1 Filed: -0- EB--0 Tab Page of ASSET MANAGEMENT PLANNING PROCESS.0 INTRODUCTION Hydro One s Asset Management Plan is a systematic approach to determine and optimize on-going operating and maintenance expenditures and capital investments in its distribution system and general plant. Hydro One has adopted an Asset Management model since its inception. The objective of this plan is to ensure all funding is spent in the most effective manner to realize the best value for Hydro One stakeholders and customers and to minimize total bill impacts. To accomplish this objective, Hydro One applies a consistent approach to assess the relative asset risk impacts on business values and strategic objectives by considering and balancing asset performance (including physical condition), costs and risks, lifecycle management from an overall power system perspective and assigning asset risk scores to the corresponding investment planning actions for in-service assets. Hydro One s mission and vision is We will be an innovative and trusted company, delivering electricity safely, reliably and efficiently to create value for our customers. The asset management process at Hydro One supports the corporation mission and vision..0 THE ASSET MANAGEMENT PLAN OVERVIEW The Hydro One Asset Management Plan is incorporated throughout the evidence as documented below: Voice of the Customer (, Tab, Schedule ) Summary of Distribution Business (, Tab, Schedule ) Planning Process (, Tab, Schedule ) Investment Plan Development (, Tab, Schedule ) Investment Prioritization Process (, Tab, Schedule )
2 Filed: -0- EB--0 Tab Page of Project/Program Approval and Control (, Tab, Schedule ) Work Execution Strategy (, Tab, Schedule ) Asset Risk Assessment (, Tab, Schedule ) Regional Planning Process (, Tab, Schedule ) Common Corporate Costs OM&A Asset Management (Exhibit C, Tab, Schedule ) Distribution Assets Investment Overview (Exhibit D, Tab, Schedule ) The results of this process is the five year capital and OM&A investment plan filed at and Exhibit D, Tab and Exhibit C, Tab..0 THE ASSET MANAGEMENT PLAN This section provides more detailed descriptions of the aspects of the Asset Management Plan.. Voice of the Customer Customers are a major driver of long-term success. Hydro One listens to its customers, analyzes their needs and then modifies its work activities and work programs to address those needs. The many channels through which Hydro One listens to its customer s needs are discussed in, Tab, Schedule.. Summary of Distribution Business The Summary of Distribution Business (, Tab, Schedule ) provides an overview of the Hydro One distribution system including the evolution of the system,
3 Filed: -0- EB--0 Tab Page of distribution system assets and asset performance. This exhibit also discusses the Corporate values, strategic goals and performance targets. All of these factors are considered to inform the Asset Management model and work plan.. Planning Process Business planning is performed annually and focuses on the development of a detailed plan for each year in the plan. The results as they apply to the test years form the basis for this Custom Rate Application.. Investment Plan Development Hydro One utilizes a systematic investment approach to plan and optimize on-going capital, operating and maintenance expenditures. Five investment categories; sustaining, development, operations, customer service and common corporate costs, follow a common investment plan development process described in, Tab, Schedule.. Investment Prioritization Process The investment prioritization process is part of the overall company risk-based asset management planning process (see, Tab, Schedule ). The prioritization process converts Hydro One Distribution s business values and key performance indicators into investment criteria and guidelines that are used for managing risk and facilitating trade-offs between investments to achieve the optimal balance of cost effectiveness, customer expectations, asset and business needs within the constraints and criteria imposed.
4 Filed: -0- EB--0 Tab Page of. Project / Program Approval and Control Once the preliminary investment plans have been accepted at the proof-of-concept stage and have gone through the investment prioritization process, a detailed analysis of the preferred alternatives and costs is completed for individual projects, programs and business cases. Based on the detailed analysis, cost estimates are prepared for review and approval by senior management and ultimately the Hydro One Board of Directors. See, Tab, Schedule for more details.. Work Execution Strategy Hydro One Distribution s Work Execution Strategy provides increased work execution capacity and necessary flexibility to accommodate the planned distribution work programs. The strategy will also address the continuing global business challenges such as the uncertainty regarding material availability and qualified personnel to undertake the work. A focus on efficiency continues throughout Hydro One s work planning and execution activities and processes. See, Tab, Schedule for more details.. Asset Risk Assessment Hydro One s Asset Risk Assessment methodology is built on the Asset Condition Assessment approach previously filed in proceeding EB Since then, Hydro One has completed an asset inventory of its key distribution assets that has been linked to other non-condition based information such as outage and customer data. This has enabled Hydro One to extend its assessment methodology to improve its focus on noncondition risk factors. More details are found in Exhibit, Tab, Schedule.
5 Filed: -0- EB--0 Tab Page of. Regional Planning Process In accordance with the Ontario Energy Board report, Renewed Regulatory Framework for Electricity Distributors: A Performance Based Approach ( RRFE ), all distributors are required to participate and align wth the regional planning process and activities., Tab, Schedule describes Hydro Ones participation in the regional planning process.. Common Corporate Costs OM&A Asset Management The Hydro One Transmission and Distribution businesses are operated using the Asset Management model. The model separates the asset management functions of planning, decision-making and approvals from the services functions of engineering, construction, customer service and grid operations which execute approved plans. The Asset Management organization focuses on ensuring that the necessary transmission and distribution assets are planned, acquired, constructed, maintained and operated such that they deliver the required function and level of performance expected by customers in a sustainable manner over the long term. See Exhibit C, Tab, Schedule for more detail.. Distribution Assets Investment Overview The Distribution Asset Investment Overview (Exhibit D, Tab, Schedule ) summarizes the results of the Asset Risk Assessment process for the key distribution assets and their primary risk factors. These results are utilitize in the identification and prioritization of asset needs to assist in the investment plan development of both the capital and operating and maintenance work programs.
SUMMARY OF CAPITAL EXPENDITURES
Filed: May, EB--00 Page of SUMMARY OF CAPITAL EXPENDITURES.0 SUMMARY OF CAPITAL BUDGET The proposed capital expenditures result from a rigorous business planning and work prioritization process that reflects
The Integrated Planning and Performance Framework
The Integrated Planning and Performance Framework Issue This briefing note provides an overview of the City's Integrated Planning Multi-Year Budgeting and Performance Framework and addresses four major
SHARED SERVICES CAPITAL - CORNERSTONE
Filed: May, 0 EB-0-00 Exhibit D Schedule Page of SHARED SERVICES CAPITAL - CORNERSTONE.0 OVERVIEW The Cornerstone Project is part of the overall information technology ( IT ) strategy to replace several
Track 1 Business & Entrepreneurship Education
Track 1 Business & Entrepreneurship Education iexec The course provides ICT related business education that enables learners to develop new strategies to transform their organization and business through
OPERATIONS CAPITAL. The Operations Capital program for the test years is divided into two categories:
Filed: September 0, 00 EB-00-0 Tab Schedule Page of OPERATIONS CAPITAL.0 INTRODUCTION Operations Capital funds enhancements and replacements to the facilities required to operate the Hydro One Transmission
RISK ADVISORY SERVICES. HYDRO UTILITIES Overview of Internal Audit & Control Services: 2014 Credentials
RISK ADVISORY SERVICES HYDRO UTILITIES Overview of Internal Audit & Control Services: 2014 Credentials THE INCREASED IMPORTANCE OF INTERNAL CONTROLS FOR HYDRO UTILITIES TO MEET THE OBJECTIVES OF FINANCIAL
Ontario Energy Board. 2014-2017 Business Plan
Ontario Energy Board 2014-2017 Business Plan Ontario Energy Board P.O. Box 2319 2300 Yonge Street 27th Floor Toronto ON M4P 1E4 Telephone: (416) 481-1967 Facsimile: (416) 440-7656 Toll-free: 1 888 632-6273
CHAPTER 8 ASSET MANAGEMENT
CHAPTER 8 ASSET MANAGEMENT 8.1 Introduction An additional task of the WRMP was to educate and engage GWA personnel in the concepts of asset management. Three specific areas of asset management have been
COST EFFICIENCIES/PRODUCTIVITY
Updated: 0-0-0 EB-0-0 Schedule Page of 0 COST EFFICIENCIES/PRODUCTIVITY.0 INTRODUCTION Hydro One has updated this exhibit to improve the information on Cost Efficiencies and Productivity initiatives and
TRANSMISSION BUSINESS PERFORMANCE
Filed: 0-0- Tx 0-0 Rates Tab Schedule Page of TRANSMISSION BUSINESS PERFORMANCE.0 INTRODUCTION 0 Hydro One is focused on the strategic goals and performance targets in the area of safety, customer satisfaction,
2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology
2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology Version Number 1 26 June 2015 Tasmanian Networks Pty Ltd (ACN 167 357 299) Table of contents 1 Introduction... 1 2 Meeting our
Transit Asset Management MBTA Initiatives
Transit Asset Management MBTA Initiatives Standing Committee on Audit and Finance March 3, 2015 1 Agenda TAM overview MAP 21 requirements MBTA TAM initiatives: Asset Management Plan Decision Support Tool
PMI Standard for Portfolio Management
Project : how organizations can measure and improve their performance PMI Standard for Milan, April 20th 2011 Walter Ginevri, PMP, PgMP Agenda 2 Evolution of PMI standard of PfM PfM definition and high-level
UPTIME MAGAZINE. june/july15 JUNE/JULY 2015. uptimemagazine.com
june/july15 UPTIME MAGAZINE JUNE/JULY 2015 uptimemagazine.com AM Developing Plans Creating Value From Physical Assets by Mark Ruby 46 june/july 15A sset management plans form the cornerstone of an effective
White Paper. www.geodecisions.com
White Paper www.geodecisions.com A Geo Spatial Total Asset Management System (TAMS) To Improve Asset Management Decision Making Fall 2013 Abstract This paper describes a Geospatial Total Asset Management
The Asset Management Landscape
The Asset Management Landscape ISBN 978-0-9871799-1-3 Issued November 2011 www.gfmam.org The Asset Management Landscape www.gfmam.org ISBN 978-0-9871799-1-3 Published November 2011 This version replaces
ACG s Growth Strategy and High Performance Business Consulting Services
ACG s Growth Strategy and High Performance Business Consulting Services ACG delivers telecom market share/forecast reports, consulting services, business case analysis, product and service message testing.
Getting to YES: Moving Utility Asset Management From Theory to Implementation
BCWWA 2011 Gold Sponsor main title of presentation subtitle of presentation if required name, designations title Getting to YES: Moving Utility Asset Management From Theory to Implementation RESULTS FROM
Concur Customer Experience 2015 REPORT. Concur // Customer Experience 2015 Report
Concur Customer Experience 2015 REPORT 1 Contents 3 Welcome Contents 4 Gathering feedback 5 The impact of your feedback 5 User experience evolution 5 Product reliability 7 Looking toward the future 7 Customer
COMMON CORPORATE COSTS CAPITAL - INFORMATION TECHNOLOGY
Updated: 0-0-0 EB-0-0 Tab Page of COMMON CORPORATE COSTS CAPITAL - INFORMATION TECHNOLOGY.0 OVERVIEW 0 Information Technology ( IT ) refers to computer systems (hardware, software and applications) that
A Systems Engineering Approach to Risk-based Asset Management
A Systems Engineering Approach to Risk-based Asset Management Michael Salvato, Executive Program Manager NYCT Enterprise Asset Management Program Office Office of the President Email: [email protected]
Asset Management Primer. the Canadian Infrastructure Report Card
Canadian Infrastructure Report Card Asset Management Primer the Canadian Infrastructure Report Card For more information on this Report Card, or the project, please contact [email protected].
Vision 2050 An Asset Management Strategy. Jaclyn Cantler Manager, Transmission Planning, PHI
1 Vision 2050 An Asset Management Strategy Jaclyn Cantler Manager, Transmission Planning, PHI 2 Agenda Case for Change About Vision 2050 Status Closing System Design Cybersecurity Interface with distributed/dispersed
Tasmanian Transmission Revenue Proposal
Tasmanian Transmission Revenue Proposal An overview for Tasmanian electricity consumers Regulatory control period 1 July 2014 30 June 2019 Tasmanian Networks Pty Ltd About TasNetworks We are Tasmania s
Principles of Execution. Tips and Techniques for Effective Project Portfolio Management
Principles of Execution Tips and Techniques for Effective Project Management Roadmap Develop A Shared Vision for Management Understanding the Difference between Project Management Reviews and Management
Attachment 2-1 Distribution System Plan Attachment 2-2 OEB Appendix 2-FA and 2-FC REG Expansion Investment
Waterloo North Hydro Inc. EB-2015-0108 Exhibit 2 Page 1 of 95 Filed: May 1, 2015 TABLE OF CONTENTS 2.5 EXHIBIT 2 - RATE BASE.... 2 2.5.1 Rate Base...2 2.5.1.1 Overview... 2 2.5.1.2 Gross Assets Property
Changing data needs from a life cycle perspective in the context of ISO 55000
Changing data needs from a life cycle perspective in the context of ISO 55000 Mr. Ed de Vroedt and Mr. Peter Hoving Affiliation: UMS Group Europe; [email protected], +316 1026 6162 ABSTRACT This paper
Asset Management Policy March 2014
Asset Management Policy March 2014 In February 2011, we published our current Asset Management Policy. This is the first update incorporating further developments in our thinking on capacity planning and
IAM Certificate in Asset Management Ver1.2 January 2013
IAM Certificate in Asset Management Ver1.2 January 2013 Introduction 1.1 The IAM Certificate is aimed primarily at new entrants and those with some experience in asset management roles and seeking to achieve
EXECUTIVE SUMMARY...5
Table of Contents EXECUTIVE SUMMARY...5 CONTEXT...5 AUDIT OBJECTIVE...5 AUDIT SCOPE...5 AUDIT CONCLUSION...6 KEY OBSERVATIONS AND RECOMMENDATIONS...6 1. INTRODUCTION...9 1.1 BACKGROUND...9 1.2 OBJECTIVES...9
Real Property Portfolio Optimization
Real Property Portfolio Optimization Improving and Modernizing Management of the Federal Real Property Portfolio to Optimize Space, Financial Resources and Energy Impact www.pwc.com/publicsector Contents
SEC. 1301. STATEMENT OF POLICY ON MODERNIZATION OF ELECTRICITY GRID.
TITLE XIII--SMART GRID SEC. 1301. STATEMENT OF POLICY ON MODERNIZATION OF ELECTRICITY GRID. It is the policy of the United States to support the modernization of the Nation's electricity transmission and
Business Unit Asset Management Plan Framework & Guidelines
Draft Report Business Unit Asset Management Plan Framework & Guidelines Prepared for March 2014 Contents Section Page Contents... i Background... 1 Asset Management Plans... 1 The AMP Framework... 1 About
We do what we say we will do.
We do what we say we will do. Investor Presentation 1 November 2013 Forward-Looking Statements Certain statements in this document are forward-looking statements, which reflect management s current beliefs
itrak - Change Management
itrak - Change Management An Agency Adapting to Change B&O Committee May 2015 Contents itrak Change Management Strategy Call To Action! Change Management, Communication and Training Activities Lessons
European Master in Sustainable Energy Systems Management
SPECIALISATION SYLLABUS : Sustainable Energy Management European Master in Sustainable Energy Systems Management Contents: TOTAL HOURS 1. Socio-economic aspects of the energy 50 2. Renewable energy markets
Total Quality Management (TQM) presented by Dr. Eng. Abed Schokry
Department of Industrial Engineering Total Quality Management (TQM) presented by Dr. Eng. Abed Schokry Policy, strategy and goal deployment Chapter 4 ١ Chapter 4: Learning Outcomes After successful studying
Practical Approaches to Achieving Sustainable IT Governance
Practical Approaches to Achieving Sustainable IT Governance Beyond Mandates: Getting to Sustainable IT Governance Best Practices Agenda IT Governance Definition IT Governance Principles IT Governance Decisions
Defining Ontario s Typical Electricity Customer
Ontario Energy Board Report of the Ontario Energy Board Defining Ontario s Typical Electricity Customer EB-2016-0153 April 14, 2016 Intentionally blank OEB Report: Defining Ontario s Typical Electricity
Proposal to Consolidate Post-Fukushima Rulemaking Activities
Proposal to Consolidate Post-Fukushima Rulemaking Activities On January 28, 2014, the U.S. Nuclear Regulatory Commission s (NRC s) Fukushima Steering Committee endorsed an NRC staff proposal for integrating
HYDROPOWER PROGRAM SUSTAINABLE HYDROPOWER PLANNING IN MYANMAR
HYDROPOWER PROGRAM SUSTAINABLE HYDROPOWER PLANNING IN MYANMAR www.ifc.org/mekonghydro December 1, 2015 THE VISION Hydropower development based on integrated water, land and ecosystem planning, reconciling
Queensland Australia Smart Grid Trials
Queensland Australia Smart Grid Trials Grahame Foulger Director SmartGrid Partners [email protected] +61419502980 Company or Institution Logo 4 th International Conference on Integration
INTRODUCTION AND SUMMARY OF O&M COSTS
EB-00-0 Exhibit F Tab Schedule Page of CUSTOMER SERVICES INTRODUCTION AND SUMMARY OF O&M COSTS The Customer Services division performs activities that are required to provide services to customers connected
PROJECT AND PORTFOLIO MANAGEMENT - NUCLEAR
Page 1 of 5 PROJECT AND PORTFOLIO MANAGEMENT - NUCLEAR 1.0 PURPOSE This evidence provides an overview of the nuclear operations project portfolio and other related project work. The project portfolio includes
K - 12 Principal & Superintendent
BOSA COMPETENCY MATRIX Minnesota Administrative Licensure K - 12 Principal & Superintendent WINONA STATE UNIVERSITY COLLEGE OF EDUCATION DEPARTMENT OF EDUCATIONAL LEADERSHIP Name: Place of Employment Mailing
UIC involvement. Teodor Gradinariu Senior Technical Advisor UIC
Asset Management UIC involvement Teodor Gradinariu Senior Technical Advisor UIC The environment The preparations for the European Single Market 1993 led to liberalisation of transportation markets Restructuring
project portfolio management Effectively plan, manage, and control projects and resources Planview Enterprise Planview Project Portfolio Management
project portfolio management Effectively plan, manage, and control projects and resources Planview Project Portfolio Management gives you the tools you need to effectively manage projects and resources
THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini)
PAGE 1 THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini) Ing. Guido Mattu More than 25 years experience in Engineering and Project Management activities
CITY OF GUNNISON EMPLOYEE PERFORMANCE APPRAISAL FORM 2013
CITY OF GUNNISON EMPLOYEE PERFORMANCE APPRAISAL FORM 2013 Name: Position: Anniversary Date in Position: Department: Supervisor: Appraisal Period: from to PURPOSE Communication about performance between
CODE: E.003 Financial Services BUDGET AND BUSINESS PLANNING POLICY. 1.2 The essential activities covered by this policy include:
BUDGET AND BUSINESS PLANNING POLICY CONTENTS 1.1 Budget and business planning is undertaken to support strategic planning and decision-making and to serve accountability by enabling administration to plan
Annual Assessment Report, 2012-2013 College of Business Administration Sharyn Gardner, Assessment Director
Annual Assessment Report, 2012-2013 College of Business Administration Sharyn Gardner, Assessment Director The Sacramento State College of Business Administration (CBA) is accredited by the AACSB and thus
How To Manage Asset Management
NHI Training Course on Transportation Asset Management Module 2 Asset Management Framework and Principles Ref Asset Management Guide Chapters 1 and 2 Learning Objectives Define transportation asset management
The Value of Optimization in Asset Management
Experience the commitment white PAPER The Value of Optimization in Asset Management Better decisions to help utilities balance costs, risks, opportunities and performance May 2015 cgi.com Improving the
Annual Risk Assessment and Audit Plan Fiscal Year 2015/2016
Annual Risk Assessment and Audit Plan Fiscal Year 2015/2016 Office of the Internal Auditor May 2015 Table of Contents Introduction... 3 Risk Assessment Process... 3 Interpreting Risk Assessment Results...
CUSTOMER EXPERIENCE PLAN Executive Summary
At the core of the 2012 strategy are five strategic focus areas that prescribe a suite of people, process and technology oriented solutions. These areas are: Operations To ensure satisfied customers through
How To Manage Transportation Asset Management
1 TRANSPORTATION ASSET MANAGEMENT THE NEW BUSINESS MODEL FOR TRANSPORTATION AGENCIES Presented at the AASHTO Subcommittee on Transportation Finance Policy Business Meeting Irvine, California June 26, 2012
Leading Practices in Business Transformation
Leading Practices in Business Transformation Stick To The Game Plan Business Transformation Conference October 2013 While the typical risks and challenges seem intuitive, why do business transformation
LONDON CORPORATE ASSET MANAGEMENT PLAN 2014
LONDON CORPORATE ASSET MANAGEMENT PLAN 2014 ACKNOWLEDGEMENT Acknowledgement The Corporate Asset Management office would like to acknowledge the efforts of the staff of the individual City of London Service
Developing Business Architecture with TOGAF
Developing Business Architecture with TOGAF Building Business Capability 2013 Las Vegas, NV Armstrong Process Group, Inc. www.aprocessgroup.com Objectives Introduce The Open Group Architecture Framework
Fundamentals of Asset Management. Step 8. Optimize Capital Investment A Hands-On Approach
Fundamentals of Asset Management Step 8. Optimize Capital Investment A Hands-On Approach Tom s bad day Fundamentals of Asset Management 2 Fourth of 5 core questions 4. What are my best O&M and CIP investment
Cybersecurity Framework. Executive Order 13636 Improving Critical Infrastructure Cybersecurity
Cybersecurity Framework Executive Order 13636 Improving Critical Infrastructure Cybersecurity National Institute of Standards and Technology (NIST) Mission To promote U.S. innovation and industrial competitiveness
Introduction to Enterprise Risk Management at UVM DRAFT
Introduction to Enterprise Management at UVM 1 Enterprise What is Enterprise Management? Enterprise risk management is a structured, consistent, and continuous process across the whole organization for
EXECUTIVE SUMMARY. Asset Management Relationships and Dependencies. Introduction
EXECUTIVE SUMMARY Introduction The Asset Management Plan demonstrates sound stewardship of the Region s existing assets to support services at desired levels and to ensure the support of the Region s infrastructure
Executive MBA. Course Descriptions FIRST PERIOD PRE-PROGRAM: FINANCIAL ACCOUNTING ONLINE TOOLS WORKSHOP MANAGERIAL SKILLS WORKSHOPS
Executive MBA Course Descriptions PRE-PROGRAM: FINANCIAL ACCOUNTING The main objective of the pre-program in financial accounting is to provide students with a foundation in basic accounting concepts.
Data Management Practices for Intelligent Asset Management in a Public Water Utility
Data Management Practices for Intelligent Asset Management in a Public Water Utility Author: Rod van Buskirk, Ph.D. Introduction Concerned about potential failure of aging infrastructure, water and wastewater