Project Cost Management
|
|
|
- Vincent Park
- 10 years ago
- Views:
Transcription
1 Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.
2 Present Value and Net Present Value (NPV) Present Value Present Value is the future value (FV) of a payment discounted at a discount rate (r) for the delay in payment. Example of Present Value: Assume that $ 1,100 (FV) is going to be invested one year (n) from now. The discount rate (e.g. inflation) is 10% (r). What is the Present Value? Answer: Present Value = FV. = $ 1,100. = $ 1,100 = $ 1,000 (1 + r/100) n (1 + 10/100) What this means: The future value of today s $1000 is $1100 after one year. Thus, there is a decrease in the value of money. Net Present Value (NPV) Net Present Value (NPV) = (Present Value of All Cash Inflows) - (Present Value of All Cash Outflows) Project Selection Criteria: Select the project with the maximum Net Present Value. The time value of money is already taken into account while calculating NPV. Example: There are 2 projects. Project A has as NPV of $ 1,000 and will be completed in 5 years. Project B has a NPV of $ 800 and will be completed in 1 year. Which project will you select? Answer: Project A will be selected. The fact that project B has a lesser duration than project A does not matter because time is already taken into account in NPV calculations. 2
3 Internal Rate of Return (IRR) Discount Rate on an investment which makes present value of cash inflows equal to present value of cash outflows Project selection criterion: Select a project with higher IRR Example: There are 2 projects. Project A has an IRR of 15% and will be completed in 5 years. Project B has an IRR of 10% and will be completed in 1 year. Which project will you select? Answer : Project A will be selected. (The fact that project B has a lesser duration than Project A does not matter because time is already taken into account in IRR calculations.) 3
4 Payback Period and Life Cycle Cost Payback Period Number of years required for an organization to recapture an initial investment Discount rate is not taken into account in payback period calculations Project selection criterion: Select a project with a shorter payback period Example: There are 2 projects. Project A has an investment of $ 500,000 and payback period of 3 years. Project B has an investment of $ 300,000 and payback period of 5 years. Using the payback period criterion, which project will you select? Answer : Project A will be selected. (The fact that project B has a lower investment than project A will not impact the selection.) Life Cycle Cost The overall estimated cost of a particular project alternative over the time period corresponding to the life of the project. Includes Direct and Indirect Costs Periodical or continuing costs of operation and maintenance Project selection criterion : For 2 projects having the same investment, select a project with lower Life Cycle Cost. 4
5 Benefit Cost Ratio (BCR) BCR = Benefits (or Payback or Revenue) Costs Selection criterion: Select project with a higher BCR BCR > 1 means that benefits (i.e. expected revenue) is greater than the cost. Hence it is beneficial to undertake the project. Project selection criterion: Select a project with a higher BCR Example: There are 2 projects. Project A has an investment of $ 500,000 and a BCR of 2.5. Project B has an investment of $ 300,000 and a BCR of 1.5. Using the Benefit Cost Ratio criterion, which project will you select? Answer : Project A will be selected. (The fact that project B has a lower investment than project A will not impact the selection.) Benefit / Payback / Revenue = Cost + Profit earned or Cost Loss incurred 5
6 Opportunity Cost and Sunk Cost Opportunity Cost: This is the cost of passing up the next best choice while making a decision. Once the best option is decided, the opportunity cost of not choosing the other option is determined. Example: There are 2 projects. Project A has as NPV of $ 1,000. Project B has a NPV of $ 800. What is the opportunity cost if Project A is selected? Answer : If project A is selected, NPV is $ 1,000. If Project A is selected and Project B is rejected, project with NPV of $ 800 will not be executed. Hence the opportunity cost of Project A = $ 800. Sunk Cost: This is the cost that has already been incurred therefore cannot be avoided. Project selection criterion: When deciding on the best option, ignore the sunk cost, because it has already been incurred and cannot be avoided. Example: Project A had an initial budget of $ 1,000 out of which an amount of $ 800 has already been spent. To complete Project A, we still need an additional $ 500. Project B requires $ 1200 to complete. Which project do you select? Answer : $ 800 spent in Project A is sunk cost hence should be ignored. So: Cost of completing project A = $ 500 Cost of completing project B = $ 1200 Hence, we should select project A. 6
7 Depreciation Depreciation is the decrease in value of an asset over a period of time and is considered for accounting and tax purposes. Depreciation Methods: Straight Line Depreciation: The asset depreciates by the same amount every year Initial Cost Salvage Value Accelerated Depreciation: The asset depreciates more rapidly in this method during the initial years as compared to the Straight Line method. Other methods of depreciation are: Double Declining Balance Sum of the Year s Digits Initial Cost Salvage Value time time 7
8 Earned Value Management Acronym Term Description Formula PV (BCWS) Planned Value (Budgeted Cost of Work Scheduled) The authorized budget assigned to the schedule work to be accomplished for a schedule activity or WBS component. EV (BCWP) Earned Value (Budgeted Cost of Work Performed) The value of work performed expressed in terms of the approved budget assigned to that work for a schedule activity or WBS component. AC Actual Cost Actual Cost of work completed that is incurred and recorded. SV Schedule Variance A measure of schedule performance on a project. Negative SV: Behind schedule Positive SV: Ahead of schedule EV PV CV Cost Variance A measure of cost performance on a project. Negative CV : Over budget; Positive CV : Under budget EV AC CPI Cost Performance Index A measure of cost efficiency on a project. Value got for 1 $ of actual cost EV = (BAC) AC (EAC) SPI Schedule Performance Index A measure of schedule efficiency on a project. Progress as a % of planned progress EV PV 8
9 Earned Value Management (continued) Acronym Term Description Formula EAC Estimate at Completion The expected total cost when the defined scope of work will be completed. 1. AC + ETC 1. Original estimating assumptions no longer valid 2. Current variances are atypical; similar variances will not occur in the future 3. Current variances are typical; similar variances may occur in the future 4. EAC taking both CPI and SPI into account 2. AC + BAC-EV 3. AC+ {(BAC-EV)/CPI} Or BAC/CPI 4. AC+ {(BAC-EV)/(CPI*SPI)} BAC Budget at Completion Budget for the whole project EAC * CPI ETC Estimate to Complete From a particular point in time, how much more time is required to complete the project EAC AC VAC Variance at Completion Over or under budget BAC EAC TCPI To-Complete Performance Index The work remaining divided by the funds remaining. Equation expressed in terms of EAC: (BAC-EV) / (EAC-AC) Equation expressed in terms of BAC: (BAC-EV) / (BAC-AC) (BAC-EV) / (EAC-AC) (BAC-EV) / (BAC-AC) 9
10 Earned Value Management (Tips) Points to note: Positive Variances (e.g., SV, CV) are desirable All ratios greater than 1 (e.g., CPI, SPI) are desirable 10
Profesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01
PMP Test C07_01 01. One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI. B. Multiply by SPI. C. Multiply by CPI. D. Divide by CPI. 02.
Unit 5: Cost Management (PMBOK Guide, Chapter 7)
(PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for
Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP
Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:
An introduction to Earned Value Analysis
An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many
INSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description
Earned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue
Project Cost Management. Richard Boser
Project Cost Management Richard Boser Project Cost Management Introduction Course Objectives Upon completing today s activities you will be knowledgeable of tools and techniques to: Allocate overall costs
Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP
PMP Formulae & Tips Cheat Sheet P a g e Integration Management Develop Project Charter process Project Selection Methods (>> Benefit Measurement Methods >> Economic Models -7) Present Value (PV) FV The
Brainstorm. What is Cost and Project Cost Management?
Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,
Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor ([email protected] and [email protected]) Rules on using templates 1) Must reference the template used 2) Use
700 Analysis and Reporting
Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how
Project Cost Management
Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please
COINS EVA Earned Value Analysis
COINS EVA Earned Value Analysis Nigel Cope July 2006 Earned Value Analysis The most widely used method for performance measurement of projects Combines scope, cost and schedule patterns Informs project
Net Present Value (NPV)
Investment Criteria 208 Net Present Value (NPV) What: NPV is a measure of how much value is created or added today by undertaking an investment (the difference between the investment s market value and
IST 302 : Project Cost Management
IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of
PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP
PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP Frequently Asked Questions What is the PMP credential? The PMP (Project Management Professional) credential is a globally recognized certification for
Chapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
Chapter 7: Project Cost Management. Munawar [email protected]
Chapter 7: Project Cost Management Munawar [email protected] Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.
Net Present Value and Capital Budgeting. What to Discount
Net Present Value and Capital Budgeting (Text reference: Chapter 7) Topics what to discount the CCA system total project cash flow vs. tax shield approach detailed CCA calculations and examples project
Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.
About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints
How To Manage A Project
Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management
Week- 1: Solutions to HW Problems
Week- 1: Solutions to HW Problems 10-1 a. Payback A (cash flows in thousands): Annual Period Cash Flows Cumulative 0 ($5,000) ($5,000) 1 5,000 (0,000) 10,000 (10,000) 3 15,000 5,000 4 0,000 5,000 Payback
Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB
Managing Project Budgets with MS Project Sonja Streuber, PMP, SSBB Sonja Streuber Project Mgmt & Engineering, Six Sigma, Risk Mgmt & Risk Analysis: 2000 2003 Agilent Technologies 2003 2009 Lockheed Martin
Project Cost Management
Project Cost Management Martin Pazderka [email protected] INSO - Industrial Software Institut für Rechnergestützte Automation Fakultät für Informatik Technische Universität Wien Agenda
Chapter 9. Year Revenue COGS Depreciation S&A Taxable Income After-tax Operating Income 1 $20.60 $12.36 $1.00 $2.06 $5.18 $3.11
Chapter 9 9-1 We assume that revenues and selling & administrative expenses will increase at the rate of inflation. Year Revenue COGS Depreciation S&A Taxable Income After-tax Operating Income 1 $20.60
CHAPTER 7: NPV AND CAPITAL BUDGETING
CHAPTER 7: NPV AND CAPITAL BUDGETING I. Introduction Assigned problems are 3, 7, 34, 36, and 41. Read Appendix A. The key to analyzing a new project is to think incrementally. We calculate the incremental
Tracking Budgets and Schedules
Tracking Budgets and Schedules David V. Tennant, PE, PMP One of the simplest questions you are likely to encounter as an engineering or project manager is: Are we on budget and schedule? While this is
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu
Why Use Net Present Value? The Payback Period Method The Discounted Payback Period Method The Average Accounting Return Method The Internal Rate of
1 Why Use Net Present Value? The Payback Period Method The Discounted Payback Period Method The Average Accounting Return Method The Internal Rate of Return Problems with the IRR Approach The Profitability
Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded?
Resource Loading: who and/or what needed where and when. Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded? Resource
PROJECT COST MANAGEMENT
PROJECT COST MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_cost_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern
Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Management, Sixth Edition Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project cost management Explain basic project cost management principles,
PROJECTS SCHEDULING AND COST CONTROLS
Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP [email protected] Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
MODULE 2. Capital Budgeting
MODULE 2 Capital Budgeting Capital Budgeting is a project selection exercise performed by the business enterprise. Capital budgeting uses the concept of present value to select the projects. Capital budgeting
Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1
Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control
Using Earned Value Management for Improving Processes. By Cynthia K. West
Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective
Performing Net Present Value (NPV) Calculations
Strategies and Mechanisms For Promoting Cleaner Production Investments In Developing Countries Profiting From Cleaner Production Performing Net Present Value (NPV) Calculations Cleaner Production Profiting
CHAPTER 14 COST OF CAPITAL
CHAPTER 14 COST OF CAPITAL Answers to Concepts Review and Critical Thinking Questions 1. It is the minimum rate of return the firm must earn overall on its existing assets. If it earns more than this,
Introduction to earn value management in Civil Engineering
3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.
CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA
CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA Basic 1. To calculate the payback period, we need to find the time that the project has recovered its initial investment. After two years, the
The Two Most Useful Earned Value Metrics: the CPI and the TCPI
PM WORLD TODAY SECOND EDITIONS JUNE 2009 Editor s note: Second Editions are papers that have been previously published that have continued relevance and deserve additional visibility. The paper below was
CHAPTER 7 MAKING CAPITAL INVESTMENT DECISIONS
CHAPTER 7 MAKING CAPITAL INVESTMENT DECISIONS Answers to Concepts Review and Critical Thinking Questions 1. In this context, an opportunity cost refers to the value of an asset or other input that will
CAPITAL BUDGETING. Definition. Time Value of Money [TVM] TVM is the reward for postponement of consumption of money.
11 CAPITAL BUDGETING 1LO 1: Time Value of Money Definition Time Value of Money [TVM] TVM is the reward for postponement of consumption of money. Principle Rs.100 received today is greater than Rs. 100
Module 5 Cost Management PMP Exam Questions
Module 5 Cost Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc Question 1 A company, which provides professional
CARNEGIE MELLON UNIVERSITY CIO INSTITUTE
CARNEGIE MELLON UNIVERSITY CIO INSTITUTE CAPITAL BUDGETING BASICS Contact Information: Lynne Pastor Email: [email protected] RELATED LEARNGING OBJECTIVES 7.2 LO 3: Compare and contrast the implications
The Time Value of Money
The Time Value of Money Future Value - Amount to which an investment will grow after earning interest. Compound Interest - Interest earned on interest. Simple Interest - Interest earned only on the original
Which projects should the corporation undertake
Which projects should the corporation undertake Investment criteria 1. Investment into a new project generates a flow of cash and, therefore, a standard DPV rule should be the first choice under consideration.
Capital Budgeting: Decision. Example. Net Present Value (NPV) FINC 3630 Yost
Capital Budgeting: Decision Criteria Example Consider a firm with two projects, A and B, each with the following cash flows and a 10 percent cost of capital: Project A Project B Year Cash Flows Cash Flows
Chapter 9 Cash Flow and Capital Budgeting
Chapter 9 Cash Flow and Capital Budgeting MULTIPLE CHOICE 1. Gamma Electronics is considering the purchase of testing equipment that will cost $500,000. The equipment has a 5-year lifetime with no salvage
$1,300 + 1,500 + 1,900 = $4,700. in cash flows. The project still needs to create another: $5,500 4,700 = $800
1. To calculate the payback period, we need to find the time that the project has recovered its initial investment. After three years, the project has created: $1,300 + 1,500 + 1,900 = $4,700 in cash flows.
AACE International Recommended Practice No. 86R 14
AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment
Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition
Chapter 7: Project Cost Management Information Technology Project Management, Fourth Edition Learning Objectives Understand the importance of project cost management. Explain basic project cost management
Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction
Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects Puian Masudifar, Deputy CEO, VIRA Consulting Engineers Fereydoun Fardad, Aryana Project Management
Chapter 5: Project Cost Management
Chapter 5: Project Cost Management 1 Learning Objectives Understand the importance of good project cost management Explain basic project cost management principles, concepts, and terms Describe how resource
CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA
CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA 1. To calculate the payback period, we need to find the time that the project has recovered its initial investment. After three years, the project
Oklahoma State University Spears School of Business. Capital Investments
Oklahoma State University Spears School of Business Capital Investments Slide 2 Incremental Cash Flows Cash flows matter not accounting earnings. Sunk costs do not matter. Incremental cash flows matter.
technical tips and tricks
technical tips and tricks Applying Earned Value Analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart
CHAPTER 11. Proposed Project. Incremental Cash Flow for a Project. Treatment of Financing Costs. Estimating cash flows:
CHAPTER 11 Cash Flow Estimation and Risk Analysis Estimating cash flows: Relevant cash flows Working capital treatment Inflation Risk Analysis: Sensitivity Analysis, Scenario Analysis, and Simulation Analysis
Solutions to Chapter 8. Net Present Value and Other Investment Criteria
Solutions to Chapter 8 Net Present Value and Other Investment Criteria. NPV A = $00 + [$80 annuity factor (%, periods)] = $00 $80 $8. 0 0. 0. (.) NPV B = $00 + [$00 annuity factor (%, periods)] = $00 $00
How To Get A Profit From A Machine
Vol. 2, Chapter 4 Capital Budgeting Problem 1: Solution Answers found using Excel formulas: 1. Amount invested = $10,000 $21,589.25 Compounding period = annually Number of years = 10 Annual interest rate
L10: Budgeting and Cost Control. Olivier de Weck
ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen
Chapter 11 Cash Flow Estimation and Risk Analysis ANSWERS TO SELECTED END-OF-CHAPTER QUESTIONS
Chapter 11 Cash Flow Estimation and Risk Analysis ANSWERS TO SELECTED END-OF-CHAPTER QUESTIONS 11-1 a. Cash flow, which is the relevant financial variable, represents the actual flow of cash. Accounting
PMP Exam Preparation Answer Key
Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.
Estimating Cost at Completion - Judgment & EV Information
Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number
PMP Exam Tips on Cost Management, Fourth Edition. Parallels between Cost and Time estimating:
, Fourth Edition Parallels between Cost and Time estimating: There are strong parallels between cost estimating and time estimating so you should have experienced some déjà vu when you first read it. In
Chapter 7: Net Present Value and Capital Budgeting
Chapter 7: Net Present Value and Capital Budgeting 7.1 a. Yes, the reduction in the sales of the company s other products, referred to as erosion, should be treated as an incremental cash flow. These lost
PMI Lexicon of Project Management Terms
Project Management Institute PMI Lexicon of Project Management Terms Version 3.0 Published by: Project Management Institute, Inc. 14 Campus Boulevard Newtown Square, Pennsylvania 19073-3299 USA Phone:
Planning for Capital Investments
12-1 Planning for Capital Investments Managerial Accounting Fifth Edition Weygandt Kimmel Kieso 12-2 study objectives 1. Discuss capital budgeting evaluation, and explain inputs used in capital budgeting.
Project Management Seminars. Financial Management of Projects
Project Management Seminars Financial Management of Projects.inproject managementandsystems engineering, is a deliverable-oriented decomposition of a project into smaller components. (source: Wikipedia)
Towards a Multi-Dimensional Framework for Assessing the Value of. Software Projects
Towards a Multi-Dimensional Framework for Assessing the Value of Software Projects by John Richard Kopp Submitted in partial fulfillment of the requirements for the Master s degree in Software Development
Earned Value Management Guidelines
Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application
Project Control with ProTrack
Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS
Simple Earned Value (Using MS Project 2010)
Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained
Lecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes
Lecture Slides for Managing and Leading Software Projects Chapter 8: Measuring and Controlling Work Processes developed by Richard E. (Dick) Fairley, Ph.D. to accompany the tet Managing and Leading Software
( ) ( )( ) ( ) 2 ( ) 3. n n = 100 000 1+ 0.10 = 100 000 1.331 = 133100
Mariusz Próchniak Chair of Economics II Warsaw School of Economics CAPITAL BUDGETING Managerial Economics 1 2 1 Future value (FV) r annual interest rate B the amount of money held today Interest is compounded
Investment Decision Analysis
Lecture: IV 1 Investment Decision Analysis The investment decision process: Generate cash flow forecasts for the projects, Determine the appropriate opportunity cost of capital, Use the cash flows and
PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION
PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and
The table for the present value of annuities (Appendix A, Table 4) shows: 10 periods at 14% = 5.216. = 3.93 years
21-18 Capital budgeting methods, no income taxes. The table for the present value of annuities (Appendix A, Table 4) shows: 10 periods at 14% 5.216 1a. Net present value $28,000 (5.216) $146,048 $36,048
Problems on Time value of money January 22, 2015
Investment Planning Problems on Time value of money January 22, 2015 Vandana Srivastava SENSEX closing value on Tuesday: closing value on Wednesday: opening value on Thursday: Top news of any financial
Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP
Earned Value Management and the Government Program Office Blair Alan Knapp Jr. MSPM PMP Agenda EVM Information Alignment OMB Exhibit 300 and Funding Government Program Office Challenges Government Program
Bank: The bank's deposit pays 8 % per year with annual compounding. Bond: The price of the bond is $75. You will receive $100 five years later.
ü 4.4 lternative Discounted Cash Flow Decision Rules ü Three Decision Rules (1) Net Present Value (2) Future Value (3) Internal Rate of Return, IRR ü (3) Internal Rate of Return, IRR Internal Rate of Return
Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166
Towards a Complete Earned Value Analysis Sam Sharp and Peter Hall Paper # 166 Planned vs Actual A purely accounting approach to project tracking involves the monitoring of status by simply comparing actual
Session #5 Capital Budgeting - II Damodaran - Chapter 9: 6,12,16,18 Chapter 10: 2,10,16(a&b) Chapter 11: 6,12,14
Session #5 Capital Budgeting - II Damodaran - Chapter 9: 6,12,16,18 Chapter 10: 2,10,16(a&b) Chapter 11: 6,12,14 I. Additional Issues in Capital Budgeting. A. Capital rationing: Use profitability index
Appendix D Glossary Of Terms
Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used
Earned Value and Agile Reporting
Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,
1.040 Project Management
MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Project Financial Evaluation
Project Management: Tracking Progress and Earned Value with MS Project 2003
Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain
PERCEPTION. Tracking Progress & EAC
PERCEPTION Tracking Progress & EAC 1 Maximize Efficiency Shipyards that know their true costs are more likely to be profitable and are in a better position to challenge their competition. They can focus
Chapter 5 Capital Budgeting
Chapter 5 Capital Budgeting Road Map Part A Introduction to finance. Part B Valuation of assets, given discount rates. Fixed-Income securities. Common stocks. Real assets (capital budgeting). Part C Determination
What is the net present value of the project (to the nearest thousand dollars)?
corporate finance, final exam practice questions, NPV *Question 1.1: Net Present Value A firm invests $200,000 in machinery that yields net after-tax cash flows of $90,000 at the end of each of the next
Capital Budgeting Further Considerations
Capital Budgeting Further Considerations For 9.220, Term 1, 2002/03 02_Lecture10.ppt Lecture Outline Introduction The input for evaluating projects relevant cash flows Inflation: real vs. nominal analysis
Capital Budgeting continued: Overview:(1) Estimating cash flows (2) CB examples (3) Dealing with uncertainty of cash flows
Capital Budgeting continued: Overview:(1) Estimating cash flows (2) CB examples (3) Dealing with uncertainty of cash flows Chapter 7: 1,5,7,8,27,32 Chapter 8: 1,3,5,8,13 (clarification for problem 13b:
Project Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.
Project Management ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.2003 1 Project Management - Training Program - Project Scope Management
Chapter 13 Capital Budgeting: Estimating Cash Flow and Analyzing Risk ANSWERS TO END-OF-CHAPTER QUESTIONS
Chapter 13 Capital Budgeting: Estimating Cash Flow and Analyzing Risk ANSWERS TO END-OF-CHAPTER QUESTIONS 13-3 Since the cost of capital includes a premium for expected inflation, failure to adjust cash
Tools for Project Evaluation. Nathaniel Osgood 1.040/1.401J 2/11/2004
Tools for Project Evaluation Nathaniel Osgood 1.040/1.401J 2/11/2004 Basic Compounding Suppose we invest $x in a bank offering interest rate i If interest is compounded annually, asset will be worth $x(1+i)
EVM.01. Earned Value Analysis Why it Doesn't Work
EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects
