1 GENERAL: Some of the Districts largest capital expenditures are from new construction, facility upgrades, and renovations. A single project can run into the millions of dollars, involving engineering, design, contractors, materials, and construction. The Construction Management Department is responsible for the design, construction and maintenance of the District's buildings and grounds and the management of its real property. AUDIT OBJECTIVES: 1) Comprehensive policies and procedures for Construction Management have been established; 2) The District is in compliance with all applicable laws and regulations; 3) The District has an effective system of controls in place that assist in appropriately managing construction-related cost; 4) Construction-related payments are made in accordance with contractual limitations or maximums; 5) Construction project bids were awarded in compliance with applicable rules and regulations; 6) Changes from the initial contract award amount and the final contract price were appropriately negotiated and documented; 7) Determine that payments for various components of construction and development cost are not duplicated; 8) Internal controls over change orders to the contract are appropriate and adequately documented. 9) District facilities and construction projects are adequately protected from liability by insurance and bonding programs;
2 10) Project close outs (e.., punch lists, certificates of occupancy and warranties) are conducted appropriately and documented; 11) Information systems are reliable and timely and accurate information is available to district management and the Board of Trustees: 12) Contractors (CG, CM, etc.) complied with the provisions stated in the contract. AUDIT PROCEDURES: 1) General a) Obtain: i. Policies and Procedures ii. Prior Audit Reports iii. External Auditor Management Reports iv. Federal and State Laws governing construction and related information v. Job Descriptions and Organizational Chart vi. Minutes of the Board approving contracts vii.significant Contracts b) Review policies and procedures to determine adequacy. Ensure that all relevant policies and procedures have been communicated to appropriate personnel. c) Review prior examination reports to determine whether corrective action has been implemented for noted deficiencies. d) Become familiar with all laws and regulation impacting construction and construction management. e) Document the procedures and flow of documents for construction project operations. f) Review construction contracts (i.e. architect, engineer and construction company)
3 i. Contract written policies and procedures for completeness, adequacy, and proper approval ii. Take note of the special contract provisions, rates, clauses, etc. iii. Highlight significant and specific terms iv. Determine if fee and reimbursement guidelines appear reasonable. g) Obtain copies of all reports generated for each construction project, determine their use and distribution. h) Determine that adequate records are received from the contractor to monitor progress (daily inspection reports, job meeting minutes, job photographs, update schedules, material and equipment delivery schedules, drawing revisions, daily job progress reports/diaries, etc.) i) Review minutes of all construction meetings held. Identify unusual situations that may require additional testing or follow-up during the examination. 2) Contract Formation General Objective: Determine that the methods selected for design and construction of district facilities are appropriate and provide the best value and risk profile. a) Select construction projects for detailed testing. b) Review Bid and Award process c) Obtain a copy of the bid package for the project. This should include the following items: i. Proposal ii. Agreement iii. General Conditions iv. Supplementary (Special) Conditions v. Technical Specifications vi. Drawings Ensure that the bidders are requested to submit their proposals in a particular format that is designed to enhance comparison of bids. Determine if bidders are required to submit bid bonds and certificates of insurance.
4 d) Examine advertising copy regarding the construction project to ensure that it met government requirement for notification. e) Document the process for qualifying bidders. Does the District determine in advance of bid opening whether or not the contractors responding are stable and have the financial wherewithal to complete the project? If this process is performed after bid opening, how do we ensure that the bid is not awarded to an unsatisfactory contractor simply because he is low bid? f) Determine which District administrator is responsible for replying to questions from bidders prior to bid opening. Is there a mechanism to ensure that no conflicting information is presented to bidders? If additional information is prepared for one bidder by request, is it automatically sent to all bidders? g) Does the District conduct pre-bid conferences and site visits for all bidders? Is this jointly or separately? Obtain a copy of the agenda for the pre-bid conference and copies of any minutes maintained. h) Document the process for receiving and controlling bids received prior to bid opening. Ensure that controls are adequate to prevent breaches of confidentiality. Ensure that a log is maintained listing the date and time of receipt of all bids. Determine that bids received after bid opening are returned unopened to the bidder after documenting the time and date of receipt. i) Obtain a copy of the bid tabulation. Review the accuracy with which the bids were transcribed, calculated, and awarded. Determine if a fair price estimate was determined in advance of bid opening. If so, comment if significant fluctuations were noted between the bids received and the price estimated. 3) Contract Review: For selected contracts, perform the following: a) Conduct a review of all construction contract documents including: i. Specifications ii. Correspondence iii. Bids iv. Contractor Records
5 v. Contract billing vi. Change order documentation vii.insurance certificates viiishop drawings ix. Material certificates x. Signed Bond forms xi. Fabrication, shipping and construction schedules xii.equipment Tagging procedures. xiii Subcontractor and material supplier bids. b) Document and analyze construction process controls which consist of: i. Planning and Scheduling Management Process that plans project activities, monitors completion of those activities, predicts timing of future activities, and reports schedule status. ii. Cost Management Process that estimates, monitors, predicts, and reports project costs. iii. Change Management Process that estimates the impact of change, enables and documents the change decision, and integrates the change into the project scope of work. Planning and Scheduling Management Process i. Determine how the District monitors, inspects, and documents progress of the project schedule. Determine how the District ensures component materials meet contract requirements. ii. Determine if the contractor submitted a project schedule that contains a clear recognition of the task of work, the proper order of their appearance on the job, correct duration of work, complete resource allocations to task, and a clear purchasing and delivery register. iii. Determine if receipt of documents from contractors is tracked on a log or check sheet to ensure items have been received. iv. Determine if all the proper building permits were obtained. v. Determine if an insurance certificate log is prepared. Review insurance certificates received and evaluate for propriety. Such insurance should
6 include general liability, automobile liability, workers compensation, and umbrella coverage. Verify the adequacy and authenticity of insurance coverage. Ensure that insurance was actually purchased. Determine how subcontractors insurance requirements are monitored. vi. Review various bonds received from the successful bidder, including the bid bond, payment bond, performance bond and possibly a maintenance bond. If possible, confirm the validity and adequacy of the bonds. Ensure the bonds were actually purchased. vii.determine how the District maintains Document Control. Project Directory Shop Drawings Architectural Drawings Request for Information Cost Event logs Meeting Minutes Schedules Inspections, etc. Cost Management Process i. Determine and document the process used by the District to document, track and report cost incurred on construction projects. Determine if the District analyses these reports daily to ensure cost are in line with contract, or issues can be corrected quickly. Determine if controls are in place to properly monitor and document cost. ii. Determine and document the method used to calculate progress payments. Ensure that there is a clear correlation between the payment processed and the percentage of work completed. iii. Obtain the original schedule of values and all requests for payments. Schedule RFP's and compare to schedule of values. Investigate unusual differences. iv. Review the schedule of payment requests or progress billings. Examine underlying RFP's and ensure that necessary evidence inspections and approval is adequately documented. Ensure that sales tax has not been included on tax-exempt improvements. v. Verify that the contractor submits all necessary lien waivers with progress payment invoices.
7 vi. Document the method used to calculate retention. (Note: Retention amounts should be documented in the contract in order to be enforceable.) On the RFP selected for testing, ensure that the appropriate retention amounts were withheld. Change Management Process i. Determine and document the process used by the District to review, verify and document change orders. Determine if the District obtains independent estimates of cost for the changes. ii. Obtain the schedule of change orders (or change order log). Examine all change orders issued, documenting the reason for the change and the amount of the change. Ensure that necessary changes are identified promptly and properly confirmed and approved. iii. Examine supporting documentation for change order pricing and confirm the accuracy. Ensure that the change orders represent changed or added work, and not work covered under the scope of the base contract or previously issued change orders. iv. Perform a re-calculation of the change order to ensure the basic mathematics of the contractor is correct. v. Determine if change order work descriptions suggest engineering, construction, and/or manufacturing problems that should be charged back to another party. vi. Ensure that change orders were not split to avoid Board of Trustee approval requirements. vii.for Projects with significant contingency allowances, examine all contigent costs for approval prior to payment. 4) Contract Close-out a) Document procedures for formally closing out construction contracts. Construction close-out should be a structured process involving final acceptance of the contractor's work, receipt of acceptable documentation required by contractual terms, and an evaluation of the contractor's performance.
8 b) Ensure that final payment of a construction contract and release of retention does not occur until the following documentation is received: i. Release of liens from the contractor and its suppliers and subcontractors ii. Titles to major equipment incorporated in the facility iii. Warranty documentation iv. As-built drawings v. Inspections and acceptance records vi. Operating and Maintenance Manuals vii.(possibly) spare parts, special tools, and consumable supplies vii.punch list clearance ix. Certificates of Occupancy (or equivalent) c) Ensure the final inspection is completed and the project meets standards before final payments. d) Ensure the "as-built" final drawings are obtained, secured, filed, and protected. e) Determine who is responsible for preparing the post-performance evaluation. Examine the completed evaluation for adequacy. 5) Budget a) Obtain the construction project's budget reports. Compare to the payment schedules maintained by the Construction Department. Review for unexplained differences, significant overdrafts or serious fluctuations from amounts initially budgeted, and unusual entries. b) Determine what procedures are followed by the Construction Department accountant and the Finance Department to ensure the accuracy and validity of invoices submitted for payment on construction projects. Ensure that controls are adequate to confirm approval and adequacy of funds available. c) As necessary, test a sample of transactions for accuracy, reasonableness, and adequacy of supporting documentation.
Request of Qualification Proposal for Construction Management Services
Request of Qualification Proposal for Construction Management Services Dated June 10, 2014 Table of Contents Overview 3 Introduction 4 Scope of Construction Managers Services 4 Submission of Qualifications
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive
Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86
Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho
Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho REQUEST FOR QUALIFICATIONS Independent School District No. 1, Lewiston, Idaho ( District ) is seeking responses from individuals
Construction Management Standards of Practice
Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388
REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT
ADVERTISEMENT: REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT The WALTON COUNTY SCHOOL DISTRICT will receive
Purchases from $750 $1,500 requires 3 Verbal Quotes. Purchases from $1,501 $24,999 requires 3 Written Quotes
Introduction A Guide for Contractors and Suppliers The Purchasing Office should be your first point of contact with the County. Our role is to bring together users and suppliers to ensure that the County
Checklist 26: How Owners Can Avoid Litigation on Construction Projects
Checklist 26: How Owners Can Avoid Litigation on Construction Projects While it is impossible to completely avoid litigation on construction projects, certain steps can be taken to minimize the potential
GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES
GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES Greenburgh Central School District No. 7 ( The District ) invites proposals to perform construction management
Construction Management Services Delmar School District RFP No. DSD16001-CONSTR_MAN
Construction Management Services Delmar School District RFP No. DSD16001-CONSTR_MAN The Delmar School District (DSD) is seeking the professional services of a Construction Management (CM) firm for the
AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES. Responsibilities of Construction Manager Scope of Construction Manager s Basic Services
AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES Article I Article II Article III Article IV Article V Article VI Article VII Article VIII Article IX Responsibilities of Construction Manager Scope of Construction
NORTH COLONIE CENTRAL SCHOOL DISTRICT 91 FIDDLERS LANE LATHAM, NEW YORK 12110-5349 INVITATION FOR CONSTRUCTION MANAGEMENT PROPOSALS
NORTH COLONIE CENTRAL SCHOOL DISTRICT 91 FIDDLERS LANE LATHAM, NEW YORK 12110-5349 INVITATION FOR CONSTRUCTION MANAGEMENT PROPOSALS The North Colonie Central School District invites your firm to submit
REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office
REQUEST FOR PROPOSALS (RFP) - Construction Management Services From: Germantown School District Project: Germantown School District Addition & Renovations to Rockfield Elementary School N132 W18473 Rockfield
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES. Part I: Qualifications Information
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES A. General Information Part I: Qualifications Information The Tacoma School District is soliciting Qualifications for onsite
Request for Proposal Architectural/Engineering Services. Adapt/SouthRiver CHC. P a g e 1
P a g e 1 Request for Proposal Architectural/Engineering Services Adapt/SouthRiver CHC RFP for Architectural/Engineering Services P a g e 2 Introduction (SRCHC), a Federally Qualified Health Center, is
TABLE OF CONTENTS. Prefacej... 1
TABLE OF CONTENTS Prefacej... 1 How Can I Receive Copies Of Solicitations?j... 2 Bidder s List... 2 Vendor Registration System... 2 Public Notice/Advertisement... 3 Posting... 3 Internet... 3 Pre-Bid Conferences...
IV. Orders, Quotations, Bids and Request for Proposal (RFP) Requirements
Policy 707 Noninstructional Operations and Business Services Purchasing I. Purpose This policy defines the process for purchasing supplies, equipment, materials and services that will be used to meet the
MANAGING THE PROJECT RECORD
MANAGING THE PROJECT RECORD Project Record Filing System 2 Agency Submittals 2 Site Acquisition 3 Planning 3 Pre-Qualification of Bidders 3 Bidding 4 Construction 4 Inspection 4 Legal 5 Contracts 5 Accounting
REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER
RFP #2016-02 REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES FOR SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RELEASE DATE: January 29, 2016 DUE DATE: February
REQUEST FOR QUALIFICATIONS (RFQ) FOR CONSTRUCTION MANAGEMENT SERVICES
REQUEST FOR QUALIFICATIONS (RFQ) FOR CONSTRUCTION MANAGEMENT SERVICES (Construction Manager At-Risk) FOR PROJECTS IN THE CENTER UNIFIED SCHOOL DISTRICT April 7, 2005 The ( District ) is seeking Statements
CHAPTER 23. Contract Management and Administration
Date Issued: June 12, 2009 Date Last Revised: September 28, 2015 CHAPTER 23. Contract Management and Administration Table of Contents CHAPTER 23. Contract Management and Administration... 23-1 23.1 Policy...
Public Works Contract Completion
I. Policy A. The Port will formally identify when public works construction contracts are completed in order to administer payments in accordance with Washington statutes and in order to identify warranty
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR)
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR) For the Project: CITY OF KATY NEW KATY FIRE STATION #2 Issued: August 13, 2015 Katy Fire Station #2 August 13, 2015 Page 1 of 17 Request
Quality Procedures and Work Instructions Manual
Quality Procedures and Work Instructions Manual Revision Number: (1) ISSUED TO: MANUAL NO: REVISION NO: ISSUE DATE: President Date 1 ii. Table of Contents 1 of 4 0 Section Number Name Revision Date i.
AUSTIN INDEPENDENT SCHOOL DISTRICT INTERNAL AUDIT DEPARTMENT PAYROLL AUDIT PROGRAM
PAYROLL GENERAL: The Payroll Department is responsible for processing all District payrolls and compliance with all rules and regulations pertaining to and/or resulting from payroll operations which includes
SAMPLE FINANCIAL PROCEDURES MANUAL
SAMPLE FINANCIAL PROCEDURES MANUAL Approved by (organization s) Board of Directors on (date) I. GENERAL 1. The Board of Directors formulates financial policies, delegates administration of the financial
STATE OF MINNESOTA GRANT CONTRACT
STATE OF MINNESOTA GRANT CONTRACT This grant contract is between the State of Minnesota, acting through its Department of Labor and Industry, Apprenticeship Unit ("State") and [FULL NAME AND ADDRESS OF
IMPORTANT! - Please use the attached Application for Payment. All payment requests must be submitted on our form. Thank you!
` SUBCONTRACTOR: PHONE PROJECT: LOCATION: Page 1 of 6 SUBCONTRACT (SHORT FORM) JOB NO.: COST CODE: PRICE: This agreement is made and effective, by and between SUN CONSTRUCTION & FACILITY SERVICES, INC.
Contracting for Services
Contracting for Services A National State Auditors Association Best Practices Document Published by the National State Auditors Association Copyright 2003 by the National State Auditors Association. All
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES ISSUED BY: INGLEWOOD UNIFIED SCHOOL DISTRICT Issued: November 20, 2015 Due: December 18, 2015 SCHEDULE OF EVENTS INGLEWOOD UNIFIED SCHOOL
AGREEMENT BETWEEN OWNER AND ARCHITECT/ENGINEER (Small Projects-Construction Costs Generally Under $100,000)
AISD PROJECT NO. PROJECT TITLE AND ADDRESS: AGREEMENT BETWEEN OWNER AND ARCHITECT/ENGINEER (Small Projects-Construction Costs Generally Under $100,000) This Agreement ( Agreement ) is made as of the day
Project Closeout Module 1 Construction Closeout Checklist
Project Closeout Module 1 Construction Closeout Checklist August 5, 2005 1 OAR Challenge How to Close the Project (Drain the Swamp) And Protect District Assets from Contractors (Alligators) 2 Project Closeout
TABLE OF CONTENTS I. PURPOSE... 3 II. GOALS...3 III. DEFINITIONS... 3-4
CARROLL COUNTY MINORITY BUSINESS ENTERPRISE POLICY Department of the Comptroller Bureau of Purchasing 10/03/02 TABLE OF CONTENTS I. PURPOSE... 3 II. GOALS...3 III. DEFINITIONS... 3-4 IV METHODS OF PROCURMENENT
RECRUITMENT LETTER. To be included on our current bidders list, please fill in the Contractor Qualification Registration, which includes:
CITY OF BRUNSWICK Department of Community Development 601 Gloucester Street * Post Office Box 550 * Brunswick * Georgia * 31520-0550 * (912) 267-5530 * Fax (912) 267-5542 Cornell L. Harvey, Mayor Felicia
NEWBURGH ENLARGED CITY SCHOOL DISTRIST NEWBURGH, NEW YORK REQUEST FOR PROPOSAL ARCHITECTURE SERVICES 2015 2016
NEWBURGH ENLARGED CITY SCHOOL DISTRIST NEWBURGH, NEW YORK REQUEST FOR PROPOSAL ARCHITECTURE SERVICES 2015 2016 Notice is hereby given that the Board of Education of the Newburgh Enlarged City School District,
EXHIBIT A SCOPE OF SERVICES CONSTRUCTION MANAGEMENT TEAM POSITIONS AND REQUIREMENTS
EXHIBIT A SCOPE OF SERVICES CONSTRUCTION MANAGEMENT TEAM POSITIONS AND REQUIREMENTS 1.0 SCOPE OF SERVICES 1.1 General Information LAUSD requires construction management services to manage and expedite
Document Management Operations Audit Checklist
PROJECT PLANNING AND START-UP 1. Do document management personnel have copies of reference materials: a. Document Management Standard Practices? b. Computerized Tracking System User Manual? 2. Are document
AGREEMENT FOR PROGRAM MANAGEMENT SERVICES WITH SINGLE GENERAL CONTRACTOR DELIVERY (Ocean View Elementary School Project)
AGREEMENT FOR PROGRAM MANAGEMENT SERVICES WITH SINGLE GENERAL CONTRACTOR DELIVERY (Ocean View Elementary School Project) This Program Management Services Agreement ( Agreement ) is made and entered into
MASTER AGREEMENT FOR PROJECT MANAGEMENT AND CONSTRUCTION MANAGEMENT SERVICES
MASTER AGREEMENT FOR PROJECT MANAGEMENT AND CONSTRUCTION MANAGEMENT SERVICES THIS AGREEMENT is made and entered into this day of, 2007, by and between the University of Washington ( Owner ) and, ( Project
STATE OF MINNESOTA MINNESOTA STATE COLLEGES AND UNIVERSITIES Minnesota State University, Mankato/System Office
STATE OF MINNESOTA MINNESOTA STATE COLLEGES AND UNIVERSITIES Minnesota State University, Mankato/System Office SERVICES CONTRACT/P. O. # Title: THIS CONTRACT, and amendments and supplements thereto, is
CHAPTER 48-01.2 PUBLIC IMPROVEMENT BIDS AND CONTRACTS
CHAPTER 48-01.2 PUBLIC IMPROVEMENT BIDS AND CONTRACTS 48-01.2-01. Definitions. In this chapter, unless the context otherwise requires: 1. "Agency construction management" means a public improvement delivery
INSURANCE REQUIREMENTS FOR MASTER AGREEMENT CONTRACTORS
INSURANCE REQUIREMENTS FOR MASTER AGREEMENT CONTRACTORS Without limiting CONTRACTOR's indemnification of COUNTY, and in the performance of this Contract and until all of its obligations pursuant to this
AUSTIN INDEPENDENT SCHOOL DISTRICT INTERNAL AUDIT DEPARTMENT TRANSPORTATION AUDIT PROGRAM
TRANSPORTATION GENERAL: The Transportation Department provides transportation of students to and from school and other special trips. The aim of an effective transportation service delivery system must
New WMHS Construction Management Firm
New WMHS Construction Management Firm RFQ Schedule November 5, 2013 Board Meeting Approval to Advertise and use revised RFQ Week December 9, 2013 Ad runs in local papers (Thursday Dec. 12 th ) Week December
Real Estate Management Services Capital Management 10100 Fair Oaks Blvd. Suite I. Fair Oaks, CA 95815 916-863-6600 / 916-863-7501 Fax
Real Estate Management Services Capital Management 10100 Fair Oaks Blvd. Suite I. Fair Oaks, CA 95815 916-863-6600 / 916-863-7501 Fax www.capitalmgnt.com Table Of Contents 1. Mission Statement 2. Capital
AGREEMENT FOR PROFESSIONAL DESIGN SERVICES
AGREEMENT FOR PROFESSIONAL DESIGN SERVICES This Professional Design Services (this "Agreement"), made as of 20 by and between the University of Cincinnati (the "University") by the Division of Administration
How To Build A House
CONTRACT TO BUILD A HOUSE AT I. Contract Parties Now comes (builder s name) (address) and (buyer s name) (address) to hereby agree to build a house on property located at (common address) and legally described
EXHIBIT "B" CRITERIA AND BILLING FOR EXTRA SERVICES
EXHIBIT "B" CRITERIA AND BILLING FOR EXTRA SERVICES The following Extra Services to the Agreement shall be performed by Architect if needed and if authorized or requested by the District: 1. Making revisions
MANTON CONSOLIDATED SCHOOLS. REQUEST for PROPOSALS ENERGY SAVING CAPITAL IMPROVEMENT PROJECTS. On a PERFORMANCE CONTRACTING BASIS
MANTON CONSOLIDATED SCHOOLS REQUEST for PROPOSALS ENERGY SAVING CAPITAL IMPROVEMENT PROJECTS On a PERFORMANCE CONTRACTING BASIS July 16, 2010 1 NOTICE IS HEREBY GIVEN THAT THE BOARD OF EDUCATION OF MANTON
REQUEST FOR QUALIFICATIONS (RFQ) DIVISION OF THE STATE ARCHITECT INSPECTOR OF RECORD SERVICES
REQUEST FOR QUALIFICATIONS (RFQ) DIVISION OF THE STATE ARCHITECT INSPECTOR OF RECORD SERVICES 1. STATEMENTS OF QUALIFICATIONS REQUESTED The San Bernardino Community College District (District) Facilities
Project Management Procedures
1201 Main Street, Suite 1600 Columbia, South Carolina 29201 Project Management Procedures Start Up The grant becomes effective upon return of one copy of the grant award executed by the Chief Executive
CHAPTER 5 SMALL PURCHASES
PIM 98-033 CHAPTER 5 SMALL PURCHASES In this Chapter look for... 5. General 5.1 Competitive Requirements 5.2 Charge Cards for Small Purchases (Deleted) 5.3 Single Quotation 5.4 Deleted 5.5 Deleted 5.6
INTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006
INTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006 1. MANAGEMENT REVIEWS The contractor should have policies and procedures for periodic monitoring of the billing
How To Manage A Power Station
CARESERV TECHNOLOGIES, LLC SERVICE AGREEMENT COLOCATION SERVICES SCHEDULE Version 2014.1 (01.01.2014) This Schedule, together with any Order referencing this Schedule or pursuant to which the services
Request For Proposal. Furnish Schneider Business Park Signs Design Build Services. For the Cibolo Economic Development Corporation Cibolo, Texas
Request For Proposal Furnish Schneider Business Park Signs Design Build Services For the Cibolo Economic Development Corporation Cibolo, Texas The City of Cibolo, Texas Economic Development Corporation
City of Dallas Specifications for Sewer Camera Maintenance & Repair Services with Parts BM1308
City of Dallas Specifications for Sewer Camera Maintenance & Repair Services with Parts BM1308 PURPOSE: The purpose for this specification is to establish a 36 month service contract for maintenance and
TROUP COUNTY COMPREHENSIVE HIGH SCHOOL
TROUP COUNTY BOARD OF EDUCATION REQUEST FOR SEALED COMPETITIVE PROPOSALS FOR CONSTRUCTION OF: RE-FLOORING TO: TROUP COUNTY COMPREHENSIVE HIGH SCHOOL LAGRANGE, GEORGIA TROUP COUNTY SCHOOL SYSTEM LAGRANGE,
Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures.
Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Contractor City, Zip Work Phone Number: Cell Phone Number: Fax Number: Email
Fundamentals of a Construction Audit. August 7, 2014
Fundamentals of a Construction Audit August 7, 2014 Agenda Definitions Risk Based Approach What Determines Risk Fraud Construction Risks What to Audit Red Flags Why Audit Prevention Wrap-up 1 Definitions
How To Get A Job Done
CUMBERLAND COUNTY COMMUNITY DEVELOPMENT (CCCD) HOUSING REHABILITATION PROGRAM PO DRAWER 1829 707 EXECUTIVE PLACE FAYETTEVILLE, NC 28302-1829 CONTRACTOR QUALIFICATIONS: REHABILITATION CONTRACTOR'S HANDBOOK
ATTACHMENT A.6 INSURANCE REQUIREMENTS ROUTINE CONSTRUCTION, MAINTENANCE AND REPAIR PROJECTS
ATTACHMENT A.6 INSURANCE REQUIREMENTS ROUTINE CONSTRUCTION, MAINTENANCE AND REPAIR PROJECTS Contractor shall obtain insurance of the types and in the amounts listed below. A. COMMERCIAL GENERAL AND UMBRELLA
Stephenson County, Illinois
Stephenson County, Illinois REQUEST FOR PROPOSALS For EXTERIOR CLEANING OF STEPHENSON COUNTY COURTHOUSE Bids Due: Sealed proposals are due and must be received in the Stephenson County Administrator s
MASTER AGREEMENT CONSTRUCTION MANAGEMENT SERVICES
MASTER AGREEMENT CONSTRUCTION MANAGEMENT SERVICES This Master Agreement made this 11 day of December, 2012, by and between the St. Lucie County School Board (hereinafter referred to as the School Board
NEGAUNEE PUBLIC SCHOOLS. REQUEST for PROPOSALS ENERGY SAVING CAPITAL IMPROVEMENT PROJECTS. On a PERFORMANCE CONTRACTING BASIS
NEGAUNEE PUBLIC SCHOOLS REQUEST for PROPOSALS ENERGY SAVING CAPITAL IMPROVEMENT PROJECTS On a PERFORMANCE CONTRACTING BASIS July 26, 2010 NOTICE IS HEREBY GIVEN THAT THE BOARD OF EDUCATION OF NEGAUNEE
REQUEST FOR PROPOSAL #R13004 INFORMATION SECURITY PENETRATION ASSESSMENT
REQUEST FOR PROPOSAL #R13004 INFORMATION SECURITY PENETRATION ASSESSMENT Joliet Junior College Request for Proposal INFORMATION SECURITY PENETRATION ASSESSMENT RFP Opening MAY 22, 2013 @ 2:00P.M. Background
Exhibit 7.9 Sample Loan Operations Risk Based Audit Program
Sample Loan Operations Risk Based Program Inquire about and review written procedures followed during the process of opening and setting up new loans on the system, and procedures on loan approval and
ATTACHMENT A. Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects
Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects Pursuant to Revised Statute of Missouri Section 8.250(3), Ozarks Technical
6. WARNING BY BUYER. BUYER shall give warning of any possible hazard to any person or persons to whom BUYER resells, gives or delivers the Property
TERMS AND CONDITIONS FOR ONLINE TRANSACTIONS TO PURCHASE GP PROPERTY (VIA GOINDUSTRY DOVEBID) By submitting a bid to purchase the Property (as defined below), BUYER (as defined below) agrees that the following
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 2 1109 S. Marion Avenue, Mail Station 2015 Lake City, Florida 32025-5874
ADVERTISEMENT FOR LETTERS OF INTEREST FOR A DESIGN BUILD PROJECT (PROCUREMENT METHOD SHORTLISTING OF PROPOSERS WITH TECHNICAL AND PRICE EVALUATION BY ADJUSTED SCORE) PROCUREMENT NUMBER: E2N44 Financial
Swarthmore College Financial Risk Management Team
Index: Overview Page 1 Definitions Pages 2-4 Responsibilities Page 5 Sample Clause Language Pages 6-9 Contract Review Checklist Pages 10-12 Contract Guideline Statement Revised: May, 2013 Contracts entered
How To Get Construction Procurement Services
Construction Procurement William C. Charvat, AIA, CSI Excerpt from The Architect s Handbook of Professional Practice, 13th edition 2000 The procurement of construction services brings together the team
Greater Dayton Regional Transit Authority 4 S. Main Street Dayton, OH 45402
Greater Dayton Regional Transit Authority 4 S. Main Street Dayton, OH 45402 August 4, 2014 TO: Prospective Quoters RE: Request for Quotation (RFQ) 14-21 Internet Service Provider The Greater Dayton Regional
FABENS INDEPENDENT SCHOOL DISTRICT FABENS, TEXAS. REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES (CM @ Risk) FOR
FABENS INDEPENDENT SCHOOL DISTRICT FABENS, TEXAS REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES (CM @ Risk) FOR A New High School Competition Gym RFP No. 052015-036 PROPOSALS ARE DUE 10:00
The AIA B 141-1997 Standard Form of Agreement between the Owner and Architect is hereby amended as follows:
AMENDMENT A to AIA B 141-1997 between the Owner, Colorado College, and Architect (Firm s name) with Standard Form of Architect s Services made as of (Contract date). PROJECT: (Project name) The numbering
Attn: Tracy Atkinson, Chief Officer Flint, MI
CITY OF FLINT DEPARTMENT OF COMMUNITY AND ECONOMIC DEVELOPMENT REQUEST FOR PROPOSALS HUD PROGRAMS PAYMENT PROCESSING AND COMPLIANCE AND PERFORMANCE MONITORING SERVICES July 28, 2014 I. Key Dates and Information
Construction Management At-Risk
Oconee County Schools P.O. Box 146, 34 School Street Watkinsville, GA 30677 706-769-5130 706-769-3513 REQUEST FOR PROPOSALS ISSUE DATE: March 10, 2016 RFP REF: Construction Management At-Risk Construction
NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES www.nicet.org 888-476-4238. Fire Alarm Systems
Fire Alarm Systems Level IV Content Outline Standard Model/CBT The skills and knowledge listed under each task are suggestive of those involved in that task, but are not intended to constitute an exhaustive
REQUEST FOR PROPOSALS FOR DISASTER RECOVERY ADMINISTRATIVE SERVICES
REQUEST FOR PROPOSALS FOR DISASTER RECOVERY ADMINISTRATIVE SERVICES Notice is hereby given that the Santa Rosa County Board of County Commissioners is calling for and requesting proposals from qualified
APPENDIX D CONTRACTUAL AGREEMENT (Sample) THE GOVERNMENT OF SASKATCHEWAN as represented by the Minister of Energy and Resources
APPENDIX D CONTRACTUAL AGREEMENT (Sample) THIS AGREEMENT made in duplicate, BETWEEN: THE GOVERNMENT OF SASKATCHEWAN as represented by the Minister of Energy and Resources (Hereinafter referred to as the
Agreement Number: F.E.I.D. Number: Procurement Number: D.M.S. Catalog Class Number:
Page 1 of 9 Agreement Number: F.E.I.D. Number: Procurement Number: D.M.S. Catalog Class Number: This Master University Agreement ( Agreement ), entered into this day of, ( Effective Date ), between the
PROJECT CLOSEOUT PROCESS & PROCEDURES
PROJECT CLOSEOUT PROCESS & PROCEDURES MARY HENDERSON-REPS, CONTRACT ADMINISTRATOR DENVER INTERNATIONAL AIRPORT FEBRUARY, 2016 CLOSEOUT PROCESS - Closeout is defined as being The period that represents
PROFESSIONAL/CONSULTING SERVICES AGREEMENT
This SERVICES AGREEMENT ( Agreement ) is entered into by and between the undersigned, ( Contractor ), (Social Security Number or Federal I.D. No.), located at and Texas Southern University ( TSU ), an
REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES
REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES Big Rapids Public Schools Building Program 2005 OWNER Big Rapids Public Schools 21034 15-Mile Road Big Rapids, Michigan 49307 PHONE: (231) 796-2627
HURRICANE PROTECTION AND SEVERE WEATHER PLAN INFORMAL REQUEST FOR PROPOSALS FOR NEW HANOVER COUNTY EMERGENCY MANAGEMENT
HURRICANE PROTECTION AND SEVERE WEATHER PLAN INFORMAL REQUEST FOR PROPOSALS FOR NEW HANOVER COUNTY EMERGENCY MANAGEMENT Proposals will be received in the New Hanover County Finance, 230 Government Center
COUNTY OF DUTCHESS OFFICE OF CENTRAL AND INFORMATION SERVICES DIVISION OF CENTRAL SERVICES 27 HIGH STREET POUGHKEEPSIE, NEW YORK 12601 (845) 486-3670
COUNTY OF DUTCHESS OFFICE OF CENTRAL AND INFORMATION SERVICES DIVISION OF CENTRAL SERVICES 27 HIGH STREET POUGHKEEPSIE, NEW YORK 12601 (845) 486-3670 The Division of Central Services has developed this
Adrian Public Schools
Adrian Public Schools A. Instructions REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES PART 1 -- GENERAL INSTRUCTIONS Qualified firms are invited to submit proposals to Adrian Public Schools (the
LOUISIANA CAPITAL IMPROVEMENT PROJECTS PROCEDURE MANUAL FOR DESIGN AND CONSTRUCTION
LOUISIANA CAPITAL IMPROVEMENT PROJECTS PROCEDURE MANUAL FOR DESIGN AND CONSTRUCTION 1985 Edition INCLUDING ADDENDA ONE AND TWO M.J. AMike@ Foster, Jr. Governor Mark C. Drennen, Commissioner of Administration