGSF-PSV-NAS-EN-PLN-0024
Environmental Incident Response Procedure Newcastle Gas Storage Facility Document Number: NGSF-PSV-NAS-EN-PLN-0024 Environmental Incident Response Procedure Document Number: NGSF-PSV-NAS-EN-PLN-0024 Version:
Chemical Storage and Spill Response Guidelines
Chemical Storage and Spill Response Guidelines 9TP-SD-066/3.0 Supporting Document Applicable to Transport Projects Delivery Office Quality Management System Status: Approved Version: 3.0 Branch: Business
Management of Environmental Risks and Emergencies. Compliance Audit Program
Management of Environmental Risks and Emergencies Compliance Audit Program 2012 State of NSW and Environment Protection Authority The State of NSW and the Environment Protection Authority (EPA) are pleased
INCIDENT RESPONSE MANAGEMENT PLAN DECEMBER 2015
INCIDENT RESPONSE MANAGEMENT PLAN DECEMBER 2015 DOCUMENT CONTROL Document Controller: Resilience Coordinator Date of last update: December 2015 Date of next update: December 2016 HPRM reference: HW2007-900/27/9.009
ENVIRONMENTAL ASPECTS REGISTER (ISO 14001)
ENVIRONMENTAL ASPECTS REGISTER (ISO 14001) 1. Scope The scope of this Environmental Aspects Register covers the following operational areas: Aberdeen Region (A); Cumbernauld Region (C); Warrington Region
Environmental Management Plan
Environmental Management Plan This environmental management plan outlines Red Bus Services objectives and strategies for protecting the environment. This plan sets out how Red Bus Services intends to comply
EPA PRIMP Pollution Incident Response Management Plan
EPA PRIMP Pollution Incident Response Management Plan QA Department: QA Documents\EPA\Pollution Incident Response Management Plan Page 1 AMENDMENT REGISTER Version Number Page Numbers Subject Date QA Department:
Bulga Complex Pollution Incident Response Management Plan
for Bulga Complex Pollution Incident Response Management Document Table of Contents 1 Heading 1... Error! Bookmark not defined.3 1.1 Heading 2... 6 1.1.1 Heading 3... Error! Bookmark not defined.3 1.1.1.1
Occupational Health & Safety Policy Injury & Incident Reporting
Occupational Health & Safety Policy Injury & Incident Reporting Policy number 46 Version 1 Approved by board on 6 June 2014 Responsible person President Review date June 2016 Introduction Living Positive
WORKING IN CONFINED SPACES GUIDELINES
WORKING IN CONFINED SPACES GUIDELINES Contents 1 Introduction... 2 2 Scope... 2 3 Definitions... 2 4 Responsibilities... 3 4.1 Permit Authoriser... 3 4.2 Permit Receiver... 3 4.3 Responsible UOW Officer...
OCCUPATIONAL HEALTH AND SAFETY POLICY: INCIDENT AND INJURY REPORTING ERJ 6.28.1
OCCUPATIONAL HEALTH AND SAFETY POLICY: INCIDENT AND INJURY REPORTING ERJ 6281 INTRODUCTION The Edmund Rice Justice Aotearoa New Zealand Trust recognises that the health and safety of its employees is a
Environment Information Sheet 8 Spill Response
Environment Information Sheet 8 Spill Response Prevention is better than spill response What s the issue with spills? Spills of fuel, oil and / or chemicals pose a significant risk to groundwater at the
WORKING IN ISOLATION PROCEDURE
Document uncontrolled when printed Procedure ID no 0479/05 WORKING IN ISOLATION PROCEDURE This procedure is applicable to: All Department of Education and Children's Services employees. DOCUMENT CONTROL
WHS LEGISLATIVE COMPLIANCE GUIDELINES
WHS LEGISLATIVE COMPLIANCE GUIDELINES CONTENTS 1 Introduction... 2 2 Scope... 2 3 Responsibilities... 2 3.1 Manager WHS Unit... 2 3.2 Management of Faculties, Divisions and Research Institutes... 2 4 Maintaining
Hazard/Incident Recording, Reporting and Investigation
Hazard/Incident Recording, Reporting and Investigation Power and Water Corporation Procedure 1 Purpose... 1 2 Scope... 1 3 References... 2 4 Roles and Responsibilities... 2 5 Definitions... 6 6 Records...
Guide on the Segregation, Packaging, Labelling and Storage of Laboratory Chemical Wastes for Schools
APPENDIX II Guide on the Segregation, Packaging, Labelling and Storage of Laboratory Chemical Wastes for Schools (Prepared by Environmental Protection Department) 1. Introduction The Waste Disposal (Chemical
4.05e WHS Guidelines for Incident Investigation Procedures Page 1 of 7
Page 1 of 7 1 Purpose It is a legal requirement under the NSW Work Health and Safety Act 2011 and NSW Work Health and Safety Regulation 2011 to identify hazards, assess the risk of those hazards, implement
Environmental Incident Classification and Reporting
Environmental Incident Classification and Reporting 9TP-PR-105/13.0 Procedure Applicable to Transport Projects Quality Management System Status: Approved Version: 13.0 Branch: Business unit: Planning and
SAFETY SIGNAGE PROCEDURE
Page 1 of 10 SAFETY SIGNAGE PROCEDURE 1.0 PURPOSE 1.1 To enable a reference to signage to meet legislative requirements and ensure in cases of emergency appropriate signage is visible. 2.0 SCOPE 2.1 This
Appendix A1. Register of legal and other requirements
Appendix A1 Register of legal and other requirements 1 Table 1 Legal register Act Activity / General Environmental Planning and Assessment Act 1979 All Comply with the terms Minister for Planning and Infrastructure
SILICON VALLEY CLEAN WATER. May 2015
SILICON VALLEY CLEAN WATER May 2015 Slug Discharge Control and Spill Containment Guidelines This document was revised and used with the permission of the Los Angeles County Sanitation District, Industrial
R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN
LEND LEASE BUILDING PTY LIMITED ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN HAZARDOUS SUBSTANCES DANGEROUS GOODS MANAGEMENT PLAN 3/12/2015 Revision
GENERAL SPECIFICATION
R64 - PAVEMENT MARKING August 1996 GENERAL SPECIFICATION G10 CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN Date JUNE 2012 Department 1 DOT Spec R64 of Infrastructure, Energy and Resources Index DEPARTMENT
OH&S Management Systems Audit Checklist (NAT, E3)
3.1.2 3.1.1 Introduction OH&S Management Systems Audit Checklist (NAT, E3) This audit checklist is based on Element 3 (Implementation) of the National Self-Insurers OHS Audit Tool. For a full copy of the
Six steps to Occupational Health and Safety
Six steps to Occupational Health and Safety This booklet gives basic guidelines for workplace health and safety systems to help industry in NSW comply with the "duty of care" principle outlined in the
CONTRACTOR INDUCTION HANDBOOK
CONTRACTOR INDUCTION HANDBOOK POLICY The health and safety of all school employees and contractor employees is a vital concern at the school. Contract personnel will be treated in a manner consistent with
LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT
LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT Introduction The purpose of this Public Environmental Report (PER) is to provide the Government
Pollution Incident Response Plan (PIRP)
1.0 Purpose... 2 2.0 Scope... 2 3.0 Responsibilities... 2 4.0 Definitions... 3 5.0 Procedure... 4 6.0 Records... 15 7.0 References... 16 8.0 Revision History... 16 9.0 Review and Approval... 16 10.0 Compliance
1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY
1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY Dumfries Timber Co. Ltd. is committed to comply with our legal duties in order to provide a safe and healthy working environment
HP SUPPLIER ENVIRONMENTAL PERFORMANCE REVIEW QUESTIONNAIRE
Document Number: HP 5951-1746-1 (CIQC STD 0014) Page 1 of 6 I. INTRODUCTION As supply chain management becomes more complex in today's procurement processes, supplier environmental management has become
Hazard Identification, Risk Assessment And Control Procedure
Hazard Identification, Risk Assessment And Control Procedure 1. Purpose 1.1 To ensure that there is a formal process for hazard identification, risk assessment and control to effectively manage hazards
CHEMICAL SPILL MANAGEMENT GUIDELINES
WHS Unit CHEMICAL SPILL MANAGEMENT GUIDELINES Contents 1 Purpose... 2 2 Scope... 2 3 Definitions... 2 4 Roles and Responsibilities... 2 5 General... 2 6 Defining Major or Minor Spill... 3 7 Major Spill
Compliance Audit Handbook
Compliance Audit Handbook This Compliance Audit Handbook has been produced by the Compliance and Assurance Section of the Department of Environment and Conservation NSW (DEC). For technical information
WASTE Application Form - Dublin Waste to Energy SECTION J ACCIDENT PREVENTION & EMERGENCY RESPONSE
SECTION J ACCIDENT PREVENTION & EMERGENCY RESPONSE Describe the existing or proposed measures, including emergency procedures, to minimise the impact on the environment of an accidental emission or spillage.
Slide 1. Enviros Consulting Ltd
Slide 1 Regulation of Waste Management Activities Past, Present and Future! Steve Bell Technical Manager Waste Management Thursday, 26 July 2007 Presentation Aims An insight of where we have come from
FLAMMABLE LIQUIDS COMPLIANCE NOTE
Issued by: Heather Rice Page: 1 of 7 COMPLIANCE NOTE INTRODUCTION This document provides additional guidance to support the Arrangement on Flammable Liquids (Ref No. CYC/HS/A27) CONTENTS Section Topic
RMM 501 Hazardous Materials Management Systems Including WHMIS Program Page 2 November 2014
RMM 501 Hazardous Materials Management Systems Including WHMIS Program Page 2 3.4 McMaster University RMM #300 Safety Orientation and Training Program 3.5 McMaster University RMM #301 Standard Operating
Proposed (Concrete Cutting And Drilling) Environmental Management Plan
SAMPLE ENVIRONMENTAL MANAGEMENT PLAN This EMP is designed for (Concrete Cutting and drilling), however you may insert your business activities with only minor changes needed. This EMP should become part
Controlling fire and explosion risks in the workplace
Controlling fire and explosion risks in the workplace A brief guide to the Dangerous Substances and Explosive Atmospheres Regulations Introduction to DSEAR This leaflet provides a brief introduction to
CHAPTER 24: ENVIRONMENTAL MANAGEMENT
Central Eyre Iron Project Environmental Impact Statement CHAPTER 24: ENVIRONMENTAL MANAGEMENT CHAPTER 24 ENVIRONMENTAL MANAGEMENT COPYRIGHT Copyright Iron Road Limited, 2015 All rights reserved This document
UCL FIRE RISK ASSESSMENT POLICY& ARRANGEMENTS
Fire Safety Technical Guide UCL FIRE RISK ASSESSMENT POLICY& ARRANGEMENTS 1.0. BACKGROUND 1.1. The Regulatory Reform (Fire Safety) Order (known Fire Safety Order) applies to England and Wales (Northern
EMS Environmental Emergency Response Plan EXAMPLE
Page 1 of 11 EMS Environmental Emergency Response Plan EXAMPLE Page 2 of 11 ENVIRONMENTAL EMERGENCY RESPONSE PLAN TABLE OF CONTENTS INTRODUCTION EMERGENCY SPILLS/DISCOVERY POLICIES AND GUIDING PRINCIPLES
CHAGUARAMAS TERMINALS LTD.
POLICY MANUAL All rights reserved to CrewsInn Limited. No part of this document may be reproduced in any form or by any means, without permission in writing from the company CHAGUARAMAS TERMINALS LTD.
EMERGENCY PLANS FACT SHEET
EMERGENCY PLANS FACT SHEET Overview This fact sheet provides general guidance for persons conducting a business or undertaking (PCBUs) and workers on preparing and maintaining general emergency plans for
EPA RISK MANAGEMENT PROGRAM RULE TO IMPACT DISTRIBUTORS AND MANUFACTURERS
EPA RISK MANAGEMENT PROGRAM RULE TO IMPACT DISTRIBUTORS AND MANUFACTURERS I. Introduction Under an EPA rule designed to prevent chemical accidents, certain distributors, formulators and manufacturers of
How To Monitor Safety Management System Performance
Guidance Note Performance standards and indicators Advice for operators of major hazard facilities on developing meaningful and useful performance standards and indicators for the Safety Management System
IMPLEMENTING ISO 14001:2004. www.aecos.co.uk
IMPLEMENTING ISO 14001:2004 www.aecos.co.uk What is an Environmental Management System? A systematic framework to manage the immediate and long term environmental impacts of an organisation s products,
An inventory of hazardous materials used in your workplace will prove useful.
Introduction Fire Protection is an organized approach designed to prevent fires. In the event of a fire, a fire protection program will help prevent or minimize personal injuries, losses, and harm to the
WHS GUIDANCE MATERIAL WHS GUIDANCE SECTION MATERIAL 4 WORKING IN CONFINED & ENCLOSED SPACE DEVELOPING WORKPLACE HEALTH & SAFETY GUIDANCE
DEVELOPING WORKPLACE HEALTH & SAFETY GUIDANCE for the RECREATIONAL & LIGHT COMMERCIAL BOATING INDUSTRIES WHS GUIDANCE MATERIAL WHS GUIDANCE SECTION MATERIAL 4 WORKING IN CONFINED & ENCLOSED SPACE 1 Prepared
WHS Contractor Management Procedure
Wudinna District Council 1. Overview Wudinna District Council as part of its commitment under its Policy recognises its obligation to: Ensure, so far as is reasonably practicable, the health and safety
ASBESTOS CONTAINING MATERIALS POLICY
ASBESTOS CONTAINING MATERIALS POLICY Document Control Version 3 Ratified by Risk Management Sub Group Date Ratified 19 December 2012 Name of Originator/Author Head of Estates and Facilities Name of Responsible
Published in "Official Gazette of the Republic of Macedonia" No. 67/2004 LAW ON AMBIENT AIR QUALITY I. GENERAL PROVISIONS
Published in "Official Gazette of the Republic of Macedonia" No. 67/2004 LAW ON AMBIENT AIR QUALITY I. GENERAL PROVISIONS Article 1 Subject of regulation (1) This Law shall regulate the measures for avoidance,
Module 14: Monitoring and Measurement
Module 14: Monitoring and Measurement Guidance...14-2 Tools and Forms...14-8 Tool 14-1: Monitoring and Measurement Worksheet...14-8 Tool 14-2: EMS Program Measurement Criteria Worksheet...14-9 Tool 14-3:
SHENZHEN ENVIRONMENTAL PRINTED CIRCUIT BOARD COMPANY. Environmental Procedure
SHENZHEN ENVIRONMENTAL PRINTED CIRCUIT BOARD COMPANY Environmental Procedure Environmental Emergency Preparedness and Response (EP-05) Revision No. : 1 Prepared by : Jiang Ho (EMR) Approved by : Ma Hung
Chapter 5: Spills Response
Chapter 5: Spills Response When printing materials are spilled, the response required by the owner or operator depends on what is spilled and the quantity. The entities who must be informed of a spill
Hazardous materials can be silent killers. Almost every household and workplace has varying amounts of chemicals that, if spilled or combined, will
HAZARDOUS MATERIALS Hazardous materials can be silent killers. Almost every household and workplace has varying amounts of chemicals that, if spilled or combined, will cause great harm and even death.
Environmental Management System Tool
Environmental Management System Tool How to use this Tool The Department of the Environment, Water, Heritage and the Arts (DEWHA) has developed the EMS Tool to assist office based organisation who are
Information for a person conducting a business or undertaking
BULLETIN Information for a person conducting a business or undertaking Overview of your responsibilities to provide a healthy and safe workplace. The Work Health and Safety laws (WHS laws) aim to provide
RESTRICTED ACCESS AND CONFINED SPACES
Health & Safety Services Unit name goes here Safety Code of Practice 39 1 st Edition, July 2011 RESTRICTED ACCESS AND CONFINED SPACES University of Reading 2015 Page 1 Contents 1 Summary... 3 2 Introduction...
AFTRS Health and Safety Risk Management Policy
AFTRS Health and Safety Risk Management Policy Responsible Officer Contact Officer Authorisation Director, Corporate and Student Services Head of Human Resources Chief Executive Officer Effective Date
Hazard/Risk Identification and Control Procedure
Hazard/Risk Identification and Control Procedure Introduction Hazard identification and the steps taken to minimize the risks associated with identified hazards are a critical component of working safely.
SPILL PREVENTION AND RESPONSE PLAN TEMPLATE FOR BUSINESSES IN DAYTON S SOURCE WATER PROTECTION AREA
SPILL PREVENTION AND RESPONSE PLAN TEMPLATE FOR BUSINESSES IN DAYTON S SOURCE WATER PROTECTION AREA Regulated Substance Management: All Regulated Substances, including chemical wastes, are to be managed
Pollution & Noise from Demolition & Construction Sites
CONTROL OF Pollution & Noise from Demolition & Construction Sites N oi se Co ns tru ct io n MAY 2008 THE LONDON BOROUGH 3 CONTENTS Part 1 Introduction Page 1. Background 4 2. Purpose of the code 5 3.
To establish a process to control all UON Health and Safety Management System Framework
UON Health and Safety Procedure: HSP 9.1 Records, Documents and Document Control 1. Purpose To establish a process to control all UON Health and Safety Management System Framework policies, elements, procedures,
Hazard Communication/Globally Harmonized System (GHS) Program
Hazard Communication/Globally Harmonized System (GHS) Program Hazard Communication/GHS Program 1.0 Overview TABLE OF CONTENTS 2.0 Labels and Other Forms of Warning A. Verification of Proper Labeling...
Division of Public Health Administrative Manual
PURPOSE To establish a protocol for the development of a written Division of Public Health Hazard Communications Program at each applicable office or laboratory workplace and to assure that employees are
Sample Emergency and Critical Incident Policy and Procedure
Sample Emergency and Critical Incident Policy and Procedure 1. Purpose and Scope Emergencies and critical incidents in the workplace can affect people physically and psychologically, and affect program
WHS CONTRACTOR MANAGEMENT PROCEDURE
1. Overview The Port Augusta City Council as part of its commitment under its WHS Contractor Management policy, recognises its obligation to: Ensure, so far as is reasonably practicable, the health and
EMERGENCY ACTION, EVACUATION AND FIRE PREVENTION SAFETY PROGRAM
EMERGENCY ACTION, EVACUATION AND FIRE PREVENTION SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29CFR1910.36-29CFR1910.38-29CFR1910.157-29CFR1910.165 NFPA-10 BASIS: The OSHA Emergency Action Planning and the
THE CORPORATION OF THE CITY OF COURTENAY BYLAW NO. 2182. A bylaw to amend Storm Sewer Bylaw No. 1402, 1986
THE CORPORATION OF THE CITY OF COURTENAY BYLAW NO. 2182 A bylaw to amend Storm Sewer Bylaw No. 1402, 1986 The Council of the Corporation of the City of Courtenay in open meeting assembled enacts as follows:
STORE HAZARDOUS SUBSTANCES SAFELY. incompatibles gas cylinders
STORE HAZARDOUS SUBSTANCES SAFELY Suitable containers incompatibles gas cylinders Oxy-Acetylene welding flammable substances 35 36 STORE HAZARDOUS SUBSTANCES SAFELY STORE HAZARDOUS SUBSTANCES SAFELY Storing
a guide for wastewater producers and wastewater treatment plant operators
Contingency plans April 2007 Contingency Plans a guide for wastewater producers and wastewater treatment plant operators Updated May 2009 * EPA 696/09: This guideline has been provided to help licensees
LPG, Flammable Liquids, Toxic and Corrosive Substances
LPG, Flammable Liquids, Toxic and Corrosive Substances LPG, Flammable Liquids, Toxic and Corrosive Substances Safe Storage and Handling Today s focus is Dangerous substances under the Dangerous Substances
Hazardous materials can be silent killers. Almost every household and workplace has varying amounts of chemicals that, if spilled or combined, will
HAZARDOUS MATERIALS Hazardous materials can be silent killers. Almost every household and workplace has varying amounts of chemicals that, if spilled or combined, will cause great harm and even death.
NASA Stennis Space Center Environmental Resources Document
16.0 Major Environmental Considerations for Proposed Actions All construction, rocket testing, and operations that may potentially impact environmental media, such as air, water, land, aquatic and biotic
EMERGENCY ACTION AND FIRE PREVENTION PLAN
Sample Written Safety Program For EMERGENCY ACTION AND FIRE PREVENTION PLAN Page 1 EMERGENCY ACTION AND FIRE PREVENTION PLAN (YOUR COMPANY NAME) EMPLOYEE EMERGENCY AND FIRE PREVENTION PLANS Emergencies
TARLETON STATE UNIVERSITY HAZARD COMMUNICATION PROGRAM
TARLETON STATE UNIVERSITY HAZARD COMMUNICATION PROGRAM Office of Risk Management and Safety August 2009 1. GENERAL The 69 th Legislature of the State of Texas, in 1985, enacted the Texas Hazard Communication
Flammable and combustible liquids. Licence guide. Guide for operators
Guide for operators About this guide This guide is for businesses that provide flammable and combustible liquids. It provides advice on licensing and fit-out guidelines for businesses. Table of Contents